Jack Frost Construction v. Bertothy, J.

Superior Court of Pennsylvania·Decided October 6, 2023·No. 208 WDA 2022·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

JACK FROST CONSTRUCTION, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA

:

v. :

:

:

JASON T. BERTOTHY AND DANA A. :

BERTOTHY :

: No. 208 WDA 2022

Appellants :

Appeal from the Judgment Entered February 8, 2022 In the Court of Common Pleas of Clearfield County Civil Division at No(s): 2019-541-CD

BEFORE: BOWES, J., MURRAY, J., and PELLEGRINI, J.* MEMORANDUM BY BOWES, J.: FILED: October 6, 2023 Jason T. Bertothy and his wife, Dana A. Bertothy (collectively “the Bertothys”), appeal from the $40,5564.26 judgment entered on the verdict in favor of Jack Frost Construction, Inc. (“Jack Frost”). We vacate the judgment and remand for further proceedings. I. Facts and Procedural History The certified record supports the following history of this case as outlined in the findings of fact enumerated in the trial court opinion and order entered on August 25, 2021. In November 2017, the Bertothys contracted with Jack Frost for the construction of a single-family residence (“the Contract”). The Contract, which was negotiated between the Bertothys and

* Retired Senior Judge assigned to the Superior Court.

Jack Frost’s owner, Billy Joe Sallurday, specifically referenced, but did not incorporate, a September 12, 2017 estimate (“the Estimate”) that outlined a flat fee for materials, plans and labor totaling $480,107.00.1 The Contract provided that payments were due within ten days of the submission of an invoice and that Jack Frost retained the right to cease work if payments were not timely received. In this vein, the contract included a provision that calculated interest at a rate of 1.5% per month or 18% per year. Neither the Contract nor the Estimate stated a completion date, but a proviso in the Estimate advised that the arrangement was “contingent upon . . . delays beyond [the contractor’s] control.” Estimate, 9/12/17, at 2.

Over the ensuing year, construction was plagued by delays associated with winter weather, an abnormal amount of rainfall, and the failure of a sub- contractor, namely the Bertothys’ son, Trent, to excavate the site, grade the driveway, and dig the trenches for housing electrical and water supply lines. The various delays prompted an ongoing dispute between the parties over the pace of construction and the use and storage of construction materials at the site.

Between the start of the project in November 2017 and July 2018, the Bertothys satisfied all four of the periodic invoices that Jack Frost submitted totaling $122,357.00. However, the Bertothys withheld payment on the fifth

1 While the Contract states the incorrect date of the Estimate, the parties do not dispute that they agreed to the Estimate provided on September 12, 2017.

pay application (“Pay Application No. 5”) for $63,060.26 due to what they claimed were unresolved construction defects that they believed Jack Frost had failed to remedy, and because that application requested payment for work that had not been completed. While the trial court ultimately determined that Jack Frost continued to work on the project despite the non-payment of Pay Application of No.5, the parties dispute the amount and pace of construction after July 2018.

On October 4, 2018, the Bertothys’ counsel mailed Jack Frost a cease-

and-desist letter. Prior to receiving the letter, Jack Frost had partially framed the structure, sheathed the roof, and completed the deck footer, footer, foundation, and plumbing slab. The concrete work was approved by Pennsafe Building Inspection Services, LLC. Within six days of issuing the letter, the Bertothys had the property inspected by David Connelly, a structural engineer, who observed extensive moisture near the foundation, slab, framing, exterior walls, and roof trusses. See N.T., 11/5/19, at 102-11, 114-17, 118-19, 120- 26, 130-31. Specifically, Mr. Connelly identified, inter alia, a wet slab and interior foundation, weather-compromised lumber used in framing and sheathing, and the accumulation of mold and mildew on the floor joists and roof trusses. Id. at 108-09, 114-26, 130-31. Overall, he described the prolonged moisture exposure as,

A lot of wet construction, in a nutshell. Everything seemed to be pretty-well soaked, even the interior. Yes, there was roof sheathing on the structure. There was still water coming through . . . that allowed a lot of water into the interior structure. . . .

[T]he exterior sheathing, really seemed to [have] taken on a lot of water.

Id. at 102. The visual inspection was performed approximately six days after Mr. Sallurday was last on the job site and claimed that he observed no moisture-related damage when he left. Id. at 138; N.T., 11/4/20, at 48, 70- 71.

