Heglar v. McAdoo Contractors, Inc.

487 S.W.2d 312, 1972 Tenn. Crim. App. LEXIS 314
CourtCourt of Appeals of Tennessee
DecidedMay 16, 1972
StatusPublished
Cited by2 cases

This text of 487 S.W.2d 312 (Heglar v. McAdoo Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heglar v. McAdoo Contractors, Inc., 487 S.W.2d 312, 1972 Tenn. Crim. App. LEXIS 314 (Tenn. Ct. App. 1972).

Opinion

NEARN, Judge.

Humboldt Housing Authority, a public corporate body politic, created under the Housing Authority Law of the State of Tennessee, entered into a contract with McAdoo Contractors, Inc., for the construction of a certain public housing project in Humboldt, Gibson County, Tennessee. McAdoo subcontracted the plumbing work to complainant, Chester Heglar. After the housing project was completed, McAdoo was paid by the Housing Authority the amount due under the contract less a per diem penalty stipulated in the contract for McAdoo’s failure to complete construction within the time prescribed in the contract with Humboldt. McAdoo paid Heg-lar the greater portion of the subcontract amount for the plumbing work, but withheld the approximate sum of Eleven Thousand ($11,000.00) Dollars. Heglar filed his Bill in the Chancery Court of Gibson County against McAdoo and The Aetna Casualty & Surety Company, the surety on McAdoo’s performance and payment bond with Humboldt Housing Authority. The Chancellor held against both McAdoo and the surety. Both McAdoo and the surety have appealed.

Four Assignments of Error have been filed with this Court. The first Assignment of Error is that the weight of the evidence preponderates against the findings and the Decree of the Chancellor. The second and third fault the Chancellor for failing to apply T.C.A. Sections 12-421 and 12-422 as a bar to complainant’s recovery. The last complains of the Chancellor’s ruling that certain testimony was inadmissa-ble.

The nature of the first Assignment of Error requires that we briefly review the facts.

The work on the housing project was begun on July 23, 1968 and, according to the contract between the Housing Authority and McAdoo, was to be completed by July 17, 1969. The job was not completed until December 16, 1969. This suit was filed October 29, 1970.

McAdoo was charged 146 days’ delay by the Housing Authority and, according to the terms of the contract with the Housing Authority, was assessed approximately Nineteen Thousand ($19,000.00) Dollars as liquidated damages. McAdoo sought to prove as a factual defense to the Original Bill that Heglar was responsible for at least 82 days of the delay. Setoff was claimed by McAdoo against Heglar in the amount of Eleven Thousand ($11,000.00) Dollars. The proof mainly consists of the testimony from various witnesses from each side with their version of which party to this suit or a third party caused the delay. It was Heglar’s testimony and that of his witnesses that Heglar caused no delay and, if anyone was to be blamed for the delay, it was either McAdoo or other subcontractors. On the other hand, McAdoo’s witnesses and proof attempted to show that the fault for the delay was to be laid at Heglar’s doorstep. However, on July 13, 1970, approximately seven months after completion, McAdoo wrote the Housing Authority seeking to avoid the contract penalty by laying the blame for the delay on the weather, strikes, failure of the dry wall subcontractor to properly perform, change orders, and skilled manpower short[314]*314age in the plumbing and carpentry trades. It was later admitted that there was no skilled manpower shortage. Ho cause, which would be directly aurmutable to Heglar, was given to the Housing Authority in the letter of July 13, 1970, by Mc-Adoo as a reason for the delay. Further, many of the daily work reports of the overall construction supervisor, employed by the architect, were favorable to Heglar and listed many causes other than the plumbing work for the delay, including delay caused directly by McAdoo.

This cause has arrived in this Court accompanied by a presumption of the correctness of the Chancellor’s findings of fact below. T.C.A. 27-303. We see no reason to unduly lengthen this Opinion by describing in detail the pros and cons of the testimony. Suffice it to say that we have weighed the evidence on the factual issue presented and find that it does not preponderate against the Chancellor’s finding that Heglar was not the cause of the delay and that McAdoo had failed to prove its right of setoff. In fact, the evidence preponderates in favor of the Court’s finding. Accordingly, the first Assignment of Error is overruled.

While we are about the matter of reviewing evidence, we think it proper at this point in the Opinion to consider appellant’s fourth Assignment of Error. During the course of the trial, counsel for appellant sought to introduce the testimony of James Guy as that of an expert in the construction trade. The excluded testimony was preserved in the record by an offer of proof. The witness was engaged in the construction business and was asked his opinion of the cause of a portion of the delay based upon hypothetical questions. The Trial Court ruled the testimony incompetent and gave no reason for its ruling. The witness was not familiar with the project under consideration and was called upon in effect to give his opinion as to the cause or blame for the overall delay on the job. Such opinion would of necessity be based on gross speculation since numerous variables such as weather and the prompt and proper performance or nonperformance of other subcontractors and the general contractor would be involved as well as contract change orders. Furthermore, expert testimony was uncalled for in this instance. The real question was not what caused the delay but who caused the delay. It was a simple matter of which witnesses were to be believed. By his certificate of election, the Trial Judge was made an expert in that field and none other was needed. In any event, the admissability of expert testimony is a matter largely within the sound discretion of the Trial Court. Thomas v. Harper (1964 M.S.) 53 Tenn.App. 549, 385 S.W.2d 130. We find no abuse of discretion. The fourth Assignment of Error is respectfully overruled.

Since public lands are not subject to labor and materialmen’s liens [See Air Temperature, Inc. v. Morris (1970 W.S.) Tenn.App., 469 S.W.2d 495], the Legislature has seen fit to require that all public works be bonded for the protection of laborers and materialmen. T.C.A. 12-417. T.C.A. Section 12-421 sets out the required notice to be given by the furnisher of labor or material for such public jobs, and T.C.A. Section 12-422 limits the time for filing suits on the contractor’s bond. T.C.A. Section 12-422 is as follows:

“Joinder of parties — Limitation of actions. — Several persons entitled may join in one suit on such bond, or one may file a bill in equity in behalf of all such, who may, upon execution of a bond for costs, by petition assert their rights in the proceeding; provided, that action shall be brought or claims so filed within six (6) months following the completion of such public work, or of the furnishing of such labor or materials.”

The Original Bill in this case was not filed until ten months after completion of the project and counsel for appellant strongly relies upon the case of City of Knoxville v. Burgess (1943) 180 Tenn. 412, [315]*315175 S.W.2d 548, to support the position that the bond in the instant case is a statutory bond and the suit was not timely filed pursuant to the statute, and should have been dismissed by the Trial Court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wal-Board Supply Co., Inc. v. Daniels
629 S.W.2d 686 (Court of Appeals of Tennessee, 1981)
Griggs v. Peerless Insurance Co.
528 S.W.2d 182 (Tennessee Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
487 S.W.2d 312, 1972 Tenn. Crim. App. LEXIS 314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heglar-v-mcadoo-contractors-inc-tennctapp-1972.