Stehlin-Miller-Henes Co. v. City of Bridgeport

117 A. 811, 97 Conn. 657, 1922 Conn. LEXIS 120
CourtSupreme Court of Connecticut
DecidedAugust 4, 1922
StatusPublished
Cited by16 cases

This text of 117 A. 811 (Stehlin-Miller-Henes Co. v. City of Bridgeport) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stehlin-Miller-Henes Co. v. City of Bridgeport, 117 A. 811, 97 Conn. 657, 1922 Conn. LEXIS 120 (Colo. 1922).

Opinion

Wheeler, C. J.

The report of the committee found the following facts: On January 23d, 1914, Durkin and contracted with defendant city to construct a high-school building exclusive of the heating, ventilating, plumbing and electric work, on or before *659 April 23d, 1915. On January 14th, 1914, plaintiff made two contracts with defendant, one to do the electric work on or before April 23d, 1915, under a penalty of $10 per day for delay, the other to do the heating and ventilating work on or before May 23d, 1915, under a penalty of $25 per day for delay. Each of the contracts made with plaintiff contained this provision: “The work to be installed as fast as the building is in condition for it to be done, and this contractor is not to cause any delay in the progress of the work of the general contractor.”

There was a delay, in the spring and summer of 1914, of approximately three months, in the work of the general contractors, Durkin and Laas, but after work was fairly started it progressed with reasonable regularity. In February, 1915, there was a delay of a week due to the general contractors. In September, 1914, defendant took the contract from Durkin and Laas and made a new contract with Shaughnessey to complete the work, and at this time there was a delay of three weeks. The building was practically completed about February 9th, 1916. All of the plaintiff’s work under its two contracts was practically completed in November, 1915. In paragraph thirteen of his report, the committee finds that after the operations were actually under way in the fall of 1914, the work progressed under Durkin and Laas in the normal and usual manner in which such buildings are erected, although somewhat slowly, and after Mr. Shaughnessey took charge it progressed in the normal and usual manner in which such buildings are erected. The building had not reached such a stage of construction as to permit the plaintiff to complete its two contracts on or before the dates of completion provided therein. The complaint contained two counts, the first for $166.59 alleged to be due for work done under the contract for the *660 electric work and for damages for delay in preventing plaintiff from completing this work within the time provided therein; the second for a balance of $327.80 alleged to be due on the heating and ventilating contract and for damages for delay in completing this contract within the time provided therein. The fourth, fifth and sixth paragraphs of each count were identical, except as to the date of completion, viz: “4. After the execution and delivery of said contract, the defendant failed for a long time to provide a building for the plaintiff to do its work in, and failed to keep the construction of the building in a proper state of forwardness so that the plaintiff could proceed with its work, and delayed the plaintiff in beginning its work, and after the plaintiff had begun its work the defendant prevented the plaintiff from continuing its work and ordered the plaintiff to cease working and to delay its work. 5. As a result of said acts of the defendant the plaintiff could not complete its contract within the time fixed by said contract for the completion of the work, namely, on or before April 23d,. 1915, but was delayed until and could not complete its work until said December 1st, 1916. 6. As a result of said acts of the defendant the plaintiff has suffered great loss and damage, in the increased cost of material and labor, the cost of superintendence and supervision during the period beyond said April 23d, 1915, the, loss of the time of the employees of plaintiff due to interruptions and delays in the work, the additional premiums on the bond required to be furnished by the plaintiff, and sundry other expenses and costs incidental to and resulting from said acts of the defendants.” These three paragraphs, with their denial in the answer, presented these questions for the committee to answer in his finding of the facts: 1. Did the defendant delay the plaintiff in its work by failing to keep the construe *661 tion of the building in a proper state of forwardness so that plaintiff could proceed with its work and complete its contracts at the time agreed? 2. As a result of such delay (if proved), did the plaintiff suffer loss and damage in the particulars specified in paragraph six of these counts? The plaintiff’s damages were set forth in eighteen items. As to item one, the committee found that the plaintiff should be allowed $327.80 as an unpaid part of the contract price. Item nine, excess cost of sheet metal $400, due to the delay of the general contractor, the committee allowed. The committee disallowed items ten, eleven and twelve, because it did not appear that there were any written orders from the architect to provide for said extra cost. It disallowed the other thirteen items without specifying the ground of disallowance. The plaintiff filed a remonstrance to the report, a part of which was as follows: “3. It appears from said report that the construction of the building did not progress in such a manner as to permit the plaintiff to complete its contracts within the time limited. 4. It appears from said report that the building was not completed for nearly a year beyond the time fixed in said contracts for the completion of the work required to be performed by the plaintiff under the contracts above referred to, a large part of which delay was due to delays by the general contractors and delays incident to the making of new contracts for the completion of the building in particulars other than the work required to be done by the plaintiff. 5. It does not appear from the report that any of the delays contributing to the delay in the final completion of nearly a year were attributable to the failure of the plaintiff to carry out the contracts above referred to. 6. It appears from said report that the committee has applied an erroneous rule of law to the evidence, in that it appears that he has ruled that the plaintiff *662 cannot recover for damages resulting from delays beyond the time fixed for the completion of his work in said contract, because the building progressed ‘in the normal and usual manner in which such buildings are erected,’ whereas the true rule of law is that the building must progress in such a manner as to permit the plaintiff to complete its contracts within the time set therein for completion.”

