Town of Brookfield v. Greenridge, Inc.

418 A.2d 907, 177 Conn. 527, 1979 Conn. LEXIS 779
CourtSupreme Court of Connecticut
DecidedMay 15, 1979
StatusPublished
Cited by18 cases

This text of 418 A.2d 907 (Town of Brookfield v. Greenridge, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Brookfield v. Greenridge, Inc., 418 A.2d 907, 177 Conn. 527, 1979 Conn. LEXIS 779 (Colo. 1979).

Opinion

Peters, J.

This ease arises out of the failure of the defendant Greenridge, Inc., to complete certain road and drainage improvements on approved subdivision plats in accordance with town specifications. The plaintiff town of Brookfield sought damages against Greenridge, in the first count of a two-count complaint, for its failure to complete the *529 improvements. The second count was against Green-ridge as principal and Travelers Insurance Company as surety on a performance bond posted by both defendants in connection with the subdivision approval. The court found the issues for the plaintiff on both counts and rendered judgment against Greenridge on the first count for $38,000 plus interest at 6 percent from January 1, 1971, and against Travelers on the second count for $15,000, to be applied toward the damages awarded in the first count. From this judgment both defendants have appealed to this court.

The relevant facts may be summarized as follows. On November 9, 1965, the plaintiff, acting through its planning commission, gave its approval to the defendant Greenridge for two subdivision plats known as Plat A and Plat B. Subdivision approval called for the completion of Plats A and B in accordance with the requirements of the town of Brookfield subdivision regulations and road regulations. In accordance with the subdivision regulations, Green-ridge as principal and Travelers as surety executed and delivered to the planning commission a surety bond in the amount of $40,000 to secure the completion of certain road improvements, as authorized by § 8-25 of the General Statutes. The bond did not specify a date for completion of the improvements. There was no formal contract or written agreement between the town and Greenridge relating to the construction of the roads other than the obligations of the parties implicit in the subdivision approval and in the posting of the aforesaid bond.

The roads in Plat A were accepted by the town and are not at issue in this appeal. The roads in Plat B, which remain at issue, were accepted by the *530 town at a town meeting in December, 1969, “collectively and at such, time as the Board of Selectmen shall have approved the conditions of the roads.” 1 Shortly thereafter, the board of selectmen reduced the amount of the surety bond to $15,000 because a major portion of the subdivision roads had been accepted and the selectmen believed the reduced amount was sufficient to insure completion of repairs.

iThe bituminous concrete surfaces of the roads in question began breaking up in 1966, shortly after the roads were constructed. The court found that the cause of the deterioration of the roads was primarily the lack of underdrain. Other problems discovered with the roads were the application of a bituminous concrete surface of substandard thickness and an insufficient amount or, in some cases, total lack of gravel subbase. As a result of the problems discovered, the plaintiff’s selectmen never incorporated the roads in Plat B into the town’s highway system, and no deed to the roads was ever accepted or recorded by the selectmen.

This appeal raises three issues: (1) Did the trial court err in holding the defendant G-reenridge liable in damages to the plaintiff for failure to complete certain road improvements, in particular the installation of underdrain, in the defendant’s subdivision plat? (2) Is the liability of the defendant Greenridge for defective performance, if any, limited to the amount of the surety bond? (3) Can the amount of the judgment be upheld when the findings do not indicate any monetary basis for the judgment?

*531 As a preliminary matter, we must consider the numerous attacks on the finding made by the defendants. The defendants seek to add several paragraphs of the draft finding which they claim to be admitted or undisputed. We have examined each of the paragraphs sought to be added to the finding and conclude that the finding is not subject to material correction. Many of the facts claimed to be admitted or undisputed have been included, implicitly or explicitly, in the finding, and the remaining facts would not alter the conclusions of this court. See E & F Realty Co. v. Commissioner of Transportation, 173 Conn. 247, 248-9, 377 A.2d 302 (1977). The defendants have also attacked several paragraphs of the finding as found without evidence. In each case, the plaintiff in its brief and appendix has referred us to evidence supporting the challenged finding, and the findings must therefore be sustained. Slattery v. Maykut, 176 Conn. 147, 149, 405 A.2d 76 (1978). The remaining assignments of error, insofar as they are briefed and argued, relate to the court’s conclusions of law and the overruling of the defendants’ claims of law, and will be treated in the discussion of the main issues on appeal.