On April 1, 2019, Jack Frost sued the Bertothys for breach of contract due to their alleged failure to satisfy Pay Application No. 5 in accordance with the Contract. It also sought $13,006.27 for windows that had been purchased in anticipation of installation. The Bertothys’ answer and new matter included several counterclaims including breach of contract based upon Jack Frost’s alleged failure to perform in a timely and workmanlike manner. The Bertothys also pled violations of the Pennsylvania Unfair Trade Practices and Consumer Protection Law (“UTPCPL”) sections 201-2(4)(vii), (xiv), and (xxi), which relate to a business’s representation of goods and services, compliance with written warranties, and fraudulent or deceptive conduct, respectively.2 Following a bench trial over three days between November 2020 and March 2021, and review of the parties’ proposed findings of fact and conclusions of law, the trial court found in favor of Jack Frost and awarded it

2 The Bertothys’ counterclaims also included alternative counts of unjust enrichment and negligence. As the Bertothys do not challenge the trial court’s rejection of these counts, we do not discuss them herein.

$40,560.26, plus the contractual interest rate, for the unpaid materials and labor costs outlined in Pay Application No. 5.3 As to the Bertothys’ counterclaims, the court rejected all of the requests for relief, holding: (1) the issue concerning Jack Frost’s alleged failure to perform in a timely and workmanlike manner was not ripe because the Bertothys had not permitted the contractor to fix the potential defects associated with the incomplete performance prior to issuing the cease-and- desist letter and taking possession of the worksite; (2) all of the completed work had been performed in a workmanlike manner; and (3) Jack Frost did not engage in any of the alleged conduct that purportedly violated the UTPCPL.

This timely appeal followed the denial of the Bertothys’ post-trial motions and the entry of judgment on the verdict. Both the Bertothys and the trial court complied with Pa.R.A.P. 1925.

The Bertothys present seven questions for our review, which we re-

ordered for ease of disposition:

1. Whether, under relevant law, the trial court erred in permitting an expert witness to testify at trial who [Jack Frost] failed to disclose or identify during discovery.

2. Whether, under relevant law, the trial court erred in finding [Jack Frost] is entitled to $40,560.26 for labor and materials,

3 While Jack Frost requested $63,060.26 in damages, plus $13,006.27 for the

new windows, the court concluded that it only established $40,560,26 of that amount. See Trial Court Opinion and Order, 8/25/21, at 7 (holding, Jack Frost did not establish $13,006.27 damages for windows or $22,500.00 in damages for plumbing materials and HVAC equipment that was not used on the project.

without any documentary evidence or business records to substantiate the amount claimed.

3. Whether, under relevant law, the trial court erred in making findings contrary to the evidence presented at trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Jack Frost Construction v. Bertothy, J., (Pa. Ct. App. 2023).

Jack Frost Construction v. Bertothy, J. (Jack Frost Construction v. Bertothy, J.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ecksel v. Orleans Construction Co.
519 A.2d 1021 (Supreme Court of Pennsylvania, 1987)
Gill v. McGraw Electric Co.
399 A.2d 1095 (Superior Court of Pennsylvania, 1979)
Feingold v. Southeastern Pennsylvania Transportation Authority
517 A.2d 1270 (Supreme Court of Pennsylvania, 1986)
Schreiber v. Republic Intermodal Corp.
375 A.2d 1285 (Supreme Court of Pennsylvania, 1977)
Clark v. Hoerner
525 A.2d 377 (Supreme Court of Pennsylvania, 1987)
Church v. Tentarelli
953 A.2d 804 (Superior Court of Pennsylvania, 2008)
Hood v. Meininger
105 A.2d 126 (Supreme Court of Pennsylvania, 1954)
Florig v. Estate of O'Hara
912 A.2d 318 (Superior Court of Pennsylvania, 2006)
Lampus v. Lampus
660 A.2d 1308 (Supreme Court of Pennsylvania, 1995)
Century Indemnity Co. v. OneBeacon Insurance Co.
173 A.3d 784 (Superior Court of Pennsylvania, 2017)
Pledger, P. v. Janssen Pharmaceuticals, Inc.
198 A.3d 1126 (Superior Court of Pennsylvania, 2018)
J.J. DeLuca Co. v. Toll Naval Associates
56 A.3d 402 (Superior Court of Pennsylvania, 2012)
Fazio v. Guardian Life Insurance Co. of America
62 A.3d 396 (Superior Court of Pennsylvania, 2012)
Woullard, D v. Sanner Concrete
2020 Pa. Super. 263 (Superior Court of Pennsylvania, 2020)
Young, J. v. Lippl, J.
2021 Pa. Super. 56 (Superior Court of Pennsylvania, 2021)