H. G. Christman Co. v. Michigan Gypsum Co.

85 F.2d 474, 1936 U.S. App. LEXIS 4150
CourtCourt of Appeals for the Eighth Circuit
DecidedSeptember 11, 1936
DocketNo. 10581
StatusPublished
Cited by6 cases

This text of 85 F.2d 474 (H. G. Christman Co. v. Michigan Gypsum Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. G. Christman Co. v. Michigan Gypsum Co., 85 F.2d 474, 1936 U.S. App. LEXIS 4150 (8th Cir. 1936).

Opinion

SANBORN, Circuit Judge.

This controversy arises out of the construction of the United States Veterans’ Hospital at Des Moines, Iowa. The action was one to recover on a bond given by the American Employers Insurance Company, as surety, to secure the performance of the construction contract, as provided by the Heard Act (Act of August 13, 1894, 28 Stat. 278, as amended, Act of February 24, [475]*4751905, 33 Stat. 811, and March 3, 1911, 36 Stat. 1167, 40 U.S.C.A. § 270). The bond was conditioned upon the satisfactory performance of the contract and the payment by the contractor for labor and material furnished for the construction. The appellants are the contractor and its surety, The appellees are materialmen who intervened in the action. The case was tried to the court without a jury, and judgments were entered in favor of the appellees, from which the contractor and his surety have appealed.

In authorizing suit on a bond such as this, the Heard Act provides: “If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and materials shall * * * have a right of action * * * Provided, That * * * jt * * * shall be commenced within one year after the performanee and final settlement of said contract, and not later.”

This action was commenced on March 22, 1934. The complaint alleged, and the appellees contended, that “final settlement” of the contract was made on August 21, 1933. The appellants, on the other hand, claimed that the date of “final settlement” was February 1, 1934, and that therefore the action was premature. The trial court determined that “final settlement” was made August 21, 1933, as contended by the appellees.

By the terms of its contract with the government, the contractor was to complete the building within 250 days, after July 9, 1932. The. contract provided for liquidated damages in case of delay, but also provided for the granting of extensions of time for completion of the work, under certain conditions. The work pro-grossed, with short interruptions due to a strike and to severe weather conditions, until February 24, 1933, at which time the contractor was forced to stop work for lack of funds due to the closing on February 21, 1933, of 'the Citizens’ National Bank of South Bend, Ind. Shortly thereafter, the contractor’s right to continue the work was terminated by the government, and the surety undertook the completion of the work on April 13, 1933.

Before the surety took over the construction work, it received a letter, dated April 1, 1933, from the Chief, Administrative Division, Construction Service of the Veterans’ Administration, reading in part as follows: “As the contract work performed by you progresses, payments will be made as provided for in the contract, The vouchers for the work performed by you will be drawn in favor of the American Employers’ Insurance Company, surety for H. G. Christman Company. The first voucher prepared will be entitled, ‘First Payment to the Surety.’ These vouchers will be prepared by the Superintendent of Construction at Des Moines and will include only the work performed and materials furnished by you. The vouchers, when certified by your representative at Des Moines and by the Superintendent, will be forwarded to this office atl(b when approved, payment will be made hy the Disbursing Officer of the Veterans’ Administration in Washington. In this connection attention is invited to the fact that the funds to be made available for your use in the completion of this work wil include the value of work still to be performed and the amount of the voucher ^or February work, which was delivered your Washington representative yesterday, making a total of $127,714.59. The unpaid balance of the value of work and materials furnished by H. G Christman Company prior to March 7, 1933 amounts to $82 861.44. This balance will be re-tamed by the Government until the work ^ completed, after which the Comptroller General will decide as to its disposition,

On August 11, 1933, the Director of Construction wrote the Veterans’ Administration that, in his opinion, liquidated damages should not be charged for 47 days’ delay caused by the closing of the bank, The Assistant Administrator indorsed his approval August 29, 1933. On August 16, 1933, the Director of Construction wrote Ike surety that the delay of 47 days caused by the closing of the bank in which the contractor’s funds were deposited was “a delay due to unforeseeable causes beyond your control and without your fault or negligence.

On August 17, 1933, the surety forwarded to the Veterans’ Administration a voucher for the final payment in the sum 0f $32,591.36, and another voucher which called for the unpaid balance due the contractor (retained percentages) amounting to $81,230.64. The latter voucher was accompanied by an assignment of the contractor’s rights to the funds called for. Each of these vouchers contained the re[476]*476cital, “Work was completed June 22, 1933,” and bore the signature of the Director of Construction; and each was approved by the “Chief, Administrative Division, Construction Service,” of the Veterans’ Administration for payment of the amount claimed in the voucher.

The Director of Construction, on August 21, 1933, made his report to the Assistant Administrator of the Veterans’ Administration, stating: “The work mentioned above having been completed by the contractor and its surety, the following is submitted as the basis for settlement:” Then' follows a detailed statement of the basis proposed, showing $32,591.36 as the unpaid balance due the surety as a final payment for the work done and materials furnished by it, and $81,230.64 as the unpaid balance due the contractor. The report concludes thus:

“Final inspection report dated July 6, 1933, states that all work was completed in accordance with the drawings and specifications on June 22, 1933. It is, therefore, recommended that the work be accepted, that settlement on the above basis be approved, that the payment of voucher, in amount $32,591.36 in favor of the American Employers Insurance Company (Surety for H. G. Christman Company) be authorized and that the voucher, in amount $81,-230.64, in favor of the H. G. Christman Company be forwarded to the General Accounting Office for direct settlement.
“Your approval in duplicate is requested.-
“L. H. Tripp.”

The Assistant Administrator indorsed, his approval on the report as follows: “Approved August 21, 1933. George E. Ijams,' Assistant Administrator.”

On or about August 29, 1933, the Veterans’ Administration referred each of the claims represented by the vouchers to the General Accounting Office by separate written “references of claims.” The- “reference” of the claim represented by the voucher calling for the final payment of $32,591.36 to the surety, after describing the nature of the claim, stated that, “In view of the foregoing, claim is approved in the amount as vouchered,” and, “The accompanying account in the amount stated above has been administratively examined and is forwarded to you.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
85 F.2d 474, 1936 U.S. App. LEXIS 4150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-g-christman-co-v-michigan-gypsum-co-ca8-1936.