Hartford Electric Applicators of Thermalux, Inc. v. Alden

363 A.2d 135, 169 Conn. 177, 1975 Conn. LEXIS 811
CourtSupreme Court of Connecticut
DecidedJuly 22, 1975
StatusPublished
Cited by32 cases

This text of 363 A.2d 135 (Hartford Electric Applicators of Thermalux, Inc. v. Alden) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Electric Applicators of Thermalux, Inc. v. Alden, 363 A.2d 135, 169 Conn. 177, 1975 Conn. LEXIS 811 (Colo. 1975).

Opinion

Longo, J.

The plaintiff, a dry wall subcontractor, sued the defendant owner-contractors, claiming $5347 due under a contract. The defendants denied that the plaintiff performed under the contract and, in their special defense and counterclaim, alleged that the plaintiff failed to complete the work in a thorough and workmanlike manner as required by the contract. The defendants further counterclaimed for liquidated damages under the terms of the agreement, claiming that the work was completed 114 days late. The court rendered judgment for the plaintiff in the sum of $5347 and for the defendants under their counterclaim in the sum of $1350, from which both parties appealed.

The defendants claim that the plaintiff failed to satisfy the terms of the contract, which provided that the work of the plaintiff was to be performed “in a good, substantial, thorough and workmanlike manner .. . and in every respect complete ... to the full satisfaction of . . .. [the] Architect”; the plaintiff, therefore, should not recover the amount due. “[W]here the court can see from the contract that it was the intent of the parties that the performance on the one side was not to be conditioned on the performance on the other, the promises will *179 be construed as independent.” Finlay v. Swirsky, 103 Conn. 624, 635, 131 A. 420; Williston, Contracts (3d Ed.) §§ 665, 669. Consequently, the parties can recover damages consistent with the losses suffered and they are left free to prove their damages by the requisite degree of persuasion. Thus, the terms of the contract requiring performance in a workmanlike manner to the satisfaction of the architect constitute a promise by the plaintiff. Strimiska v. Yates, 158 Conn. 179, 185, 257 A.2d 814; Lach v. Cahill, 138 Conn. 418, 421, 85 A.2d 481. The finding, supported by the evidence printed in the appendix to the plaintiff’s brief, supports the conclusion that the work was performed in a workmanlike manner. Consequently, the court correctly refused to award damages to the defendants on that counterclaim.

Another clause of the contract, however, unmistakably provides that payment by the defendants is conditioned upon approval by the architect, 1 who is also an owner-contractor and a codefendant. See Haugen v. Raupach, 43 Wash. 2d 147, 260 P.2d 340; Silverstone, “Satisfaction in the Performance of Contracts,” 2 Conn. B.J. 10. The finding, as supported by the evidence printed in the appendices to the briefs, indicates that the plaintiff, in response to the architect’s expression of dissatisfaction with certain portions of the work, effected some repairs. The architect, however, never returned to inspect *180 the new work; he did not specify which work items remained outstanding and stood in the way of approval. Under these circumstances, where payment is conditioned on approval by the architect who is also a party to the contract, the architect owes the subcontractor, within reason, the duty to inspect the work and to specify those items which must be corrected in order to secure his approval. Clover Mfg. Co. v. Austin Co., 101 Conn. 208, 213-14, 125 A. 646; Frankfort Distilleries, Inc. v. Burns Bottling Machine Works, Inc., 174 Md. 12, 197 A. 599; Hood v. Meininger, 377 Pa. 342, 105 A.2d 126; Restatement, Contracts $ 265. If it were otherwise, the contractor’s promise to pay would be illusory; there would be no mutuality of consideration, thereby rendering suspect a standard contract provision widely used in the construction industry. Therefore, the failure of the defendant architect to fulfill his duty to inspect the work following the plaintiff’s repairs, and to specify additional corrections required, constitutes a waiver by the defendants of the condition requiring satisfaction of the architect precedent to payment. Haugen v. raupach, supra; Restatement, 1 Contracts § 303 (d). Consequently, the defendants are estopped from raising any defense based upon that provision. ravitch v. Stollman Poultry Farms, Inc., 165 Conn. 135, 149, 328 A.2d 711.

In its cross appeal, the plaintiff assigns error with respect to the granting of liquidated damages to the defendants. Substantial performance was completed twenty-five calendar days after the contract completion date. The plaintiff claims that the defendants breached the contract by delaying notification, for forty days past the agreed upon final date for such notification, that it might com *181 menee performance. 2 It argues that the defendants’ breach entirely excuses it from the liquidated damages clause in the contract. In the alternative, the plaintiff argues that for purposes of computing liquidated damages, it should be credited with the forty-day delay of the defendants.

