City of Knoxville v. Melvin F. Burgess, Inc.

175 S.W.2d 548, 180 Tenn. 412, 16 Beeler 412, 1943 Tenn. LEXIS 16
CourtTennessee Supreme Court
DecidedNovember 20, 1943
StatusPublished
Cited by9 cases

This text of 175 S.W.2d 548 (City of Knoxville v. Melvin F. Burgess, Inc.) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Knoxville v. Melvin F. Burgess, Inc., 175 S.W.2d 548, 180 Tenn. 412, 16 Beeler 412, 1943 Tenn. LEXIS 16 (Tenn. 1943).

Opinion

*415 Me. Chief Justice .Gkeen

delivered the opinion of the Court.

City of Knoxville, through a subsidiary, entered into a contract with Melvin F. Burgess, Inc., to construct an extension to the City’s electric distribution system at a cost of $200,000'. The work was completed and accepted and there remains in the hands of the City a balance of some $19,000 retained percentage.

It appears from a bill tiled by the City that a number of persons furnishing material for this work have not been paid by the contractor. It further appears that the contractor executed a bond with New Amsterdam Casualty Company as surety to secure performance and to indemnify the City against default and also to protect laborers and materialmen. And later the contractor undertook to assign its claim for the retained percentage to this surety.

Under these circumstances the City filed a. bill, in the nature of a bill of interpleader, making the contractor, the surety and the several unpaid creditors defendants. One of the creditors, Aluminum Company of America, answered the City’s bill and filed a cross bill against the Burgess Company and the surety seeking a recovery against the two for the amount of its unpaid claim, some $9,000. The Surety Company demurred to this cross bill, its demurrer was sustained, and the cross bill dismissed outright. From this decree of the chancellor the surety has prosecuted an appeal to this court.

The chancellor regarded as decisive of the merit of the cross bill the question as to whether the bond executed by the surety was a statutory bond or a common law bond. He was of opinion that in so far as the laborers and materialmen were involved the bond was a statutory *416 bond under tbe laws of Tennessee and that suit thereupon was barred by Code, seo. 7959. On tbe bearing before tbis court tbe principal debate ha.s been witb respect to tbe nature of tbe bond.

Code, sec. 7955, provides that “No contract shall be let for any public work in tbis state, by any city, county or state authority, until tbe contractor shall have first executed a good and solvent bond to tbe effect that be will' pay for all tbe labor and materials used by said contractor, or any immediate or remote sub-contractor under him, in said contract, in lawful money of tbe United 'States. ...”

Section 7958 provides that any laborer or furnisher of labor or material to said contractor, or to any immediate or remote sub-contractor under him, may bring an action on said bond and have recovery in bis own name, etc.

•Code, section 7959, is in these words:

“Several persons entitled may join in one suit on such bond, or one may file a bill in equity in behalf of all such, who may, upon execution of a bond for costs, by petition assert their rights in tbe proceeding; provided, that action shall be brought or claims so filed within six months following tbe completion of such public work, or of tbe furnishing of such labor or materials.”

Tbe Aluminum Company concedes herein that its cross bill was filed more than six months following tbe completion of tbis public work or of tbe furnishing of materials by it. Hence tbe chancellor’s decision.

In view of tbe allegations in its cross bill it is difficult to see bow tbe Aluminum Company can maintain that tbe bond it here sues on, in so far as it affects laborers and materialmen, is a common law bond.

Code, section 7966; provides that tbe furnisher of labor or material, to secure tbe advantage of the statute, shall *417 “■within ninety days after the completion of snch public work, give written notice by return-receipt registered mail, or by personal delivery, either to the contractor who executed the bond, or to the public official who had charge of the letting or awarding of the contract.” The cross bill avers that cross-complainant believed this work to have been accepted by the City on November 22, 1940, and that “cross-complainant gave notice to the New Amsterdam Casualty Company as required by statute in Section 7956 of the Code of Tennessee for 1932, by sending a registered letter to the surety under date of November 19,1940, notifying the surety of the amount of the claim and substituting (submitting) an itemized statement to support such claim. ’ ’

It was set out in the cross bill that cross-complainant had been previously informed that the affairs of the original contractor were in the hands of the surety and that the surety was completing all unfinished contracts. The cross bill continues, “It is alleged that this notice was within ninety days from the completion of the contract, or of the furnishing of materials by this cross-complainant, and that notice to the surety under the above circumstances was notice to the contractor as required under Section 7956, and within the time, and in the form and manner required in said statute. ’ ’

The cross bill then sets out certain negotiations that transpired between cross-complainant and the surety and charges that certain action of the surety “was a deliberate attempt to forestall your cross-complainant from filing suit and that such action amounted to a waiver of Section 7959 of the Code of Tennessee requiring suit to be instituted within six months following the completion of such public work or the furnishing of such labor or materials.”

*418 In another paragraph, of the cross bill a certain statement of an officer of the- surety is mentioned and it is averred that such a statement “constitutes a waiver of Section 7959 of the Code of Tennessee regarding the filing of suit within six months from the completion of the work or the furnishing of the material.”

In still another paragraph of the bill a different act of the surety is charged “as a waiver of its rights to the fund in the hands of the City of Knoxville and a waiver of Section 7969' of the statutes of Tennessee.”

Thus obviously the theory of the cross bill was that in so far as materialmen were concerned the bond sued on was a statutory bond and the rights of materialmen with respect to the bond were controlled by the Tennessee statute. Upon such pleadings as the foregoing the cross-complainant is scarcely entitled to recovery against the surety on the theory that the bond in suit is a common law obligation as to materialmen. Nevertheless we consider this contention.

It was virtually conceded in argument that the bond in question was dual in its nature. That is, in one aspect it protected the City, in another aspect it protected laborers and materialmen. Bonds of this nature have been before this court previously and the obligations to the governmental-agency on the one hand and to laborers and materialmen on the other have been treated as distinct and separate obligations although combined in one paper. City of Bristol v. Bostwick, 139 Tenn., 304, 202 S. W., 61; Cass v. Smith, 146 Tenn., 218, 240 S. W., 778. The obligation to the governmental ag*ency may be subject to the common law and the obligation to laborers and materialmen may be subject to the statute if the •latter obligation is only such an obligation as is required by the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aetna Casualty & Surety Co. v. Woods
565 S.W.2d 861 (Tennessee Supreme Court, 1978)
Varner Construction Co. v. Mid-South Specialties, Inc.
547 S.W.2d 569 (Tennessee Supreme Court, 1977)
Heglar v. McAdoo Contractors, Inc.
487 S.W.2d 312 (Court of Appeals of Tennessee, 1972)
Thompson & Green Machinery Co. v. Travelers Indemnity Co.
421 S.W.2d 643 (Court of Appeals of Tennessee, 1967)
National Automation Corp. v. Reinsurance Corp.
47 Misc. 2d 893 (New York Supreme Court, 1965)
National Surety Corp. v. Fischer Steel Corp.
374 S.W.2d 372 (Tennessee Supreme Court, 1964)
Graybar Electric Co. v. New Amsterdam Casualty Co.
211 S.W.2d 903 (Tennessee Supreme Court, 1948)
Graybar Electric Co. v. New Amsterdam Casualty Co.
54 N.E.2d 811 (New York Court of Appeals, 1944)
Hogan v. Walsh & Wells, Inc.
177 S.W.2d 835 (Tennessee Supreme Court, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
175 S.W.2d 548, 180 Tenn. 412, 16 Beeler 412, 1943 Tenn. LEXIS 16, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-knoxville-v-melvin-f-burgess-inc-tenn-1943.