Hood v. Meininger

105 A.2d 126, 377 Pa. 342, 44 A.L.R. 2d 1106, 1954 Pa. LEXIS 518
CourtSupreme Court of Pennsylvania
DecidedMay 24, 1954
DocketAppeals, 274, 275 & 276
StatusPublished
Cited by14 cases

This text of 105 A.2d 126 (Hood v. Meininger) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hood v. Meininger, 105 A.2d 126, 377 Pa. 342, 44 A.L.R. 2d 1106, 1954 Pa. LEXIS 518 (Pa. 1954).

Opinion

Opinion by

Mb. Justice Chidsey,

These three actions of assumpsit were brought to recover damages for breach of contract and were tried together. The appellant, Margaret Meininger, who was the plaintiff in two of the cases in the court below and defendant in the third, successively employed three independent contractors, appellees herein, to repair and remodel certain buildings on her farm in Perkasie, Pennsylvania.

The first contractor, appellee Robert Gerling, entered into an oral contract with the appellant in February, 1948 to make these alterations and improvements. After work had progressed under this contract, because of certain differences between the parties, they executed a written agreement on July 6, 1949 which purported to cover work already completed and work to be done in the future. The written contract contained a provision that the contractor would furnish first class workmanship and materials which must be satisfactory to the owner. There was also a clause that provided for weekly payments to the contractor upon the submittal by him of an itemized statement of the cost of materials and labor. Gerling was discharged by the appellant in September, 1949 because of alleged defective and unsatisfactory work.

Sometime in June, 1950 the appellant entered into an oral contract with appellee Samuel Friedman, to complete the work left undone by Gerling and to make other renovations and additions to the property for an agreed upon price. The initial price was increased during the course of the work because extra work was ordered by the appellant. Friedman was also discharged in October, 1950 for the same reason as Ger-ling. The appellant then executed a written contract with appellees Frank Hood and George Gross, trading as Hood & Gross, on December 20, 1950, to complete *345 the project first undertaken by Gerling and later by Friedman and to rectify a part of the alleged defective work. Hood & Gross entered upon the task and rendered two monthly statements for work done during January and February of 1951 for which they received approximately $3,915. Their contract was similar to the one appellant made with Gerling in that it contained a provision that the contractor would furnish first class workmanship and materials to the owner’s satisfaction and contained a clause for monthly payments upon the contractor’s tender of an itemized statement of the cost of labor and materials. In March, 1951 the appellant, through her architect, directed Hood & Gross to stop work for the same reason that their predecessors were ordered to discontinue the operation.

In November, 1950 the appellant instituted two separate actions against appellees Gerling and Friedman respectively, for restitution of money paid for defective work and the cost of correcting such defects. Gerling counterclaimed for unpaid labor and materials supplied by him and for loss of profit. Friedman in the suit against him set up a counterclaim for loss of profit. Appellees Hood and Gross, in July, 1951 filed a complaint against the appellant to recover the balance due them for work they had completed and damages for loss of profit; the appellant counterclaimed for damages suffered due to defective work and for certain losses by theft. At appellant’s request the three cases were consolidated, jury trial was waived and the trial judge after hearings entered judgment in Appeal No. 274 for appellees Hood and Gross, for the sum of $11,610.81 and found against the defendant on her counterclaim. In Appeal No. 275 the court entered judgment against appellant on her claim against appellee Gerling, and found for him on his *346 counterclaim in the amount of $>1,409.09. In Appeal No. 276 the court found against the appellant on lier claim and against appellee Friedman, on Ms counterclaim. Exceptions were taken by the appellant to the findings of fact and conclusions of law of the trial judge which were dismissed by the court en banc and judgments were entered on the findings, from which these three appeals were taken.