The trial court concluded that the date mentioned in the contract, April 20, was not a guaranteed commencement date, but merely an approximation of the earliest possible date that the plaintiff could start working. The plaintiff attacks this finding, claiming that the defendants’ delay in notification until approximately June 1 that the work could begin constituted a breach of contract. The conclusion of the trial court is tested by the finding and must stand unless it is legally or logically inconsistent with the facts found or unless it involves the application of some erroneous rule of law material to the case. New Haven v. United Illuminating co., 168 Conn. 478, 483, 362 A.2d 785.

The plaintiff has also attacked the underlying finding of fact that “[t]he plaintiff and defendants agreed that the earliest possible date on which work by the plaintiff might begin was April 20, 1970.” “A finding of fact is tested by the evidence printed in the appendices to the briefs.” State ex rel. Golembeske v. White, 168 Conn. 278, 280, 362 A.2d 1354. The defendants have not filed an appendix to their reply brief and there is no other evidence *182 in any other appendix which could support the finding of fact. It is their duty to print all material evidence in the appendices to the briefs; the court will not look beyond the appendices to examine the transcript unless justified by extraordinary circumstances. Practice Book §§ 645, 721; Barnini v. Sun Oil Co., 161 Conn. 59, 62, 283 A.2d 217; State

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Old Colony Construction, LLC v. Southington
Supreme Court of Connecticut, 2015
Flaherty v. Flaherty
990 A.2d 1274 (Connecticut Appellate Court, 2010)
Quiello v. Reward Network Establishment Services, Inc.
420 F. Supp. 2d 23 (D. Connecticut, 2006)
Cantonbury Heights Condominium Ass'n v. Local Land Development, LLC
873 A.2d 898 (Supreme Court of Connecticut, 2005)
Goldberg v. Hartford Fire Insurance
849 A.2d 368 (Supreme Court of Connecticut, 2004)
American Express T.R.S. v. Weppler, No. Cv 01-0384633-S (Jan. 27, 2003)
2003 Conn. Super. Ct. 1579 (Connecticut Superior Court, 2003)
Magnano v. Testa, No. Cv 97 0140517 S (Oct. 12, 2000)
2000 Conn. Super. Ct. 12613 (Connecticut Superior Court, 2000)
Bouchard v. Boyer, No. 543089 (May 17, 1999)
1999 Conn. Super. Ct. 6067 (Connecticut Superior Court, 1999)
Silvio Benedetto Assc. v. Ind. Mar. Corp., No. Cv96 0154352 (Jun. 18, 1998)
1998 Conn. Super. Ct. 7707 (Connecticut Superior Court, 1998)
General Motors Corp. v. Blanchard, No. Cv-97-406057 (May 19, 1998)
1998 Conn. Super. Ct. 6670 (Connecticut Superior Court, 1998)
Mendenhall v. Connecticut Post Ltd., No. Cv94 031 64 15 S (Nov. 26, 1997)
1997 Conn. Super. Ct. 11527 (Connecticut Superior Court, 1997)
Herbert S. Newman & Partners, P.C. v. CFC Construction Ltd. Partnership
674 A.2d 1313 (Supreme Court of Connecticut, 1996)
Wartko v. Bachman Snax of So. Ct., Inc., No. Cv94 04 56 04s (Mar. 15, 1995)
1995 Conn. Super. Ct. 2079 (Connecticut Superior Court, 1995)
Gm Testani Construction Co. v. Delcegno, No. Cv-92-0291747s (Oct. 25, 1994)
1994 Conn. Super. Ct. 10872 (Connecticut Superior Court, 1994)
Naugatuck Savings Bank v. Fiorenzi, No. 0104014 (Feb. 25, 1994)
1994 Conn. Super. Ct. 2009 (Connecticut Superior Court, 1994)
Van Dyck Printing Co. v. Dinicola
648 A.2d 898 (Connecticut Superior Court, 1993)
Denino v. Udolf, No. Cv-91-0501958s (Sep. 1, 1992)
1992 Conn. Super. Ct. 8293 (Connecticut Superior Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
363 A.2d 135, 169 Conn. 177, 1975 Conn. LEXIS 811, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-electric-applicators-of-thermalux-inc-v-alden-conn-1975.