American Masons' Supply Co. v. F. W. Brown Co.

384 A.2d 378, 174 Conn. 219, 1978 Conn. LEXIS 821
CourtSupreme Court of Connecticut
DecidedFebruary 7, 1978
StatusPublished
Cited by75 cases

This text of 384 A.2d 378 (American Masons' Supply Co. v. F. W. Brown Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Masons' Supply Co. v. F. W. Brown Co., 384 A.2d 378, 174 Conn. 219, 1978 Conn. LEXIS 821 (Colo. 1978).

Opinion

Cotter, J.

The plaintiff, a building materials supplier, brought this action under § 49-42 of the General Statutes, seeking reimbursement for materials alleged to have been furnished B & G Construction, Inc., hereinafter B & G, a subcontractor of F. W. Brown Company, hereinafter Brown, the general contractor which had contracted with Regional School District No. 4 for the construction of a school. Pursuant to General Statutes § 49-41 Brown furnished a bond in the amount of the contract for the protection of persons supplying labor or materials in the prosecution of the work provided for in the contract. Under the terms of the bond, the defendants, Brown, as principal, and Aetna Casualty and Surety Company, as surety, bound themselves to make payments promptly to all claimants *221 furnishing labor and material used or reasonably-required for use in the construction project. Subsequent to the execution of the contract and the furnishing of the bond, Brown entered into a subcontract with B & G to do all the site work for the entire project including the installation of drainage pipes around the exterior of the proposed building. Brown also entered into a subcontract with the Becker and Goldstein Company for the plumbing and heating work which similarly required the installation of drainage pipe in the sewage system. Becker and Goldstein, however, engaged B & G to install this drainage pipe in the sewage system required under the plumbing subcontract.

Pursuant to purchase orders issued by B & G, the plaintiff made two deliveries of poroswall pipe to the construction site and billed B & G for the materials in the amount of $3,025.10. Failing to receive payment from B & G, the plaintiff, pursuant to § 49-42, duly notified the defendants Brown and Aetna Casualty and Surety Company, and demanded payment from Brown. After the expiration of more than five months following the notification to the defendants regarding their delinquency, the plaintiff commenced the present action to recover on the bond. The court (Palmer, J.) overruled the defendants’ demurrer to the plaintiff’s complaint which alleged that suit was not commenced within the time limitation prescribed by statute, and upon trial of the matter, the court (Bracken, J.) rendered judgment for the plaintiff in the sum of $3,025.10 plus interest, and the defendants have appealed.

The defendants raise three issues on appeal: (1) The applicability of a 1969 amendment to § 49-42 *222 to this case; (2) the plaintiff’s contractual relationship as within the contemplated coverage of the payment bond required by statute (§49-42); and (3) the propriety of the trial court’s action in opening the case suo motu.

At the time of the execution of the contract and payment bond in January, 1969, and until October 1,1969, § 49-42 (b) provided that no suit on the bond “shall be commenced after the expiration of one year after the date of final settlement” of the contract. The time limit for filing suit under § 49-42 (b) was amended by 1969 Public Acts, No. 192, § 1, effective October 1, 1969, to provide that no “suit shall be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied.” The plaintiff made final delivery of the materials to the construction site on May 5, 1969; it provided notice of the delivery and demanded payment from the defendant Brown on July 3, 1969; and suit was filed on February 9, 1971. The defendants, by letter sent to the trial court and at oral argument, conceded that the present action was commenced within one year of final settlement as required under the provisions of § 49-42 (b) as it existed prior to the effective date of Public Act No. 192. The defendants argue, however, that the 1969 statutory amendment applies and operates as a bar to the plaintiff’s action because suit was not commenced until almost twenty months after the plaintiff’s final delivery of the materials.