I

The first issue concerns the liability of the defendant Greenridge for its failure to complete road and drainage improvements in the roads in Plat B. Greenridge argues that it had no responsibility to install underdrain on the roads in question because underdrain was not specifically referred to in the town’s road specifications, nor indicated on the plats, and that the plaintiff is attempting to impose a contract for the construction of drainage where none existed. The defendants’ argument rests on the fact *532 that subdivision approval called for conformance with the town’s subdivision regulations, section 9.1 of which provides: “In all subdivisions adequate provision shall be made for storm drainage according to the filed map.” (Emphasis added.) The defendant Greenridge asserts that since the requirement of underdrain was not specifically indicated on the filed map, nor spelled out in the road specifications, it was not required to provide any underdrain in the process of road construction.

The defendants’ argument cannot survive their own concession and the court’s finding that under-drain is an integral part of road construction, basic to proper road building wherever wet field conditions exist. The court’s finding indicates that installation of underdrain is not a common specification for road construction because it is not needed for every road, but is necessary for proper construction when such wet field conditions are discovered. Moreover, unchallenged findings reveal that town selectmen informed representatives of Greenridge that under-drain was required on roads shown on approved maps, and that Greenridge did in fact install some underdrain on at least one of the roads in Plat B. The defendants’ citations to the “general rule” that a planning board, having given approval to a subdivision plan, cannot thereafter attach supplementary conditions to such approval; see 4 Rathkopf, The Law of Zoning and Planning, c. 71, p. 71-99 (1978); 3 Anderson, American Law of Zoning, § 19.25, p. 444 (1968); are inapposite.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Haven Holdings Ltd. Partnership v. Planning & Zoning Commission
77 A.3d 866 (Connecticut Appellate Court, 2013)
Dornfried v. Granquist, No. Cv00-0502628 (Mar. 27, 2003)
2003 Conn. Super. Ct. 3964-e (Connecticut Superior Court, 2003)
Town of Southington v. Commercial Union Insurance
805 A.2d 76 (Connecticut Appellate Court, 2002)
Town of Haddam v. Axa Global Risks, No. X03 Cv 99 0497638s (Mar. 15, 2001)
2001 Conn. Super. Ct. 3721 (Connecticut Superior Court, 2001)
Leake v. Commissioner of Consumer Prot., No. Cv98-0061494s (Mar. 25, 1999)
1999 Conn. Super. Ct. 3547 (Connecticut Superior Court, 1999)
Puerto Rican Cement Co. v. Junta de Planificación
146 P.R. Dec. 428 (Supreme Court of Puerto Rico, 1998)
Town of Southington v. Comm. Union Ins., No. Cv-95-565691 (Jan. 22, 1998)
1998 Conn. Super. Ct. 376 (Connecticut Superior Court, 1998)
Fournier v. Gama Developers, Inc., No. Cv95-0125666 (Jul. 29, 1997)
1997 Conn. Super. Ct. 7909 (Connecticut Superior Court, 1997)
Herbert S. Newman & Partners, P.C. v. CFC Construction Ltd. Partnership
674 A.2d 1313 (Supreme Court of Connecticut, 1996)
Chapman v. Ei Constructors, Inc., No. Cv 0040938 (Feb. 21, 1995)
1995 Conn. Super. Ct. 1702 (Connecticut Superior Court, 1995)
Yelmini v. Taylor, No. Cv 92 0512519s (Nov. 26, 1993)
1993 Conn. Super. Ct. 10246 (Connecticut Superior Court, 1993)
T J Food Markets v. J. P. Kempf Co., No. Cv 89-0287555 (Jun. 22, 1993)
1993 Conn. Super. Ct. 6101 (Connecticut Superior Court, 1993)
Nationwide Mut. Ins. v. R S Assoc., No. Cv 92-0451559s (Sep. 18, 1992)
1992 Conn. Super. Ct. 8845 (Connecticut Superior Court, 1992)
Larue v. Hoar, No. 45556 (Apr. 28, 1992)
1992 Conn. Super. Ct. 3775 (Connecticut Superior Court, 1992)
Hines v. Westfield Inc., No. Cv-88-0251120 S (Apr. 29, 1991)
1991 Conn. Super. Ct. 3735 (Connecticut Superior Court, 1991)
Transdulles Centre Ltd. Partnership v. USX Corp.
761 F. Supp. 430 (E.D. Virginia, 1991)
Hamann v. Town of Newtown
541 A.2d 899 (Connecticut Appellate Court, 1988)
Dooley v. Leo
440 A.2d 236 (Supreme Court of Connecticut, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
418 A.2d 907, 177 Conn. 527, 1979 Conn. LEXIS 779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-brookfield-v-greenridge-inc-conn-1979.