Jack Frost Construction v. Bertothy, J.

CourtSuperior Court of Pennsylvania
DecidedOctober 6, 2023
Docket208 WDA 2022
StatusUnpublished

This text of Jack Frost Construction v. Bertothy, J. (Jack Frost Construction v. Bertothy, J.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jack Frost Construction v. Bertothy, J., (Pa. Ct. App. 2023).

Opinion

J-A02017-23

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

JACK FROST CONSTRUCTION, INC. : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : JASON T. BERTOTHY AND DANA A. : BERTOTHY : : No. 208 WDA 2022 Appellants :

Appeal from the Judgment Entered February 8, 2022 In the Court of Common Pleas of Clearfield County Civil Division at No(s): 2019-541-CD

BEFORE: BOWES, J., MURRAY, J., and PELLEGRINI, J.*

MEMORANDUM BY BOWES, J.: FILED: October 6, 2023

Jason T. Bertothy and his wife, Dana A. Bertothy (collectively “the

Bertothys”), appeal from the $40,5564.26 judgment entered on the verdict in

favor of Jack Frost Construction, Inc. (“Jack Frost”). We vacate the judgment

and remand for further proceedings.

I. Facts and Procedural History

The certified record supports the following history of this case as

outlined in the findings of fact enumerated in the trial court opinion and order

entered on August 25, 2021. In November 2017, the Bertothys contracted

with Jack Frost for the construction of a single-family residence (“the

Contract”). The Contract, which was negotiated between the Bertothys and

____________________________________________

* Retired Senior Judge assigned to the Superior Court. J-A02017-23

Jack Frost’s owner, Billy Joe Sallurday, specifically referenced, but did not

incorporate, a September 12, 2017 estimate (“the Estimate”) that outlined a

flat fee for materials, plans and labor totaling $480,107.00.1 The Contract

provided that payments were due within ten days of the submission of an

invoice and that Jack Frost retained the right to cease work if payments were

not timely received. In this vein, the contract included a provision that

calculated interest at a rate of 1.5% per month or 18% per year. Neither the

Contract nor the Estimate stated a completion date, but a proviso in the

Estimate advised that the arrangement was “contingent upon . . . delays

beyond [the contractor’s] control.” Estimate, 9/12/17, at 2.

Over the ensuing year, construction was plagued by delays associated

with winter weather, an abnormal amount of rainfall, and the failure of a sub-

contractor, namely the Bertothys’ son, Trent, to excavate the site, grade the

driveway, and dig the trenches for housing electrical and water supply lines.

The various delays prompted an ongoing dispute between the parties over the

pace of construction and the use and storage of construction materials at the

site.

Between the start of the project in November 2017 and July 2018, the

Bertothys satisfied all four of the periodic invoices that Jack Frost submitted

totaling $122,357.00. However, the Bertothys withheld payment on the fifth

1 While the Contract states the incorrect date of the Estimate, the parties do not dispute that they agreed to the Estimate provided on September 12, 2017.

-2- J-A02017-23

pay application (“Pay Application No. 5”) for $63,060.26 due to what they

claimed were unresolved construction defects that they believed Jack Frost

had failed to remedy, and because that application requested payment for

work that had not been completed. While the trial court ultimately determined

that Jack Frost continued to work on the project despite the non-payment of

Pay Application of No.5, the parties dispute the amount and pace of

construction after July 2018.

On October 4, 2018, the Bertothys’ counsel mailed Jack Frost a cease-

and-desist letter. Prior to receiving the letter, Jack Frost had partially framed

the structure, sheathed the roof, and completed the deck footer, footer,

foundation, and plumbing slab. The concrete work was approved by Pennsafe

Building Inspection Services, LLC. Within six days of issuing the letter, the

Bertothys had the property inspected by David Connelly, a structural engineer,

who observed extensive moisture near the foundation, slab, framing, exterior

walls, and roof trusses. See N.T., 11/5/19, at 102-11, 114-17, 118-19, 120-

26, 130-31. Specifically, Mr. Connelly identified, inter alia, a wet slab and

interior foundation, weather-compromised lumber used in framing and

sheathing, and the accumulation of mold and mildew on the floor joists and

roof trusses. Id. at 108-09, 114-26, 130-31. Overall, he described the

prolonged moisture exposure as,

A lot of wet construction, in a nutshell. Everything seemed to be pretty-well soaked, even the interior. Yes, there was roof sheathing on the structure. There was still water coming through . . . that allowed a lot of water into the interior structure. . . .

