Lambert Lumber Co. v. Jones Engineering & Construction Co.

47 F.2d 74, 1931 U.S. App. LEXIS 3391
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 2, 1931
Docket8875
StatusPublished
Cited by17 cases

This text of 47 F.2d 74 (Lambert Lumber Co. v. Jones Engineering & Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lambert Lumber Co. v. Jones Engineering & Construction Co., 47 F.2d 74, 1931 U.S. App. LEXIS 3391 (8th Cir. 1931).

Opinion

KENYON, Circuit Judge.

Appellant furnished material to the Jones Engineering & Construction Company to be used in the performance of a contract for the construction of a government hospital at Excelsior Springs, Mo. It sought on March 15, 1926, to intervene in an action brought by another contractor under section 270, title 40, chapter 3, USCA, against the Jones Engineering & Construction Company and the sureties on its bond.

A jury was waived in writing. The trial court held that the intervention was not in time, as it was attempted over a year after the work was performed and final settlement made between the government and the contractor, and dismissed intervener’s petition.

Findings of fact were made by the court, i. e., that the bond contemplated under section 270 (40 USCA) was duly given; that inter-vener furnished the materials to the contractor, as claimed, and is entitled to recover, if its intervention was in time; that an original contract and a supplemental contract had been entered into; that suit was originally filed upon the bond by another company, which was dismissed but afterwards reinstated to permit intervention; that the work undertaken by the contractor was completed more than one year before intervention; that material had been furnished by intervener both for the original contract and the supplemental contract; but that it was unnecessary to separate the liability of the several sureties. We quote certain of the findings:

“5. The contract in question specifically provided that:
“ ‘The work * * * shall be done under the jurisdiction and control of the Chief of tho Bureau of Yards and Docks, Navy Department, or such representative as he may designate.’
“Relative to payment under the contract, it was provided that tho contractor ‘shall be paid, * * * upon vouchers prepared
and certified by the Bureau of Yards and Docks, Navy Department, and approved by the Director, U. S. Veterans’ Bureau.’
“7. In the matter of final settlement the evidence showed and the Court finds that on February 20,1925, the Government procured a release from the contractor which contained the following recitals:
“ ‘Whereas, by provisions of the contract dated September 20, 1923, by and between Jones Engineering and: Construction Company, Inc., a corporation of the Stale of Nebraska, party of the first part, and the United States, a party of the second part, for the construction of a ward and subsistence building, at the U. S. Veterans’ Hospital, Excelsior Springs, Missouri, it is contemplated that final settlement therefor shall not be made until the party of the first part shall have executed and delivered a final release of all claims or demands growing out of the eon-tract ; and
“ ‘Whereas all the conditions, covenants and provisions of the said contract as modified liave been performed and fulfilled by and on the part of the party of the first part;
“ ‘Now, therefore, in consideration of tho premises and of tho sum of ten thousand nine hundred seventy-five and 39/100 ($10975.39) dollars, lawful money of the United States, being the full and entire sum due upon the completion of the work, as aforesaid, to the said party of the first part in hand paid by the said party of the second part, the receipt of which is hereby acknowledged, the said party of the first part does hereby remise, release, and forever discharge the said party of the second part of and from any and all *76 manner of actions, suits, debts, dues, sums and sums of money, accounts, reckonings, bonds, bills, covenants, controversies, agreements, promises, claims, and demands whatsoever in law or in equity that the said party of the first part has or may have for or on account of or in connection with the contract aforesaid, as modified by Changes A and B and Supplemental Agreement.’ ”
“8. This'release was the culmination of correspondence between the proper department of the Government and the contractor. Under the contract, the work should have been completed on or before September 3, 1924. It was actually completed September 20,1924. Because of this delay of seventeen days the Government deducted for liquidated damages $50.00 a day or a total of $850.00 from the contract price. After such deduction was. made a balance of $10,975.39 was determined. A voucher for said sum was approved by each and every department interested in the construction, as provided by the contract, on the day the release was executed, to-wit, February 20, 1925, save the approval of L. E. Gregory, Chief of the Bureau of Yards and Docks, was noted upon the voucher as of March 2, 1925.”
“10. After this was done, the voucher was sent to the general accounting office of the Government, accompanied by the following letter:
“United States Veterans’ Bureau Claim
Reference to General Accounting Office Treasury Division.’
-19—
“Examined in the sum of $10,975.39 and respectfully referred to the General Accounting Office for examination, settlement and approve for payment in the amount found due to Jones Engineering & Construction Co., Inc., e/o Chief, Bureau Yds. & Docks, Navy Dept. Washington, D. C. from the appropria/-t-ions stated below:
“ ‘Hospital Facilities & Services, Veterans’ Bureau’
“Letter dated May 22,1924, extended the contract time 23 calendar days because of abnormal weather conditions. In view of recent suspensions, because time extensions were given for similar reasons, the voucher is forwarded for direct settlement.
“Frank T. Hines, Director.”
“11. On April 2, 1925, the Comptroller General of the general accounting office eej’-tified that he had ‘examined and settled the claim of Jones Engineering and Construction Company for final payment.’
“If the settlement was made on April 2, 1925, as certified by the Comptroller General of the general accounting office, then the in-tervener is entitled to recover because its claim was filed by its intervention on March 15, 1926, which was less than one year after final settlement. If the final settlement was made on March 2, 1925, the date on which the voucher in final settlement was approved by the departmental representatives mentioned in the contract, then intervener is not entitled to recover because its intervention was more than one year after final settlement.”
“12. The Court finds that final settlement occurred prior to March 15, 1925, and that the intervention herein was filed more than one year after the date of final settlement and that therefore intervener cannot recover.”

The trial court filed an opinion pointing out that the only question was the time of final settlement, and stated that the litigants were in agreement that “a ‘final settlement’ is • when the government finally determines according to administrative methods what amount it is willing to pay to the contractor.” It relied on Illinois Surety Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. St. Louis Clay Products Co.
68 F. Supp. 902 (E.D. Missouri, 1946)
Great Lakes Const. Co. v. Republic Creosoting Co.
139 F.2d 456 (Eighth Circuit, 1943)
Doehler Metal Furniture Co. v. Warren
129 F.2d 43 (D.C. Circuit, 1942)
State Farm Mut. Automobile Ins. Co. v. Bonacci
111 F.2d 412 (Eighth Circuit, 1940)
Gezina v. Riggins
89 F.2d 300 (Fourth Circuit, 1937)
Wellston Trust Co. v. Snyder
87 F.2d 44 (Eighth Circuit, 1937)
H. G. Christman Co. v. Michigan Gypsum Co.
85 F.2d 474 (Eighth Circuit, 1936)
Standard Transp. Co. v. Wood Towing Corp.
64 F.2d 282 (Fourth Circuit, 1933)
United States Fidelity & Guaranty Co. v. Yeilding Bros.
143 So. 176 (Supreme Court of Alabama, 1932)
Consolidated Indemnity & Ins. Co. v. WA Smoot & Co.
57 F.2d 995 (Fourth Circuit, 1932)
First Nat. Bank of Ortonville, Minn. v. Andresen
57 F.2d 17 (Eighth Circuit, 1932)
Arundel Corp. v. Wathen
55 F.2d 228 (Fourth Circuit, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
47 F.2d 74, 1931 U.S. App. LEXIS 3391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lambert-lumber-co-v-jones-engineering-construction-co-ca8-1931.