Herbert S. Newman & Partners, P.C. v. CFC Construction Ltd. Partnership

674 A.2d 1313, 236 Conn. 750, 1996 Conn. LEXIS 108
CourtSupreme Court of Connecticut
DecidedApril 30, 1996
Docket15197
StatusPublished
Cited by96 cases

This text of 674 A.2d 1313 (Herbert S. Newman & Partners, P.C. v. CFC Construction Ltd. Partnership) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herbert S. Newman & Partners, P.C. v. CFC Construction Ltd. Partnership, 674 A.2d 1313, 236 Conn. 750, 1996 Conn. LEXIS 108 (Colo. 1996).

Opinion

PETERS, C. J.

The principal issue in this appeal is whether contracting parties who, pursuant to General Statutes § 49-41,1 execute a public works construction [752]*752payment bond may expand the coverage of the bond beyond the coverage required by the statute. The plaintiff, Herbert S. Newman and Partners, P.C., is an architectural firm that rendered services in connection with a public works project. The plaintiff brought an action against the defendants, CFC Construction Limited Partnership (CFC), which was the successor in interest to the general contractor on the public works project and the principal on the payment bond for the project, and National Union Fire Insurance Company of Pittsburgh, Pennsylvania (National Union), the surety on the bond. The plaintiff asserted a claim for damages against CFC for breach of contract and sought payment under the bond from both defendants for services it had rendered pursuant to the contract. The defendants denied the plaintiffs claim that it was owed compensation for services rendered. After a hearing, the trial court rendered judgment for the plaintiff. The defendants appealed jointly from the judgment of the trial court to the Appellate Court, and we transferred the appeal to this court pursuant to Practice Book § 4023 and General Statutes § 51-199 (c). We affirm the judgment of the trial court.

The following facts are undisputed. In 1986, Chase Enterprises authorized the plaintiff to begin rendering architectural services for the development of a design concept for a new city hall building in New Haven. On February 11, 1988, Enterprise Construction Company, [753]*753Inc. (Enterprise), an entity affiliated with Chase Enterprises, entered into an owner-contractor agreement with the city of New Haven for the construction of the new city hall building. The owner-contractor agreement identified the plaintiff as the architect on the project.

CFC, another entity affiliated with Chase Enterprises, subsequently assumed Enterprise’s obligations under the owner-contractor agreement. Pursuant to § 49-41, CFC furnished the city with a payment bond in the amount of $11,827,644. Under the terms of the payment bond, CFC, as principal, and National Union, as surety, bound themselves to make payments promptly to all claimants supplying labor, services or materials for the city hall project. The payment bond incorporated by reference the owner-contractor agreement and expressly provided that the bond was furnished pursuant to § 49-41. On July 13, 1989, the city consented to CFC’s substitution as general contractor on the city hall project. On July 14, 1989, the city and CFC amended the owner-contractor agreement to reflect the assumption by CFC of Enterprise’s obligations under the agreement.

On June 21,1990, the city sent CFC a notification that it was terminating CFC’s status as general contractor on the city hall project, effective seven days after CFC’s receipt of the notification. On June 25, 1990, CFC received the city’s notice of termination. On July 2,1990, in accordance with the city’s notice of termination, CFC relinquished control of the project to the city. Additional facts will be discussed as they become relevant to the issues before us.

On June 25,1991, the plaintiff commenced this action against the defendants, seeking payment of its invoices, interest, costs and attorney’s fees. The plaintiffs amended complaint alleged that CFC, as principal, and National Union, as surety, were liable to the plaintiff [754]*754under the terms of the payment bond for services that the plaintiff had rendered pursuant to its contract with CFC. The defendants denied that they owed the plaintiff compensation for those services, raised several special defenses to the plaintiffs claims and filed a counterclaim against the plaintiff for indemnity for any sums awarded against them in pending litigation.2

Specifically, the defendants claimed that the plaintiff was barred from recovering under its contract with CFC because, inter aha: (1) the plaintiff had failed to obtain a necessary contract modification for payment of the services for which it sought compensation; and (2) CFC’s obhgations under the contract had been discharged under the doctrine of accord and satisfaction. The defendants also claimed that, even if CFC were hable under its contract with the plaintiff, the plaintiff was not entitled to rehef under the payment bond because: (1) the plaintiff had failed to estabhsh that its services fell within the coverage of the bond; and (2) the plaintiff had failed to commence its action on the bond in a timely manner. The defendants further claimed that, even if the plaintiff could recover under the payment bond, the plaintiff was not entitled to recover under the bond for services that it had rendered after the city had terminated the owner-contractor agreement.