Since the case was tried without a jury, the question presented is whether the findings of fact of the trial judge, having been confirmed by the court en banc, are supported by substantial evidence: Kahn v. American Cone & Pretzel Company et al., 365 Pa. 161, 167, 74 A. 2d 160. If they are so supported, they are conclusive on this appeal, since they have the same weight as the verdict of a jury in cases tried by a jury: Andrikanics v. Andrekanics, 371 Pa. 222, 224, 89 A. 2d 792; Pennsylvania Company for Insurances on Lives and Granting Annuities v. Wallace et al., 346 Pa. 532, 535, 31 A. 2d 71. We will consider the evidence and findings in each case seriatim in an attempt to obviate much of the confusion that resulted in the trial below by the consolidation of the causes.

In Appeal No. 275 the trial judge found that appellee Gerling faithfully and honestly endeavored to perform his contract in all material and substantial particulars and that the appellant unjustifiably refused to make payments due to the defendant on demand. He also found that the reduction allowed by the appellee for work which he admitted was defective was adequate for that purpose. From these findings he concluded that appellant had breached the contract. He further concluded that in view of the conjectural testimony as to the party responsible for the defective work, the appellant had failed to carry her burden of *347 proving that the alleged defects were traceable to Gerling.

The contract in the Gerling case being one in which performance was conditioned on the satisfaction of the owner, the test of adequate performance was not whether the owner ought to have been satisfied but whether she was satisfied: Singerly v. Thayer, 108 Pa. 291, 2 A. 280; Burke v. Daughters of the Most Holy Redeemer, Inc., 344 Pa. 579, 581, 26 A. 2d 460; Ehrlich v. United States Fidelity and Guaranty Company, 356 Pa. 417, 429, 51 A. 2d 794. There are, however, two limitations inherent in this principle: (1) that the dissatisfaction must be genuine and not prompted by caprice or bad faith, and (2) that if the work is not sufficiently completed for a reasonable determination whether it was or would be satisfactory, then the rejection is premature. Singerly v. Thayer, supra; James Schleicher and Adolph Schleicher, trading as Schleicher, Schumm & Co. v. United Security Life Insurance and Trust Company, 191 Pa. 477, 43 A. 380.

It was the appellee’s position that various changes in the original plans delayed the completion of the project and he testified that the work was left unfinished because the appellant refused to make the progress payments contemplated by the written contract. Appellant on the other hand testified that the work was impeded because the appellee changed workmen on numerous occasions. She testified further that when she complained of his imperfections, he always assured her that if any defects existed they would be corrected in due course. The record discloses that the appellee’s duties were of an indefinite nature after the execution of the oral contract. Originally the appellee had only obligated himself to erect a two-car garage with an apartment above.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jack Frost Construction v. Bertothy, J.
Superior Court of Pennsylvania, 2023
Church v. Tentarelli
953 A.2d 804 (Superior Court of Pennsylvania, 2008)
Aster v. BP Oil Corp.
412 F. Supp. 179 (M.D. Pennsylvania, 1976)
Hartford Electric Applicators of Thermalux, Inc. v. Alden
363 A.2d 135 (Supreme Court of Connecticut, 1975)
Commonwealth v. BERGER
312 A.2d 100 (Commonwealth Court of Pennsylvania, 1973)
St. Paul at Chase Corp. v. Manufacturers Life Insurance
278 A.2d 12 (Court of Appeals of Maryland, 1971)
Universal Builders, Inc. v. Moon Motor Lodge, Inc.
244 A.2d 10 (Superior Court of Pennsylvania, 1968)
First National Realty Corporation v. Warren-Ehret Company, Inc.
233 A.2d 811 (Court of Appeals of Maryland, 1967)
Day & Zimmermann, Inc. v. Blocked Iron Corp.
200 F. Supp. 132 (E.D. Pennsylvania, 1961)
Willred Company v. Westmoreland Metal Mfg. Co.
200 F. Supp. 59 (E.D. Pennsylvania, 1961)
Magar v. Lifetime, Inc.
144 A.2d 747 (Superior Court of Pennsylvania, 1958)
Wissahickon Realty Corp. v. Boyle
122 A.2d 720 (Supreme Court of Pennsylvania, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
105 A.2d 126, 377 Pa. 342, 44 A.L.R. 2d 1106, 1954 Pa. LEXIS 518, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hood-v-meininger-pa-1954.