Graybar Electric Co. v. New Amsterdam Casualty Co.

54 N.E.2d 811, 292 N.Y. 246, 1944 N.Y. LEXIS 1380
CourtNew York Court of Appeals
DecidedMarch 10, 1944
StatusPublished
Cited by27 cases

This text of 54 N.E.2d 811 (Graybar Electric Co. v. New Amsterdam Casualty Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graybar Electric Co. v. New Amsterdam Casualty Co., 54 N.E.2d 811, 292 N.Y. 246, 1944 N.Y. LEXIS 1380 (N.Y. 1944).

Opinion

J.

Plaintiff supplied to a contractor materials for the performance of public work at Knoxville, Tennessee, and upon default in payment therefor began this action on a performance bond whereby the defendant surety company undertook with the local public authorities to make good the claims of laborers and materialmen. The answer of the surety company sets forth provisions of a Tennessee statute which authorizes a bond of that type. The substance of the several defenses is that the plaintiff failed to comply with conditions laid down by this statute as necessary to the recovery demanded in the complaint.

On motion .by the plaintiff, Special Term held the defenses to be invalid and awarded to the plaintiff a summary judgment for the price of the materials in question — $39,889.23. A cross motion by the defendant for summary dismissal of the complaint was denied. The Appellate affirmed and granted leave to the defendant to present the case to this court for review.

The ground of the decision at Special Term was that the bond in suit is a common-law bond. After that decision had been affirmed at the Appellate Division, the highest court of Tennessee in the case of City of Knoxville v. Melvin F. Burgess (175 S. W. 2d 548 [Tenn.]) pronounced this same bond to be a statutory bond insofar as the rights of laborers and materialmen are concerned. The bond was made and delivered in Tennessee and was there to be performed. Hence the character of the obligation of the instrument is to be determined in accordance with the relevant law of that State whether declared as common law or by statute. (Teel v. Yost, 128 N. Y. 387, 394.) We have been licensed to take judicial notice of foreign law (Civ. Prac. Act, § 344-a). Accordingly, we now acknowledge the authority of City of Knoxville v. Melvin F. Burgess (supra) and we recognize the statutory nature of the bond in suit. (Whether section 344-a is to be applied in cases triable as of right by jury we need not now consider.)

*251 The statute of Tennessee on which.the surety company relies for its defenses makes these provisions: Such furnisher of labor or material, or such laborer, to secure the advantage of the two foregoing sections [permitting them to sue on the statutory bond] shall, after such labor or material is furnished, or such labor is done, and within ninety days after the completion of such public work, give written notice by return-receipt registered mail, or by personal delivery, either to the contractor who executed the bond, or to the public official who had charge of the letting or awarding of the contract; such written notice to sét forth the nature, and itemized account of the material furnished or labor done, and balance due therefor; and a description of the property improved; provided, that in the case of public work undertaken by a municipality, or any of its commissions, notice, or statement herein required, so mailed or delivered to the mayor thereof, shall be deemed 'sufficient * * ”. (Tennessee Code, § 7956.) 11 Several persons entitled may join in one suit on such bond, or one may file a bill in equity in behalf of all such, who may, upon execution of a bond for costs, by petition assert their rights in the proceeding; provided, that action shall be brought or claims so filed within six months following the completion of such public work, or of the furnishing of such labor or materials.” (Tennessee Code, § 7959.)

Inasmuch as the bond in suit was given pursuant to this statute, the statutory text is to be read into the instrument. The notice so prescribed was never served by this materialman nor was this action commenced within the six months period so defined. In that state of the controversy, the decision now to be passed will determine this question: Do the provisions of the Tennessee statute pertain to the substance of the obligation of the bond in suit, with the result that the plaintiff has no case; or do these provisions go merely to the remedy for a breach of that obligation, with the result that they are immaterial, since the law that governs the remedy is the law of New York. (See Reilly v. Steinhart, 217 N. Y. 549.)

