Paradigm Contract Management Co. v. St. Paul Fire & Marine Insurance

979 A.2d 1041, 293 Conn. 569, 2009 Conn. LEXIS 389
CourtSupreme Court of Connecticut
DecidedOctober 6, 2009
DocketSC 18301
StatusPublished
Cited by2 cases

This text of 979 A.2d 1041 (Paradigm Contract Management Co. v. St. Paul Fire & Marine Insurance) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paradigm Contract Management Co. v. St. Paul Fire & Marine Insurance, 979 A.2d 1041, 293 Conn. 569, 2009 Conn. LEXIS 389 (Colo. 2009).

Opinion

Opinion

McLACHLAN, J.

This case presents the narrow issue of whether any claim that may be asserted against a labor and material payment bond required by General *571 Statutes (Rev. to 1995) § 49-41 1 must be asserted within the time limit provided in General Statutes (Rev. to 1995) § 49-42 (b). 2 The plaintiff, Paradigm Contract Man *572 agement Company, brought this action against the defendant, St. Paul Fire and Marine Insurance Company, seeking to enforce, pursuant to § 49-41, a labor and material payment bond that the defendant had executed in connection with a municipal construction project. The defendant filed a motion to dismiss the action on the ground that it was barred by the statute of limitations set forth in § 49-42 (b). The trial court granted the motion to dismiss. The plaintiff appeals 3 from the judgment of the trial court, claiming that § 49-42 (b) does not apply to this action because the plaintiff had not brought the action pursuant to § 49-42 but, rather, had brought a common-law action on the bond, and the parties had entered into a tolling agreement whereby they had agreed to extend the statute of limitations. We affirm the judgment of the trial court.

The record reveals the following facts, the truth of which we assume for purposes of the issue raised in this appeal. See Thomas v. West Haven, 249 Conn. 385, 392, 734 A.2d 535 (1999) (“[i]n evaluating a motion to dismiss, [t]he evidence offered by the plaintiff is to be taken as true and interpreted in the light most favorable to [the plaintiff], and every reasonable inference is to be drawn in [the plaintiffs] favor” [internal quotation marks omitted]), cert. denied, 528 U.S. 117, 120 S. Ct. 1239, 146 L. Ed. 2d 99 (2000). On April 1, 1997, the defendant, as surety, and Metcalf and Eddy, Inc. (Met-calf), as general contractor and principal, executed a labor and material payment bond as required by § 49- *573 41 in the amount of $8.9 million in favor of the city of Danbury (city) in connection with a construction contract for the closure of the city’s municipal landfill (project). Under the terms of the bond, Metcalf and the defendant bound themselves to make payments promptly to all claimants furnishing labor and materials to the project. 4 The bond provided in relevant part that “[n]o suit or action shall be commenced hereunder by any claimant . . . [ajfter the expiration of one . . . year following the date on which [Metcalf] ceased work on said [c]ontract, it being understood, however, that if any limitation embodied in this bond is prohibited by any law controlling the construction hereof such limitation shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law. ...”

The plaintiff was a subcontractor of Poole and Kent-New England, Inc., which, in turn, was a subcontractor of Metcalf on the project. In 1999, the plaintiff brought a timely action against the defendant alleging that the plaintiff had provided labor and materials for the project for which it had not been paid and seeking payment from the defendant under the bond. Thereafter, the plaintiff and the defendant entered into a written tolling agreement, with an effective date of April 19, 2002, pursuant to which the plaintiff agreed to withdraw the action on the bond and the defendant agreed to waive any statute of limitations defenses that might arise after the effective date of the agreement. 5 The defendant agreed that this waiver would remain in effect for a *574 period of one year after the effective date of the agreement.

On February 26, 2003, the plaintiff brought another action seeking payment under the bond. Thereafter, the defendant filed a motion to dismiss the plaintiffs complaint on the ground that it was barred by the time limitation set forth in § 49-42. The trial court, Adams, J., denied the motion to dismiss. The defendant then filed a second amended answer in which it claimed as an affirmative defense that the plaintiffs action was time barred under § 49-42. The defendant also raised a counterclaim for attorney’s fees pursuant to § 49-42, claiming that the plaintiffs action was without substantial basis in law or fact. The plaintiff filed a motion to dismiss the counterclaim on the ground that it was time barred under § 49-42. The defendant then filed a second motion to dismiss the plaintiffs complaint on the ground that it was time barred under § 49-42.

The trial court, Jennings, J., granted the defendant’s motion to dismiss the complaint on the ground that the plaintiff had commenced the action more than one year after the date that it last had performed work on the project 6 and the action was, therefore, time barred under § 49-42. The court rejected the plaintiffs claim that, because the plaintiff had not brought an action pursuant to § 49-42 but, instead, had brought a common-law action on the bond, the time limitation in § 49-42 did not apply to the action. The court concluded that there is no common-law right to sue on a bond issued pursuant to § 49-41. With respect to the plaintiffs motion to dismiss the defendant’s counterclaim, the trial court concluded that it need not decide the question of whether the counterclaim was time barred, as the plaintiff had claimed, because, in light of the court’s dismissal of the plaintiffs complaint on timeliness *575 grounds, the court would be unable to determine whether the complaint was “without substantial basis in fact or law.” General Statutes (Rev. to 1995) § 49-42 (a). Accordingly, the court concluded that the counterclaim was “in a state of procedural mootness” and dismissed the counterclaim on this alternate ground. This appeal followed. See footnote 3 of this opinion.

The plaintiff claims that the trial court 7 improperly granted the defendant’s motion to dismiss its complaint on the grounds that the complaint was time barred under § 49-42 because the plaintiff had not brought its action pursuant to that statute, but instead had brought a common-law action on the bond. 8 We conclude that the trial court properly granted the motion to dismiss.

“The standard of review for a court’s decision on a motion to dismiss is well settled. A motion to dismiss tests, inter alia, whether, on the face of the record, the court is without jurisdiction. . . . [O]ur review of the court’s ultimate legal conclusion and resulting [determination] of the motion to dismiss will be de novo.” (Internal quotation marks omitted.) State v. Marsh & McLennan Cos., 286 Conn. 454, 463-64, 944 A.2d 315 (2008).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blakely v. Danbury Hospital
150 A.3d 1109 (Supreme Court of Connecticut, 2016)
Tayco Corp. v. Planning & Zoning Commission
986 A.2d 290 (Supreme Court of Connecticut, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
979 A.2d 1041, 293 Conn. 569, 2009 Conn. LEXIS 389, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paradigm-contract-management-co-v-st-paul-fire-marine-insurance-conn-2009.