The trial court concluded that CFC had failed to perform its contract with the plaintiff. The trial court also concluded that the defendants were hable to the plaintiff on the payment bond for services that the plaintiff had rendered pursuant to its contract with CFC and for which it had not received compensation. The trial court [755]*755rendered judgment for the plaintiff on both the complaint and the counterclaim, and awarded the plaintiff $184,793.02, plus costs and interest.

I

The defendants’ primary claim is that the work performed by the plaintiff is not covered by the payment bond that CFC furnished for the city hall project. The defendants contend that, as a matter of law, the coverage of a payment bond executed pursuant to § 49-41 cannot be broader than the coverage required by the statute, and that the statute expressly protects only “persons supplying labor or materials.” The defendants further contend that the plaintiff can recover on the payment bond as a “[person] supplying labor or materials” only for services that it rendered on the project job site and that, because the plaintiff did not distinguish between services it had rendered at the job site and services it had rendered away from the job site, it failed to establish its entitlement to recovery on the bond. We need not determine whether the defendants’ interpretation of § 49-41 is correct, however, because we conclude that the coverage of a payment bond executed pursuant to § 49-41 can be broader than the coverage required by the statute and that in this case the bond executed by the defendants expressly covered the services rendered by the plaintiff.

We first address the defendants’ claim that a payment bond executed pursuant to § 49-41 cannot establish broader protection than that required by the statute. Our analysis of this issue “is guided by well established principles of statutory construction. Statutory construction is a question of law and therefore our review is plenary. . . . [0]ur fundamental objective is to ascertain and give effect to the apparent intent of the legislature. ... In seeking to discern that intent, we look to the words of the statute itself, to the legislative history [756]*756and circumstances surrounding its enactment, to the legislative policy it was designed to implement, and to its relationship to existing legislation and common law principles governing the same general subject matter.” (Citations omitted; internal quotation marks omitted.) State v. Burns, 236 Conn. 18, 22-23, 670 A.2d 851 (1996); HUD/Barbour-Waverly v. Wilson, 235 Conn. 650, 656, 668 A.2d 1309 (1995).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wheeler v. Beachcroft, LLC
210 Conn. App. 725 (Connecticut Appellate Court, 2022)
Abrams v. PH Architects, LLC
193 A.3d 1230 (Connecticut Appellate Court, 2018)
Computer Reporting Services, LLC v. Lovejoy & Associates, LLC
145 A.3d 266 (Connecticut Appellate Court, 2016)
Vasily v. Mony Life Insurance Co. of America
104 F. Supp. 3d 207 (D. Connecticut, 2015)
Old Colony Construction, LLC v. Southington
Supreme Court of Connecticut, 2015
Meadowbrook Center, Inc. v. Buchman
Connecticut Appellate Court, 2014
Cedar Mountain, LLC v. D & M Screw MacHine Products, LLC
41 A.3d 1131 (Connecticut Appellate Court, 2012)
Vance v. Tassmer
16 A.3d 782 (Connecticut Appellate Court, 2011)
Paradigm Contract Management Co. v. St. Paul Fire & Marine Insurance
979 A.2d 1041 (Supreme Court of Connecticut, 2009)
Kline v. Kline
922 A.2d 261 (Connecticut Appellate Court, 2007)
Precision Mechanical Services, Inc. v. Shelton Yacht & Cabana Club, Inc.
903 A.2d 692 (Connecticut Appellate Court, 2006)
Young v. Young
827 A.2d 722 (Connecticut Appellate Court, 2003)
Santone v. Liberty Mutual Ins. Co., No. Cv 98 0354105 (Mar. 18, 2003)
2003 Conn. Super. Ct. 3783 (Connecticut Superior Court, 2003)
Professional Employ. v. Empire Paving, No. Cv-01-0458733 S (Dec. 13, 2002)
2002 Conn. Super. Ct. 16118 (Connecticut Superior Court, 2002)
Photronics, Inc. v. Decarlo, No. Cv00-033 85 19 S (Nov. 26, 2002)
2002 Conn. Super. Ct. 15186 (Connecticut Superior Court, 2002)
Farrell v. Viski, No. Cv99-0270274-S (Aug. 7, 2002)
2002 Conn. Super. Ct. 10193 (Connecticut Superior Court, 2002)
Simkins Industries v. Standard Group, No. X01 Cv 00 0165315 S (Jun. 5, 2002)
2002 Conn. Super. Ct. 7213 (Connecticut Superior Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
674 A.2d 1313, 236 Conn. 750, 1996 Conn. LEXIS 108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herbert-s-newman-partners-pc-v-cfc-construction-ltd-partnership-conn-1996.