This court has consistently expressed its reluctance to construe statutes as having retroactive application. East Village Associates, Inc. v. Monroe, 173 Conn. 328, 332, 377 A.2d 1092. A statute *223 “affecting substantial changes in the law” is not to be given a retrospective effect unless it clearly and unequivocally appears that such was the legislative intent. State ex rel. Rundbaken v. Watrous, 135 Conn. 638, 648, 68 A.2d 289; New Haven v. Public Utilities Commission, 165 Conn. 687, 726, 345 A.2d 563. The test of whether a statute is to be applied retroactively, absent an express legislative intent, “is not a purely mechanical one” and even if it is a procedural statute, which ordinarily will be applied retroactively without a legislative imperative to the contrary, “it will not be applied retroactively if considerations of good sense and justice dictate that it not be so applied. Lavieri v. Ulysses . . . [149 Conn. 396, 401, 180 A.2d 632]; E. M. Lowe’s Enterprises, Inc. v. International Alliance, 127 Conn. 415, 418, 17 A.2d 525.” Carvette v. Marion Power Shovel Co., 157 Conn. 92, 96, 249 A.2d 58; Jones Destruction, Inc. v. Upjohn, 161 Conn. 191, 196, 286 A.2d 308. These aids to legislative interpretation apply with equal force to amendatory acts which effectuate changes in existing statutes. See Lavieri v. Ulysses, 149 Conn. 396, 402, 403, 180 A.2d 632; 1A Sutherland, Statutory Construction (4th Ed.) § 22.36. The rule that statutes which are, general in their terms and affect matters of procedure can be applied retroactively, however, does not include a statute which, though in form providing but a change in remedy, actually brings about changes in substantive rights. Field v. Witt Tire Co., 200 F.2d 74, 77 (2d Cir.).

We have concluded that the General Assembly intended General Statutes §§ 49-41 and 49-42 to operate in general conformity with the federal statute, popularly known as the Miller Act (40 U.S.C. §§ 270a — 270e); Pittsburgh Plate Glass Co. v. Dahm, *224 159 Conn. 563, 567, 271 A.2d 55; International Harvester Co. v. L. G.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paradigm Contract Management Co. v. St. Paul Fire & Marine Insurance
979 A.2d 1041 (Supreme Court of Connecticut, 2009)
Gates v. Gates
975 A.2d 147 (Connecticut Superior Court, 2008)
Commissioner of Labor v. C.J.M. Services, Inc.
806 A.2d 1105 (Connecticut Appellate Court, 2002)
Millgard Corp. v. White Oak Corp.
224 F. Supp. 2d 425 (D. Connecticut, 2002)
Coastal Energy v. Conn. Carpentry Corp., No. Cv-99-269868-S (Oct. 11, 2001)
2001 Conn. Super. Ct. 13526 (Connecticut Superior Court, 2001)
Fairfield Resources v. City of Danbury, No. Cv98-033 16 19 S (Apr. 12, 2001)
2001 Conn. Super. Ct. 5187 (Connecticut Superior Court, 2001)
Barreira Landscaping & Masonry v. Frontier Insurance
779 A.2d 244 (Connecticut Superior Court, 2000)
Barreira Land. Mason. v. Frontier In., No. Cv97 034 69 08 (Dec. 6, 2000)
2000 Conn. Super. Ct. 15914 (Connecticut Superior Court, 2000)
Ames v. State Dept. of Motor Vehicles, No. Cv 99 0498564s (Sep. 26, 2000)
2000 Conn. Super. Ct. 12142-x (Connecticut Superior Court, 2000)
Northeast Waste Sys. v. Ct Abatement Tech., No. Cv980419724s (May 31, 2000)
2000 Conn. Super. Ct. 6538 (Connecticut Superior Court, 2000)
Western Surety Company v. State, No. Cv 99 0494408s (Dec. 15, 1999)
1999 Conn. Super. Ct. 16140 (Connecticut Superior Court, 1999)
Stamford Wrecking Company v. A.A.I.S., No. Cv-98-0420321 (Aug. 23, 1999)
1999 Conn. Super. Ct. 11883 (Connecticut Superior Court, 1999)
Bleiler v. Metcalf Eddy, Inc., No. Cv 98-0580066s (Feb. 17, 1999)
1999 Conn. Super. Ct. 2570 (Connecticut Superior Court, 1999)
Avon Meadow Condominium Ass'n v. Bank of Boston Connecticut
719 A.2d 66 (Connecticut Appellate Court, 1998)
KMK Insulation, Inc. v. A. Prete & Son Construction Co.
715 A.2d 799 (Connecticut Appellate Court, 1998)
Dysart Corp. v. Seaboard Surety Co.
688 A.2d 306 (Supreme Court of Connecticut, 1997)
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
Grinnell Fire Prot. Sys. v. Hartford Fire Ins., No. 32 20 81 (Nov. 1, 1996)
1996 Conn. Super. Ct. 9527 (Connecticut Superior Court, 1996)
B.W. Dexter II v. A. Prete Son Cons., No. Cv 96-0557033s (Aug. 23, 1996)
1996 Conn. Super. Ct. 5261-AAAAAAAA (Connecticut Superior Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
384 A.2d 378, 174 Conn. 219, 1978 Conn. LEXIS 821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-masons-supply-co-v-f-w-brown-co-conn-1978.