United States ex rel. Brown-Ketcham Iron Works v. Robinson

214 F. 38, 130 C.C.A. 432, 1914 U.S. App. LEXIS 1101
CourtCourt of Appeals for the Second Circuit
DecidedApril 7, 1914
DocketNo. 211
StatusPublished
Cited by20 cases

This text of 214 F. 38 (United States ex rel. Brown-Ketcham Iron Works v. Robinson) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Brown-Ketcham Iron Works v. Robinson, 214 F. 38, 130 C.C.A. 432, 1914 U.S. App. LEXIS 1101 (2d Cir. 1914).

Opinion

LACOMBE, Circuit Judge.

.[1] The sole question to be determined here is the meaning of the phrase “final settlement of the contract” between the original contractor and the government. Does it mean that all outstanding controversies between the government and the contractor arising out of the contract must be finally determined ? Or is it sufficient if the government has officially indicated that it intends to make no effort to collect anything further from the contractor or from the bond? The statute is awkwardly and inartificially expressed, but it seems to us it may be easily construed by applying the well-recognized rule of ascertaining first what was the difficulty to remedy which the statute was passed and second what was the method adopted to remedy such difficulty.

Under the old act, the United States was exposed to a loss of the security it had provided to secure a proper execution of the contracts it had let, in cases where the contractor became insolvent. Subcontractors and materialmen, sometimes before the work was even near completion, could proceed independently to secure their pay out of the proceeds of the bond, thereby reducing it to such an extent that the government might get nothing. Manifestly this was improvident legislation and it was undoubtedly to remedy this difficulty that the act was passed. The new act provided in the first place that suit to enforce the bond should be brought by the United States and material-men be allowed merely to intervene in that suit. There might, of course, be instances where the government, making no claim against its contractor to recover damages would bring no suit on the bond. In that case the new act provides that the materialmen may themselves bring such suit. These provisions deal more particularly with the practice.

The more important part of the new act is found in the clauses which provide in substance that no materialman shall take one dollar out of the fund which the bond produces, until every dollar due the United States under the contract shall be fully paid. Keeping these clauses in mind, it seems to us that a reasonable interpretation of the [40]*40disputed phrase is. to be readily found. In determining the- time when materialmen may begin suit, it would not do to fix it at some day “after complete performance” merely. Defective work, damages for .delay, and other matters might give the United States some claim which it might not decide to prosecute until some time after the work was turned over, apparently complete. The date was, therefore, fixed relatively to “complete performance of the contract and final settlement thereof!’ We take it that these italicized words refer to the time when the proper government officer, who has the final discretion in such matters, after examination of the facts, satisfies himself that the government will accept the work, as it is, without making any claim against the contractor for unfinished or imperfect work, damages for delay or what not, and records that decision in some orderly way. Six months after that date, materialmen may begin suit. This construction protects the government against the defect of the old act, viz., that its suit to recover might prove barren, because the money is gone. We can see no reason why Congress should have provided that, when the government claims nothing from contractor or sureties, all others must wait still further until some claim of the contractor against the government for having underpaid him reaches a conclusion. Such suit can in no way affect the fund provided by the bond out of which the government might have satisfied its claim, if it had any. In other words we see no reason for holding that the final settlement must be mutual, in cases where the government makes no claim against the contractor.

Under the statute whenever the government does make claim, it will be paid first, since the act says:

“After paying the full amount due the United States, the remamder shall be distributed pro fata,” etc.

The time fixed by the statute for beginning a subcontractor’s suit is any time within the period extending from six months after completion and final settlement to one year after completion and final settlement.

Referring to the referee’s report, we find a letter of the supervising architect to the Secretary of the Treasury March 13, 1908, and a supplementary letter July 1, 1908, recommending final settlement on the basis of deducting from the 15 per cent, held up on periodical payments a certain sum for overtime damages and other sums to cover omissions, defects, and unfinished items. Since the amount retained exceeds the aggregate of these sums, the proposed settlement contemplated the payment of a balance of some $5,000 to the contractor. This was approved in writing by the Secretary of the Treasury on February 10, 1909, and was a final statement by the head of the department that the contract had been completed to the satisfaction of the government and that after paying over the $5,000 it had no claim to make against the contractor or his surety.

There are decisions, no doubt, to the effect that the United States may repudiate such action by its officers, when a private party could not, and that no lapse of time or laches can bind it; but Congress was not legislating with regard to any such unusual or abnormal cases. [41]*41What it had in mind was such a determination as to its rights, by the proper govérnment officers, as might fairly be taken by all persons interested as an authoritative announcement that the government was not a claimant to any part of the proceeds of the bond. When such a determination has been made and six months has elapsed thereafter, then the others interested in the fund may bring their suit. Such a construction does not expose a government to risk of loss. Even after a creditor’s action is brought the United States may bring an action in its own name on the bond, if it thinks its officers acted improvidently and that it has some claim of its own against the contractor. If it should bring such,action, there would be no ascertainable “remainder” available for creditors until after such action was disposed of; and if the government prevailed in such action there might in some cases be no “remainder” at all.

'This suit was begun October 15,. 1909, more than six months and less than a year after February 10, 1909, the date when the Secretary of the Treasury recorded the fact that the government had no claim to make on the bond. This was within the statutory period, and the judgment of dismissal must be reversed, except as to one of the defendants. This defendant is J. F. Yawger, as receiver of the Metropolitan Surety Company one of the sureties on the bond. That company was dissolved and permanent receiver appointed by final decree of the state court on January 30, 1909, more than six months before plaintiffs’ causes of action accrued. The referee held that the plaintiffs have no claim against the receiver or upon the funds with which he has been intrusted by the state court for distribution among the creditors of the surety company, under the authority of People v. Metropolitan Surety Co., 205 N. Y. 135, 98 N. E. 412, Ann. Cas. 1913D, 1180. No one seems to dispute the correctness of this ruling. As to Yawger, receiver, therefore, the judgment is affirmed'; as to the other defendants, it is reversed.

NOTE.

The text of the act construed in the above opinion is as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. McBride v. Campbell Bldg. Co.
77 P.2d 341 (Utah Supreme Court, 1938)
Kirkpatrick v. Douglas
65 P.2d 1169 (Montana Supreme Court, 1937)
Campbell Bldg. Co. v. District Court of Millard County
63 P.2d 255 (Utah Supreme Court, 1936)
Territory of Hawaii Ex Rel. Kahului Railroad v. Mellor
33 Haw. 523 (Hawaii Supreme Court, 1935)
Consolidated Indemnity & Ins. Co. v. WA Smoot & Co.
57 F.2d 995 (Fourth Circuit, 1932)
New York Indemnity Co. v. Niven
133 So. 261 (Supreme Court of Alabama, 1931)
United States v. Starr
20 F.2d 803 (Fourth Circuit, 1927)
Antrim Lumber Co. v. Hannan
18 F.2d 548 (Eighth Circuit, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
214 F. 38, 130 C.C.A. 432, 1914 U.S. App. LEXIS 1101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-brown-ketcham-iron-works-v-robinson-ca2-1914.