Long v. Ferris

196 Misc. 567, 94 N.Y.S.2d 493, 1949 N.Y. Misc. LEXIS 3100
City of New York Municipal Court·Decided October 28, 1949·Published·Cited by 5 cases

Opinion

Byrnes, Ch. J.

The defendant Glens Falls Indemnity Company has moved under rule 107 of the Buies of Civil Practice to dismiss the complaint against it, and, more particularly, the fourth alleged cause of action.

The case arises out of a public construction contract made and performed in the State of Connecticut. The plaintiff furnished materials used in such construction to a subcontractor, the defendant Ferris; the general contractor was the defendant Great Atlantic Construction Corporation.

It is alleged in the complaint that the moving defendant Glens Falls Indemnity Company, as surety, executed and delivered to the State Highway Department of the State of Connecticut a performance bond conditioned upon the performance by the said general contractor of all the terms and conditions of its contract. This performance bond was an indemnity bond, and the contention of the plaintiff that it inured to the plaintiff’s benefit must be rejected at the outset. The performance bond was not written for the benefit of persons who furnished labor or materials in the prosecution of the work provided in the contract. That bond had no purpose other than to indemnify the State of Connecticut against losses that it might sustain by reason of the general contractor’s failure to complete performance of its contract. It made no reference (as the form of bond submitted on this motion shows) either directly or by implication to creditors of the contractor or any subcontractor, [569] and no intention to benefit such creditors may be inferred from the terms of the bond. The only condition stated in that obligation was the following: “ Now, therefore, if the saidl Principal shall well and truly keep, perform and execute all the terms, conditions and stipulations of said contract according to its provisions on its/his part to be kept and performed, and shall indemnify the Obligee for all loss that the Obligee may sustain by reason of the Principal’s failure to comply with said terms, conditions and stipulations, then this obligation shall be null and void, otherwise it shall remain and be in full force and effect.” There were no provisions in the bond inuring to the benefit of laborers or materialmen or other creditors of the contractor or subcontractor. Insofar as the performance bond is concerned, the case is therefore unlike McClare v. Massachusetts Bonding & Ins. Co. (266 N. Y. 371).

However, the defendant surety company also wrote a payment bond, which was plainly intended for the benefit of persons such as this plaintiff, who furnished materials or labor used or employed in the execution of the contract. The important question, therefore, is whether an action may be maintained in this court which is based upon the payment bond. The motion to dismiss is grounded upon the moving defendant’s contention that this court lacks jurisdiction of the subject matter of such an action.

The payment bond is a statutory obligation; that is, it was given pursuant to, and because it was required by, the statutes of Connecticut (Conn. Gen. Stat. [1941 Supp. to 1930 Revision], ch. 274, §§ 694f, 695f, 696f; now Conn. Gen. Stat. [1949 Revision], ch. 362, §§ 7214, 7215, 7216). The statute is referred to in the bond; the condition of that obligation reads as follows: Now, Therefore, If the said Principal shall well and faithfully make payment for all materials and labor used or employed in the execution of such contract, to the extent required by Chapter 274 (Sections 694F, 695F and 696F) of the 1941 Supplement to the General Statutes, then this obligation shall be null and void, otherwise it shall remain and be in full force and effect.”

It has been held in the highest court of Connecticut that such a bond and the statute which required it must be construed together and that the liability of the surety under the bond is coterminous with the statute ”, and not greater (New Britain Lumber Co. v. American Surety Co. of New York, 113 Conn. 1, 7). In that case it was held that the provision of the statute which required the filing by a materialman of a statement of [570] claim within sixty days after ceasing to furnish materials, as a condition precedent to recovery — although it was not expressly stated or repeated in the bond — was nevertheless to be regarded as one of its terms, as “ the parties are deemed to have had the law in contemplation when the contract was executed.” The court said: ‘ ‘ Where a statutory bond is given,. the provisions of the statute will be read into the bond ”. (P.5.) To the same effect is Graybar Electric Co. v. New Amsterdam Cas. Co. (292 N. Y. 246, 251), in which the court, referring to a performance bond given under the laws of Tennessee, said: Inasmuch as the bond in suit was given pursuant to this statute, the statutory text is to be read into the instrument.”

Free access — add to your briefcase to read the full text and ask questions with AI

Long v. Ferris, 196 Misc. 567, 94 N.Y.S.2d 493, 1949 N.Y. Misc. LEXIS 3100 (N.Y. Super. Ct. 1949).

196 Misc. 567 (Long v. Ferris) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J. R. Cristoni, Inc. v. Reliance Ins., No. Cv94 0358013 (Jul. 25, 1994)
1994 Conn. Super. Ct. 7007 (Connecticut Superior Court, 1994)
State ex rel. United States Fidelity & Guaranty Co. v. Mehan
581 S.W.2d 837 (Missouri Court of Appeals, 1979)
Johnson Acoustics, Inc. v. P. J. Carlin Construction Co.
292 A.2d 273 (Connecticut Superior Court, 1971)
Omega New York Products Corp. v. Parisi Bros.
57 Misc. 2d 1000 (New York Supreme Court, 1968)
United States Fidelity & Guaranty Co. v. Colonial Baking Co.
247 S.W.2d 997 (Supreme Court of Arkansas, 1952)