Pittsburgh Plate Glass Co. v. Dahm

271 A.2d 55, 159 Conn. 563, 1970 Conn. LEXIS 503
CourtSupreme Court of Connecticut
DecidedJune 29, 1970
StatusPublished
Cited by11 cases

This text of 271 A.2d 55 (Pittsburgh Plate Glass Co. v. Dahm) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittsburgh Plate Glass Co. v. Dahm, 271 A.2d 55, 159 Conn. 563, 1970 Conn. LEXIS 503 (Colo. 1970).

Opinion

Alcorn, C. J.

In 1962 the defendant Douglas E. Dahm, hereinafter referred to as Dahm, contracted with the department of public works to construct a building for the American School for the Deaf in West Hartford. Since the contract price exceeded $1000 and was for the construction of a public building, Dahm gave a bond with the defendant Continental Casualty Company, hereinafter referred to as Continental, as surety for the protection of persons supplying labor and material in the prosecution of the work as required by §49-41 of the General Statutes. The plaintiff Pittsburgh Plate Glass Com *565 pany, hereinafter referred to as Pittsburgh, as a subcontractor to Dahm, sold and delivered building materials to him in connection with the construction of the building for which $15,544 remained unpaid. By complaint dated February 11, 1966, Pittsburgh brought suit to recover the amount due. The action was brought pursuant to § 49-42 of the General Statutes, the material part of which is quoted in the footnote. 1

Dahm was defaulted for failure to appear and, following a trial of the issues between Pittsburgh and Continental, the trial court rendered judgment in Pittsburgh’s favor. Continental has appealed from the judgment.

The statute having created the cause of action and prescribed the procedure, the mode of proceeding is mandatory and must be strictly complied with. Beach v. Trumbull, 133 Conn. 282, 289, 50 A.2d 765; *566 Scoville v. Columbia, 86 Conn. 568, 570, 86 A. 85. The principal issue on this appeal is whether the plaintiff’s action was brought within one year “after the date of final settlement of such contract” as required by § 49-42. Continental claims that the “final settlement” was on July 7,1964. Pittsburgh’s claim is that the court properly determined that the final settlement occurred on November 24,1965. Involved in these claims is a dispute over whether the court had seen fit to determine the final settlement date by the improper exercise of an administrative function.

No correction of the finding material to our determination of the appeal is required. The court found, in substance, that on July 7,1964, the department of public works, after inspection, concluded that the work which had been done met the requirements of the contract with four minor exceptions and thereupon it transferred the custody of the building to the American School for the Deaf, which became responsible for its maintenance and for insurance coverage from that date. On that date, however, there were claims outstanding between Dahm, the state, and the American School for the Deaf, principally related to amounts due Dahm under the contract and for extras. As of July 9,1964, there was no final settlement, and no determination of the final settlement date was ever made by the public works commissioner. There were many conferences concerning the conflicting claims until November, 1965, when the disputes were resolved, and on November 24, 1965, payment was made by the state and releases between the parties were executed. Both Pittsburgh and Continental requested the public works commissioner to furnish a certified statement of the date of final settlement pursuant to § 49-43 of the General Statutes, the material part of which is quoted in the *567 footnote. 2 The commissioner has never certified a final settlement date, however. Under these circumstances, the court concluded that final settlement had not occurred before November 24, 1965, so that the time within which the plaintiff was required to commence an action began to run on that date and, consequently, the action commenced on February 11, 1966, was timely.

As we have previously pointed out, the similarity between § 49-42 and the federal statute, popularly known as the Miller Act (40 U.S.C. §§ 270 a-d), makes the decisions of the federal courts relative to the latter helpful. International Harvester Co. v. L. G. DeFelice & Son, Inc., 151 Conn. 325, 333, 197 A.2d 638. There seems to be no disagreement between the parties that the term “final settlement” which appears in both the state and the federal statute does not mean final payment, “but the administrative determination by the officer having the execution of the work in charge that it has been performed and his finally fixing the amount due”; R. P. Farnsworth & Co. v. Electrical Supply Co., 112 F.2d 150, 152 (5th Cir.); United States v. Arthur Storm *568 Co., 101 F.2d 524, 526 (6th Cir.); or, as stated by the United States Supreme Court, the date of “final settlement” is the date on which “so far as the Grovernment was concerned, the amount which it was finally bound to pay or entitled to receive was fixed administratively by the proper authority”. Illinois Surety Co. v. United States, 240 U.S. 214, 221, 38 S. Ct. 321, 60 L. Ed. 609; United States Fidelity & Guaranty Co. v. United States, 65 F.2d 639, 641 (9th Cir.). It is unnecessary for us to decide whether, as claimed by the defendant, § 49-43 confers exclusive authority on an administrative authority of the state to issue a “certified statement of the date of such settlement” and that the Superior Court improperly undertook to exercise such an administrative function. It is clear that a court may not perform administrative or nonjudicial functions. Connecticut Television, Inc. v. Public Utilities Commission, 159 Conn. 317, 329, 269 A.2d 276; Adams v. Bubinow, 157 Conn. 150, 158, 251 A.2d 49. It seems quite clear, however, that if an applicant under § 49-43 were unsuccessful in obtaining a certificate from the appropriate administrative state official, he could not properly request the Superior Court to issue a certificate as to the date of final settlement. In the present case, no such request was made of the court nor did the court purport to perform any function such as that contemplated by § 49-43.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winsted Land Dvl. v. Design Collab. Arch., No. Cv-96-0071571 (Aug. 12, 1999)
1999 Conn. Super. Ct. 11167 (Connecticut Superior Court, 1999)
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
Summit Crane Co. v. Continental Metalcraft, No. Cv 93035564s (Sep. 26, 1996)
1996 Conn. Super. Ct. 5613 (Connecticut Superior Court, 1996)
Santos Foundation v. Ins. Co., N. Am., No. Cv93 0343701 (Nov. 21, 1994)
1994 Conn. Super. Ct. 11642 (Connecticut Superior Court, 1994)
Okee Industries, Inc. v. National Grange Mutual Insurance
623 A.2d 483 (Supreme Court of Connecticut, 1993)
Wickes Manufacturing Co. v. Currier Electric Co.
596 A.2d 1331 (Connecticut Appellate Court, 1991)
Beck v. Heintz
568 A.2d 466 (Connecticut Appellate Court, 1990)
Nor'easter Group, Inc. v. Colossale Concrete, Inc.
542 A.2d 692 (Supreme Court of Connecticut, 1988)
Hayes v. Smith
480 A.2d 425 (Supreme Court of Connecticut, 1984)
American Masons' Supply Co. v. F. W. Brown Co.
384 A.2d 378 (Supreme Court of Connecticut, 1978)
Baldwin-Lima-Hamilton Corporation v. Aetna Casualty & Surety Co.
307 A.2d 169 (Supreme Court of Connecticut, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
271 A.2d 55, 159 Conn. 563, 1970 Conn. LEXIS 503, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittsburgh-plate-glass-co-v-dahm-conn-1970.