National Surety Corp. v. Fischer Steel Corp.

374 S.W.2d 372, 213 Tenn. 396, 17 McCanless 396, 1964 Tenn. LEXIS 399
CourtTennessee Supreme Court
DecidedJanuary 8, 1964
StatusPublished
Cited by12 cases

This text of 374 S.W.2d 372 (National Surety Corp. v. Fischer Steel Corp.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Corp. v. Fischer Steel Corp., 374 S.W.2d 372, 213 Tenn. 396, 17 McCanless 396, 1964 Tenn. LEXIS 399 (Tenn. 1964).

Opinion

*397 Mr. Justice Holmes

delivered the opinion of the Court.

This is an appeal by the National Surety Corporation from a decree of the Chancery Court rendering a judgment in the amount of $3,781.38 in favor of Fischer Steel Corporation against the appellant and Fred Young, a contractor. The National Surety Corporation is the surety upon a “labor and material payment bond” executed by Fred Young, as principal, to the Shelby County Board of Education. The facts in the case are stipulated.

On February 27, 1961 Fred Young entered into a contract with the Shelby County Board of Education for construction of an addition to a County school. The National Surety Corporation became the surety upon Fred Young’s bond as such contractor. The Fischer Steel Corporation furnished materials to the contractor in the amount of the judgment, for which it has not been paid. The job was completed and accepted by Shelby County on October 5, 1961. Demand for payment was made by Fischer Steel Corporation, but no registered notice or personal delivery notice was given within 90 days after the completion of the work. The action was commenced *398 in the Chancery Court on September 26, 1962, which is within one year from the date of completion of the work and within one year from the date of the last delivery of materials, hut more than six months following each of said dates. Fischer Steel Corporation furnished the materials directly to Fred Young, the contractor, and had a direct contract with him.

The bond sued on provides that Fred Young, as principal, and the National Surety Corporation, as surety, are held and firmly bound unto the Shelby County Board of Education “for the use and benefit of claimants as hereinbelow defined” in the amount of $161,779.00. The bond then makes reference to the contract to construct an addition to the school and makes that contract a part of the bond by reference. It then provides:

“NOW, THEBEFOBE, THE CONDITIONS OF THIS OBLIGATION is such that if the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in the performance of the Contract, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however to the following conditions:
1. A claimant is defined as one having a direct contact with the Principal or with a subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the contract, labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.”

The bond further provides that every claimant as above defined may sue on this bond and prosecute the *399 suit to final judgment for such sum or sums as may be justly due claimant and have execution therefor. It next provides that no suit or action shall be commenced by any claimant unless claimant ‘ ‘ other than one having a direct contract with the Principal, shall have given written notice to any two of the following: The Principal, the Owner, or the Surety above named, within 90 days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made.”

The bond further provides no suit or action shall be commenced by any claimant “after the expiration of one (1) year following the date on which Principal ceased to work on said Contract, it being understood, however, that if any limitation embodied in this bond is prohibited by any law controlling the construction hereof such limitation shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law.”

The bond then fixes the venue of any action brought on the bond in a State Court of competent jurisdiction in the county in which the project or any part thereof is situated, or in the United States District Court for the district in which the project or any part thereof is situated. The bond makes no reference to the Tennessee statutes relating to contractor’s bonds for public work in this state. T.C.A. sees. 12-417 to 12-422.

T.C.A. see. 12-417 provides:

“No contract shall be let for any public work in this state, by any city, county or state authority, until the contractor shall have first executed a good and solvent bond to the effect that he will pay for all the labor and *400 materials used by said contractor, or any immediate or remote subcontractor under bim, in said contract, in lawful money of the United States. ’ ’

T.O.A. sec. 12-418 makes it a misdemeanor for any public officer to let or award a contract without requiring the bond provided for in T.C.A. sec. 12-417.

T.O.A. sec. 12-420 gives any laborer or furnisher of material the right to maintain an action on the bond in his own name.

T.O.A. sec. 12-421 provides:

“Such furnisher of labor or material, or such laborer, to secure the advantage of secs 12-417 — 12-422, shall, after such labor or material is furnished, or such labor is done, and within ninety (90) days after the completion of such public work, given written notice by return-receipt registered mail, or by personal delivery, either to the contractor who executed the bond, or to the public official who had charge of the letting or awarding of the contract”.

This Section also provides the information to be contained in the notice.

T.O.A. sec. 12-422 provides that action shall be brought within six months following the completion of such public work.

The contentions of the National Surety Corporation are summarized in its brief as follows:

“It is the defendant surety company’s contention that the complainant was required to give notice under the bond, and it denies that the complainant did give any notice to it or its co-defendant, as required by Section 12-421, T.C.A.
*401 “It was further the contention of the defendant surety company that the complainant failed to bring its suit within the time limitation as prescribed by Section 12-422, T.C.A.
“In other words, it was the defendant’s position that the bond was a statutory bond required on public jobs, and that the statutes as notices and limitations as to the bringing of suit are applicable, and that the complainant had no right of action against the defendant surety corporation, except as provided by Section 12-422, T.C.A.”
•H* ^ "T?
“* * * and that the complainant had no rights independent of Sections 12-421 and 12-422, T.C.A. ”

Certainly, if the bond executed by the surety gave complainant no rights, these contentions would be sound. The bond sued on expressly provides

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paradigm Contract Management Co. v. St. Paul Fire & Marine Insurance
979 A.2d 1041 (Supreme Court of Connecticut, 2009)
Tip's Package Store, Inc. v. Commercial Insurance Managers, Inc.
86 S.W.3d 543 (Court of Appeals of Tennessee, 2001)
Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
United American Bank of Memphis v. Gardner
706 S.W.2d 639 (Court of Appeals of Tennessee, 1985)
Anthony v. Construction Products, Inc.
677 S.W.2d 4 (Court of Appeals of Tennessee, 1984)
Waddell v. Davis
571 S.W.2d 844 (Court of Appeals of Tennessee, 1978)
Heglar v. McAdoo Contractors, Inc.
487 S.W.2d 312 (Court of Appeals of Tennessee, 1972)
Air Temperature, Inc. v. Morris
469 S.W.2d 495 (Court of Appeals of Tennessee, 1970)
Joseph F. Hughes & Co. v. George H. Robinson Corp.
175 S.E.2d 413 (Supreme Court of Virginia, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
374 S.W.2d 372, 213 Tenn. 396, 17 McCanless 396, 1964 Tenn. LEXIS 399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-corp-v-fischer-steel-corp-tenn-1964.