In City of Knoxville v. Melvin F. Burgess (supra, pp. 551-552), the highest Court of Tennessee said: “ The statute does not prescribe any form in which the bond for the protection of laborers and materialmen is to follow. If this bond had con *252 tained a provision for no.tice and a provision limiting the time for suit, such provisions would only he effective in so far as they coincided with the statutory requirements as to notice and time of suit. It has been held in a number of cases where the statute was silent as to the terms of the that in case of a conflict between provisions of the bond and provisions of the statute as to the time limits prescribed by the statute, the statutory limits would prevail. Smith & W. Co. v. Carlsted, 165 Minn. 313; Lawson v. County Board of Pub. Instruction, 118 Fla. 246; United States Fidelity & G. Co. v. Tafel Electric Co., 262 Ky. 792. The Kentucky case grew out of a Tennessee contract. The court held that it was governed by the Tennessee statute and that although the bond provided a longer time in which suit might be brought than did the statute, nevertheless the short limitation of the Tennessee statute controlled and barred the suit.”

To our minds, these words mean that the provisions of the statute of Tennessee were limitations of the liability undertaken upon the bond in suit and not limitations of the rights of action thereby conferred upon laborers and materialmen. (Cf. National Surety Co. v. Architectural Co., 226 U. S. 276; Home Ins. Co. v. Dick, 281 U. S. 397, 407; Clark Plastering Co. v. Seaboard Surety Co., 259 N. Y. 424.) The Tennessee statute (as so construed by the highest court of that State) must here be accorded the full faith and credit which is enjoined by the Federal Constitution in respect of the “ public acts ” of a sister State. (John Hancock Ins. Co. v. Yates, 299 U. S. 178.)

■ Ch. J., Lewis, CoNway, and Thacher, JJ., «concur; Rippey, J., dissents and votes to

.Judgments reversed, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scaffold-Russ Dilworth Ltd. v. Shared Management Group, Ltd.
289 A.D.2d 932 (Appellate Division of the Supreme Court of New York, 2001)
Scaccia Concrete Corp. v. Hartford Fire Insurance
212 A.D.2d 225 (Appellate Division of the Supreme Court of New York, 1995)
Pennex Aluminum Co. v. International Fidelity Insurance
818 F. Supp. 772 (M.D. Pennsylvania, 1993)
Fisher v. Velasquez
126 Misc. 2d 24 (Civil Court of the City of New York, 1984)
Felix Contracting Corp. v. Federal Insurance
97 A.D.2d 533 (Appellate Division of the Supreme Court of New York, 1983)
Omega New York Products Corp. v. Parisi Bros.
57 Misc. 2d 1000 (New York Supreme Court, 1968)
National Automation Corp. v. Reinsurance Corp.
47 Misc. 2d 893 (New York Supreme Court, 1965)
Chester Airport, Inc. v. Aeroflex Corp.
37 Misc. 2d 145 (New York Supreme Court, 1962)
Lai v. Vargas
16 A.D.2d 643 (Appellate Division of the Supreme Court of New York, 1962)
Cooper v. Commercial Insurance
14 A.D.2d 55 (Appellate Division of the Supreme Court of New York, 1961)
Cohen v. Gilbert
12 A.D.2d 301 (Appellate Division of the Supreme Court of New York, 1961)
Pigott v. Field
10 A.D.2d 99 (Appellate Division of the Supreme Court of New York, 1960)
Burry Colonial Corp. v. A. E. Ottaviano, Inc.
21 Misc. 2d 814 (New York Supreme Court, 1960)
Triple Cities Construction Co. v. Dan-Bar Contracting Co.
285 A.D. 299 (Appellate Division of the Supreme Court of New York, 1954)
Daniel-Morris Co. v. Glens Falls Indemnity Co.
283 A.D. 504 (Appellate Division of the Supreme Court of New York, 1954)
Dog Owners Ass'n of New York State, Inc. v. Hilleboe
206 Misc. 119 (New York Supreme Court, 1953)
Cardinal v. State of New York
107 N.E.2d 569 (New York Court of Appeals, 1952)
In re the Estate of Peart
277 A.D.2d 61 (Appellate Division of the Supreme Court of New York, 1950)
Long v. Ferris
196 Misc. 567 (City of New York Municipal Court, 1949)
Gilpin v. Mutual Life Ins. Co. of N.Y.
86 N.E.2d 737 (New York Court of Appeals, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
54 N.E.2d 811, 292 N.Y. 246, 1944 N.Y. LEXIS 1380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graybar-electric-co-v-new-amsterdam-casualty-co-ny-1944.