-3- J-A02017-23

[T]he exterior sheathing, really seemed to [have] taken on a lot of water.

Id. at 102. The visual inspection was performed approximately six days after

Mr. Sallurday was last on the job site and claimed that he observed no

moisture-related damage when he left. Id. at 138; N.T., 11/4/20, at 48, 70-

71.

On April 1, 2019, Jack Frost sued the Bertothys for breach of contract

due to their alleged failure to satisfy Pay Application No. 5 in accordance with

the Contract. It also sought $13,006.27 for windows that had been purchased

in anticipation of installation. The Bertothys’ answer and new matter included

several counterclaims including breach of contract based upon Jack Frost’s

alleged failure to perform in a timely and workmanlike manner. The Bertothys

also pled violations of the Pennsylvania Unfair Trade Practices and Consumer

Protection Law (“UTPCPL”) sections 201-2(4)(vii), (xiv), and (xxi), which

relate to a business’s representation of goods and services, compliance with

written warranties, and fraudulent or deceptive conduct, respectively.2

Following a bench trial over three days between November 2020 and

March 2021, and review of the parties’ proposed findings of fact and

conclusions of law, the trial court found in favor of Jack Frost and awarded it

2 The Bertothys’ counterclaims also included alternative counts of unjust enrichment and negligence. As the Bertothys do not challenge the trial court’s rejection of these counts, we do not discuss them herein.

-4- J-A02017-23

$40,560.26, plus the contractual interest rate, for the unpaid materials and

labor costs outlined in Pay Application No. 5.3

As to the Bertothys’ counterclaims, the court rejected all of the requests

for relief, holding: (1) the issue concerning Jack Frost’s alleged failure to

perform in a timely and workmanlike manner was not ripe because the

Bertothys had not permitted the contractor to fix the potential defects

associated with the incomplete performance prior to issuing the cease-and-

desist letter and taking possession of the worksite; (2) all of the completed

work had been performed in a workmanlike manner; and (3) Jack Frost did

not engage in any of the alleged conduct that purportedly violated the UTPCPL.

This timely appeal followed the denial of the Bertothys’ post-trial

motions and the entry of judgment on the verdict. Both the Bertothys and

the trial court complied with Pa.R.A.P. 1925.

The Bertothys present seven questions for our review, which we re-

ordered for ease of disposition:

1. Whether, under relevant law, the trial court erred in permitting an expert witness to testify at trial who [Jack Frost] failed to disclose or identify during discovery.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ecksel v. Orleans Construction Co.
519 A.2d 1021 (Supreme Court of Pennsylvania, 1987)
Gill v. McGraw Electric Co.
399 A.2d 1095 (Superior Court of Pennsylvania, 1979)
Feingold v. Southeastern Pennsylvania Transportation Authority
517 A.2d 1270 (Supreme Court of Pennsylvania, 1986)
Schreiber v. Republic Intermodal Corp.
375 A.2d 1285 (Supreme Court of Pennsylvania, 1977)
Clark v. Hoerner
525 A.2d 377 (Supreme Court of Pennsylvania, 1987)
Church v. Tentarelli
953 A.2d 804 (Superior Court of Pennsylvania, 2008)
Hood v. Meininger
105 A.2d 126 (Supreme Court of Pennsylvania, 1954)
Florig v. Estate of O'Hara
912 A.2d 318 (Superior Court of Pennsylvania, 2006)
Lampus v. Lampus
660 A.2d 1308 (Supreme Court of Pennsylvania, 1995)
Century Indemnity Co. v. OneBeacon Insurance Co.
173 A.3d 784 (Superior Court of Pennsylvania, 2017)
Pledger, P. v. Janssen Pharmaceuticals, Inc.
198 A.3d 1126 (Superior Court of Pennsylvania, 2018)
J.J. DeLuca Co. v. Toll Naval Associates
56 A.3d 402 (Superior Court of Pennsylvania, 2012)
Fazio v. Guardian Life Insurance Co. of America
62 A.3d 396 (Superior Court of Pennsylvania, 2012)
Woullard, D v. Sanner Concrete
2020 Pa. Super. 263 (Superior Court of Pennsylvania, 2020)
Young, J. v. Lippl, J.
2021 Pa. Super. 56 (Superior Court of Pennsylvania, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Jack Frost Construction v. Bertothy, J., Counsel Stack Legal Research, https://law.counselstack.com/opinion/jack-frost-construction-v-bertothy-j-pasuperct-2023.