The defendant demurred to the remonstrance for the following reasons: “1. It appears from the report of the committee that the plaintiff was delayed in the performance of its work under said contracts, due to the manner in which the general contractors performed the work, and that the committee allowed the plaintiff just damages for whatever loss it suffered as a consequence thereof. 2. It appears from the transcript of the evidence that defendant’s Exhibit A was properly admitted in evidence.” The court sustained the demurrer, accepted the report, and rendered judgment for the $727.80, and the appeal brings up the ruling upon the demurrer.

The defendant offered in evidence, and the committee admitted, a statement of the plaintiff’s claims which differed from the claims made by the plaintiff on the hearing. Its admission was objected to on the ground that it had been made with a view to a compromise. On the record it does not appear to have been so made, and the adverse ruling of the committee is therefore conclusive upon this point.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gm Testani Construction Co. v. Delcegno, No. Cv-92-0291747s (Oct. 25, 1994)
1994 Conn. Super. Ct. 10872 (Connecticut Superior Court, 1994)
Rostenberg-Doern Co. v. Weiner
552 A.2d 827 (Connecticut Appellate Court, 1989)
Janow v. Town of Ansonia
525 A.2d 966 (Connecticut Appellate Court, 1987)
Seal Audio, Inc. v. Bozak, Inc.
508 A.2d 415 (Supreme Court of Connecticut, 1986)
Dobson v. Rutgers, State University
384 A.2d 1121 (New Jersey Superior Court App Division, 1978)
Hartford Electric Applicators of Thermalux, Inc. v. Alden
363 A.2d 135 (Supreme Court of Connecticut, 1975)
Studer v. Rasmussen
344 P.2d 990 (Wyoming Supreme Court, 1959)
Hopewell Baptist Church v. Craig
124 A.2d 220 (Supreme Court of Connecticut, 1956)
Northeastern Gas Transmission Co. v. Lapham
117 A.2d 441 (Connecticut Superior Court, 1955)
Frank T. Hickey, Inc. v. Los Angeles Jewish Community Council
276 P.2d 52 (California Court of Appeal, 1954)
Livolsi Construction Co., Inc. v. Shepard
48 A.2d 263 (Supreme Court of Connecticut, 1946)
Andrews v. Cox
17 A.2d 507 (Supreme Court of Connecticut, 1941)
Byrne v. Bellingham Consolidated School District No. 301
108 P.2d 791 (Washington Supreme Court, 1941)
Lyon v. Wilcox
119 A. 361 (Supreme Court of Connecticut, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
117 A. 811, 97 Conn. 657, 1922 Conn. LEXIS 120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stehlin-miller-henes-co-v-city-of-bridgeport-conn-1922.