United States ex rel. Crellin v. George F. Pawling & Co.

297 F. 65, 1924 U.S. App. LEXIS 2770
CourtCourt of Appeals for the Third Circuit
DecidedMarch 1, 1924
DocketNo. 3023
StatusPublished
Cited by3 cases

This text of 297 F. 65 (United States ex rel. Crellin v. George F. Pawling & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Crellin v. George F. Pawling & Co., 297 F. 65, 1924 U.S. App. LEXIS 2770 (3d Cir. 1924).

Opinion

DAVIS, Circuit Judge.

The District Judge who’heard this case without a jury held that' the plaintiffs below- and plaintiffs in error here, instituted this action before it could be legally commenced under the Act of 1894 ( 28 Stat. 278) as amended in 1905 (33 Stat. 811 [Comp. St. § 6923]), pursuant to which it was brought, and accordingly entered judgment against them. The defendants George F Paw-ling & Company, on or about September 26, 1918, entered into a contract with the United States for the construction of a seaplane hangar at the Navy Yard at Philadelphia, Pa. On the same day, George F. Pawling & Co., as principal, and George F. Pawling and John Wilde, as sureties, executed a bond to the United States in the sum of $61,-781.10 for the faithful performance of the contract and for the payment “to all persons supplying it [the contractor] labor and materials in the prosecution of the work provided .for in the aforesaid contract.”

On October 3. 1918, the use plaintiffs, a copartnership, doing business as the Pittsburgh-Des Moines Steel Company entered into a contract with the defendant to furnish all the structural steel for the hangar for the sum of $74,302.86. The contract between the defendant and the United States was fully performed, and the contractor was paid. The contractor, however, it is alleged, failed, to pay the use plaintiffs a balance of $14,929.72 on the structural steel, and they brought suit for that amount on March 7, 1921. Under the act as amended in 1905, the United States alone may bring suit any time [67]*67within six months after the complete performance and final settlement of the contract against the contractor for any claim it may have against him. Creditors of the contractor who supplied him with labor or materials may intervene and have their rights and claims adjudicated in that suit. If the United States, however, does not bring suit within six months, the creditors themselves, as use plaintiffs, may commence action, provided “that where suit is instituted by any of such creditors on the bond of the contractor it shall not be commenced until six months after the complete performance of said cohtract and final settlement thereof, and shall be commenced within one year after the performance and final settlement of said contract, and not later.” It is admitted that the work was completed July 24, 1919. The controversy arises over the date of the “final settlement” of the contract.

The plaintiffs contend that “final settlement” was made on August 28, 1920, and the defendant on December 5, 1919, but the learned trial judge found that it was made on September 15, 1920. If he is right, the suit was instituted eight days too soon; but if the defendants are right- it was begun three months and two days too late. The sole question, therefore, is the date when “final settlement” was made.

There is no dispute about the facts in this case. They are perfectly clear. Some time prior to August 28, 1920, every question as to the account between the contractor and the United States had been determined except the difference between them as to the amount of liquidated damages for which the contractor was liable on account of the delay'' in completing the work. That amount was agreed upon, in April, 1920, and a final settlement voucher was directed to be prepared. But, owing to a difference in the figures, through clerical errors or otherwise, as to the amount of tire allowance at the Navy Yard in Philadelphia and in the Department of the Bureau of Yards and Docks at Washington, the voucher was not prepared. This difference was the subject, of further calculation and adjustment by correspondence between the public works officer in charge of the work at Philadelphia and the chief of the Bureau of Yards and Docks at Washington, who had authority to make “final settlement” of the contract. Finally this matter was settled on August 28, 1920, in a letter from C. W. Parks, who was then the chief of the Bureau of Yards and Docks, to the public works officer. A voucher in accordance with this final determination was prepared on September 2, 1920, and approved by the defendants on the same day. It was forwarded to the Bureau of Yards and Docks and approved by the chief on September 15, 1920, and was paid on September 27, 1920.

As above stated, the defendants contend that the date of final settlement was made on December 5, 1919, when the contractor was paid about 80 per cent, of the amount due him; but this cannot be the date of final settlement, because the damages for delay had not at that time been determined, and it was then impossible to fix the amount due the contractor on final settlement. Was the final settlement of contract made on August 28, September 2, or September 15, 1920?

The purpose of the act was to secure priority to. the United States, and thereafter to secure payment to persons who had supplied labor or materials in the prosecution of the work covered by the con[68]*68tract. The provision of the act was a beneficent one for the subcontractor. A contract in which a corporation or person for profit had undertaken to insure the obligee against a failure of performance on the part of the principal obligor should be liberally construed, and not according to the rule of strictissimi juris. Guaranty Co. v. Pressed Brick Co., 191 U. S. 416, 426, 24 Sup. Ct. 142, 48 L. Ed. 242; Illinois Surety Co. v. John Davis Company et al., 244 U. S. 376, 37 Sup. Ct. 614, 61 L. Ed. 1206; Brogan v. National Surety Co., 246 U. S. 257, 38 Sup. Ct. 250, 62 L. Ed. 703, L. R. A. 1918D, 776.

This case ultimately turns upon the meaning of “final settlement.” The Circuit Court of Appeals of the Second Circuit in the case of United States v. Robinson et al., 214 Fed. 38, 130 C. C. A. 432, said:

“We take it that these italicized words [“final settlement”] refer to the time when the proper government officer, who has the final discretion in such matters,-after examination of the facts, satisfies himself that the government will accept the work, as it is, without making any claim against the contractor for unfinished or imperfect work, damages for delay or what not, oand records that decision in some orderly way.”

It is admitted that the chief of the Bureau of Yards and Docks was the government officer who had the final discretion to accept the work as completed without making further claims against the contractor for unfinished or imperfect work. Was the letter of August 28, 1920, which adjusted the amount of liquidated damages and finally fixed the amount for which the voucher was subsequently drawn and paid, an orderly record of that fact? In the case of Illinois Surety Co. v. Peeler, 240 U. S. 214, 36 Sup. Ct. 321, 60 L. Ed. 609, the Supreme Court in defining “final settlement” used many expressions which greatly illumine the facts in this case. The time allowed for the government to bring suit in that case began to run “when the contract 'had been completed and the government in its final adjustment and settlement according to established administrative methods' had determined what amount, if any, was due.” Final settlement, therefore, is the determination by administrative methods of what amount is due.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Territory of Hawaii Ex Rel. Kahului Railroad v. Mellor
33 Haw. 523 (Hawaii Supreme Court, 1935)
Community Bldg. Co. v. Maryland Casualty Co.
8 F.2d 678 (Ninth Circuit, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
297 F. 65, 1924 U.S. App. LEXIS 2770, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-crellin-v-george-f-pawling-co-ca3-1924.