National Surety Corp. v. Reynolds

87 F.2d 865, 1937 U.S. App. LEXIS 2602
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 12, 1937
DocketNo. 10706
StatusPublished
Cited by3 cases

This text of 87 F.2d 865 (National Surety Corp. v. Reynolds) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Corp. v. Reynolds, 87 F.2d 865, 1937 U.S. App. LEXIS 2602 (8th Cir. 1937).

Opinion

SANBORN, Circuit Judge.

Wm. A. Riley Construction Company (hereinafter called the contractor) on November 15, 1932, entered into a written contract with the United States to build certain noncommissioned officers’ quarters at Jefferson Barracks, Mo. The National Surety Company executed the bond required to insure the performance of the contract and payment for labor and materials. The National Surety Corporation (hereinafter called the surety) later assumed this obligation of the National Surety Company. The contractor sublet the plumbing and heating to D. H. Reynolds. The buildings were completed July 17, 1933. On July 21, 1933, Major Schoenfeld, the Constructing Quartermaster, wrote to the Commanding Officer at Jefferson Barracks, as follows:

"Subject: Transfer of four double sets
N.C.O. quarters.
“To: The Commanding Officer, Jefferson Barracks, Mo.
“1. All terms of Contract No. W 430 qm-682 [the contract in suit], for the construction of four double sets of N.C.O. quarters at this station, have been complied with and work completed in a satisfactory manner.
“2. In compliance with paragraph 19, A.R. 30-1435, this work is hereby transferred to your headquarters effective this date.
“3. Written acceptance is requested.
“F. Schoenfeld,
“Major QM Corps Quartermaster.”

On July 22, 1933, Major Schoenfeld sent the following letter to Captain Gray, the Finance Officer in St. Louis:

“Subject: Final Payment Contract No.
W430 qm-682
“To: The Finance Officer, U.S. Army, 2nd. and Arsenal Sts., St. Louis, Missouri.
“1. Transmitted herewith, for final payment, estimate under -contract for construction of four double sets Non-Commissioned Officers Quarters, is submitted for .payment, approved in the amount of Three Thousand Nine Hundred Fifty Six Dollars and Seventy-Five Cents ($3956.-75).
“2. Liquidated Damages in the amount of One Hundred Fifty Dollars and no/100 Cents has been deducted.
“Fredk Schoenfeld [Signature] “Frederick Schoenfeld “Major QM Corps “Constructing Quartermaster.”
The estimate transmitted was that of the contractor “for completed work.” It showed that the total price, plus extras, was $53,780.85; that previous payments amounted to $49,674.10, and liquidated damages to $150, leaving a balance due the contractor of $3,956.75.
Accompanying the estimate was a statement, approved by Major Schoenfeld, entitled, “Final Payment To Contractor.” It identified the contract, showed that the contractor was the Wm. A. Riley Construction Company, and recited:
$53,780.85 Contract Total. Total Completion.......... $53,780.85
Less Previous Payments.... 49,674.10
4,106.75
Less Liquidated Damages.. 150.00 Amount of.Final Payment.. $ 3,956.75
?{? sjc %
Contract completed July 17, 1933.

Major Schoenfeld’s letter, with the accompanying documents, was received by Captain Gray, the Finance Officer, July 24, 1933. Apparently at his verbal request or that of one of his clerks, the Major wrote him on July 26, 1933, as follows:

“Subject: Completion date, Contract No.
W 430 qm-682.
“To: The Finance Officer, U.S. Army, 2nd ' and Arsenal Sts., St. Louis, Missouri.
“1. Contract No. W 430 qm-682, with the Wm. A. Riley Construction Company, of University City, Missouri, for the con-

[867]*867struction of four double sets of Non-commissioned Officers Quarters at this station, was successfully completed on July 17, 1933.

“F. Schoenfeld [Signature]
“F. Schoenfeld
“Major QM Corps
“Constructing Quartermaster.”

This letter was received by. Captain Gray on the day it was written. Captain Gray issued a voucher which bears date July 25, 1933, and which contains the following recitals:

“The United States, Dr. To Wm. A. Riley Construction Company, * * *
Dollars Cts.
Per detailed bill herewith #876 4,106 75 Less liquidated damages
15 days at $10.00 per day.... 150 00
3,956 75
$ % ifc % íjí
Contract completed July 17, 1933.
Final.
Total, 3,956 75
i(L ifc jjc
“Paid by Check No. 23742, dated Jul. 26, 1933 for $3956.75 on Treasurer of the United States in favor of payee named above.”

The voucher above referred to and the check in payment thereof were released on July 26, 1933.

On July 24, 1934, Reynolds, the subcontractor, intervened in an action brought upon the bond under the Heard Act (Act of August 13, 1894, 28 Stat. 278, as amended, Act of February 24, 1905, 33 Stat. 811, and March 3, 1911, 36 Stat. 1167, § 291, 40 U.S.C.A. § 270), which provided: “If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and materials shall * * * have a right of action * * * Provided, That * * * it * * * shall be commenced within one year after the performance and final settlement of said contract, and not later.”

Reynolds alleged in his complaint in intervention that there was a balance due him for labor and material furnished, and that final settlement of the contract took place on July 26, 1933, the day when Captain Gray released the voucher and check. The surety, on the other hand, asserted that final settlement of the contract was made on July 22, 1933, when the Constructing Quartermaster determined that the contract was completed and that final payment was due.

At the trial, the surety moved for a directed verdict, on the ground that the suit was brought too late. The trial court denied this motion, and submitted to the jury the question whether the action of Captain Gray on July 26, 1933, constituted final settlement. The jury found for the intervener. From the judgment entered on the verdict, this appeal is taken.

“The term ‘final settlement,’ as used in the act, was not intended to denote payment, but was used to describe an administrative determination of the amount due upon completion of the contract. Illinois Surety Co. v. United States to Use of Peeler, 240 U.S. 214, 36 S.Ct. 321, 60 L. Ed. 609; Globe Indemnity Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
87 F.2d 865, 1937 U.S. App. LEXIS 2602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-corp-v-reynolds-ca8-1937.