Precision Mechanical Services, Inc. v. Shelton Yacht & Cabana Club, Inc.

903 A.2d 692, 97 Conn. App. 258, 2006 Conn. App. LEXIS 387
CourtConnecticut Appellate Court
DecidedAugust 29, 2006
DocketAC 26800
StatusPublished
Cited by3 cases

This text of 903 A.2d 692 (Precision Mechanical Services, Inc. v. Shelton Yacht & Cabana Club, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Precision Mechanical Services, Inc. v. Shelton Yacht & Cabana Club, Inc., 903 A.2d 692, 97 Conn. App. 258, 2006 Conn. App. LEXIS 387 (Colo. Ct. App. 2006).

Opinion

Opinion

HENNESSY, J.

In this action to foreclose a mechanic’s lien, the defendant, the Shelton Yacht and Cabana Club, Inc., doing business as Pinecrest Country Club (Pinecrest), appeals from the judgment of the trial court rendered in favor of the plaintiff, Precision Mechanical Services, Inc. (Precision). Pinecrest claims that the court improperly (1) found that it breached the contract it entered into with Precision, (2) awarded Precision $47,806 for breach of contract and (3) prohibited Pine-crest from calling an expert witness it did not disclose until after the trial had started. We affirm the judgment of the trial court.

*260 The following procedural history and facts found by the court are relevant to our consideration of the issues in Pinecrest’s appeal. Precision is a corporation that designs, fabricates and installs sprinklers. Its president, Kevin M. Wypychoski, is a licensed fire protection contractor and plumber in Connecticut. Pinecrest is a corporation operating a catering and function hall at 745 River Road in Shelton. Jonathan Zuckerman, its president, has operated Pinecrest for more than thirty years.

In 2002, Pinecrest was warned by the town fire marshal that it was not in conformity with the applicable fire codes and that it needed to install a sprinkler system in order to continue operating. As a result, Pinecrest, through Zuckerman, contacted Precision about fabricating and installing a sprinkler system. Shortly thereafter, Wypychoski met with Zuckerman at Pinecrest to discuss sprinkler systems and associated costs. During ■ the meeting, Zuckerman told Wypychoski that Pine-crest’s multiroom building was approximately 10,000 square feet. Wypychoski told Zuckerman that it would cost $5 per square foot to fabricate and install the sprinkler system and, thus, the sprinkler system would cost approximately $50,000. Wypychoski drafted a budget proposal outlining what he orally told Zuckerman.

After meeting with Wypychoski, Zuckerman spent the next six months looking for a way to keep Pinecrest in operation without installing a sprinkler system. Zuck-erman’s attempt to find an alternative method to continue operating ultimately proved futile, and he therefore contacted Precision and another sprinkler company, Connecticut Fire Protection & Sprinkler Service Company, Inc. Precision sent a second budget proposal, dated March 4, 2003, which restated that it would cost $50,000 to fabricate and install a sprinkler system. Connecticut Fire Protection & Sprinkler Service Company, Inc., sent a proposal stating that it would fabricate *261 and install a sprinkler system for $89,500. Pinecrest hired Precision because it was the lower bidder.

Precision drafted a contract on the basis of the second proposal. Article one of the contract states that Precision “shall . . . [d]esign and install a fire sprinkler system throughout the entire building (approximately 10,000 square feet).” Zuckerman added a clause to the contract requiring that all work result in compliance with the applicable fire codes. Zuckerman then signed the contract.

Between March 18 and April 10, 2003, Precision’s employees took detailed measurements of the building. The measurements indicated that the building was actually 20,800 square feet. As a result, Wypychoski notified Zuckerman of the discovery and that the contract would have to be amended to reflect the increased cost due to the additional square footage. Wypychoski further told Zuckerman that he would be issuing a change order reflecting the new price.

Subsequently, on April 24, 2003, Precision started sending material and equipment that would later be used for the fabrication and installation of the sprinkler system. On April 30, 2003, Precision issued a change order, which reflected an additional cost of $46,800 for the additional square footage. On May 2, 2003, Pine-crest’s counsel sent a letter to Wypychoski, arguing that Precision was bound by the $50,000 price of the contract and that Pinecrest would not pay the price reflected in the change order. Despite the letter, Zuckerman and Wypychoski continued to negotiate the final price. During these negotiations, Zuckerman instructed Wypy-choski to proceed with the work. Precision continued to fabricate and install the sprinkler system. Zuckerman, however, made no additional payments for work done after May 2, 2003.

*262 On June 2, 2003, Precision, with the sprinkler system not fully completed, stopped working because it was not receiving any of the prearranged scheduled payments. On July 10, 2003, Precision removed all of its materials and equipment from the job site. Precision then billed Pinecrest for the completed work, which Precision argued was 100 percent of the original contract work and $12,600 on the change order, totaling $66,356, of which Pinecrest paid $18,550. As a result, Precision executed, served and recorded a mechanic’s lien to secure payment of the balance.

On September 29, 2003, Precision commenced this action to foreclose its mechanic’s lien on theories of breach of contract and unjust enrichment. In response, Pinecrest asserted the special defenses of failure to perform work at an agreed on price, payment in full, estoppel and negligent installation. In addition, Pine-crest filed a counterclaim seeking damages for incomplete performance of the contact, loss of income from the inability to use the premises and improper installation requiring removal and replacement of the sprinkler system. 1

The matter was tried to the court on July 6 and September 7, 8, 9, 13 and 28, 2004. On August 10, 2004, during the recess between the first and second day of trial, Pinecrest attempted to disclose a third expert witness, Roger H. Brake, Jr. Precision objected to the disclosure, arguing that it was untimely and prejudicial. The court sustained the objection. The court ultimately rendered judgment in favor of Precision. This appeal followed. Additional facts will be set forth as necessary.

I

Pinecrest first claims that the court improperly found that it breached the contract it entered into with Precision. Pinecrest specifically argues that the original written contract was never modified and, thus, both parties *263 were bound by its terms. Before we address the merits of Pinecrest’s claim, we set forth the applicable standard of review and legal principles relating to contract modification.

“For a valid modification to exist, there must be mutual assent to the meaning and conditions of the modification and the parties must assent to the same thing in the same sense.” (Internal quotation marks omitted.) Herbert S. Newman & Partners, P.C. v. CFC Construction Ltd. Partnership, 236 Conn. 750, 761, 674 A.2d 1313 (1996). “The manifestation of assent may be made wholly or partly by written or spoken words or by other acts or by failure to act.” (Internal quotation marks omitted.) Ubysz v. DiPietro, 185 Conn. 47, 51, 440 A.2d 830 (1981).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vasily v. Mony Life Insurance Co. of America
104 F. Supp. 3d 207 (D. Connecticut, 2015)
Hicks v. State
948 A.2d 982 (Supreme Court of Connecticut, 2008)
Precision Mechanical Services, Inc. v. Shelton Yacht & Cabana Club, Inc.
909 A.2d 524 (Supreme Court of Connecticut, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
903 A.2d 692, 97 Conn. App. 258, 2006 Conn. App. LEXIS 387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/precision-mechanical-services-inc-v-shelton-yacht-cabana-club-inc-connappct-2006.