Studer v. Rasmussen

344 P.2d 990, 80 Wyo. 465, 1959 Wyo. LEXIS 46
CourtWyoming Supreme Court
DecidedOctober 20, 1959
Docket2853
StatusPublished
Cited by14 cases

This text of 344 P.2d 990 (Studer v. Rasmussen) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Studer v. Rasmussen, 344 P.2d 990, 80 Wyo. 465, 1959 Wyo. LEXIS 46 (Wyo. 1959).

Opinion

*470 OPINION

Mr. Chief Justice BLUME

delivered the opinion of the court.

This is an action brought by Willard N. Rasmussen and Clifford E. Rasmussen against R. J. Studer, doing business as Studer Construction Company, to recover an amount due on a subcontract and for damages for delay in connection therewith. Subsequently the Stud-er Construction Company was added as a defendant.

The defendants had a contract with the United States Government for constructing water and sewer systems, paved roads and electrical distributing system *471 at the Glasgow Air Force Base near Glasgow, Valley County, Montana. Part of this work relating to the construction of roads was subcontracted by the defendants to the plaintiffs in this case. Under that contract the subcontractors agreed to furnish all labor, materials, equipment and supplies, and to perform all work as described below. It was agreed that the work, labor and materials to be done, performed or furnished by the subcontractors were as follows:

“Item No. 7. 3,760 Cu. Yd. Leveling Course, 1½ inch minus (in place)

“Item No. 8. 30,300 Cu. Yd. Base Course, 1½ inch minus (in place)

“Item No. 10 (Part). 1,670 Ton Mineral Aggregate, (produce and stockpile only.)”

The contractor agreed to pay the subcontractors for performance of the subcontract as follows:

“Unit Price Estimated Amount

“Item No. 7. 3,760 C.Y. § 1.40 $ 5,264.00

“Item No. 8. 30,300 C.Y. 1.00 30,300.00

“Item No. 10. 1,670 Ton 2.00 3,340.00”

It might be mentioned that many months after the times hereinafter stated Item No. 10 was eliminated from the work to be performed on behalf of the Government of the United States but the government agreed to pay and did pay the defendants for 387 tons of mineral aggregate under Item 10 already produced at that time and the defendants herein used 194 tons and 91 tons of this aggregate and agreed to pay the plaintiffs for that at the rate of $3 per ton.

*472 The contract provided that the subcontractors should be bound by the general conditions of the contract between the government and the contractor.

This action was brought on May 15, 1957, in the District Court of Sheridan County. In the first cause of action the plaintiffs claimed judgment for $2,818.04 and interest. This included the sum of $1,000 still'due under items 7 and 8, the amount paid by the government for the 387 tons of mineral aggregate, the amount due for the mineral aggregate used by the defendants themselves and also the sum of $889.04 for a bond furnished by the plaintiffs in accordance with the agreement between the parties.

In the second cause of action plaintiffs claimed damages for delaying the plaintiffs in the performance of their contract for a period from July 15, 1955, to September 15,1955, and also further damages by reason of the fact that they had to perform the contract in cold weather and were delayed in the work by reason thereof.

The court rendered judgment for the plaintiffs on the first cause of action as claimed by the plaintiffs and on the second cause of action found the following facts:

“8. That on July 5, 1955, the Defendant wrote Plaintiffs a letter directing them to move on to the job and commence work thereon by July 11, 1955 at the latest.
“9. That in response to said direction from the Defendant, the Plaintiffs moved their equipment, supplies and labormen from Sheridan, Wyoming, to the jobsite at Glasgow Air Force Base, near the town of Glasgow in- northern Montana, and *473 were ready, able and willing to begin performance under said sub-contract between the parties hereto on the 20th day of July, 1955.
“10. That the approximate value of Plaintiffs’ equipment allocated, moved to and used upon said job was $200,000.00.
“11. That on the said 20th day of July, 1955, and for a period thereafter, extending up until September 12, 1955, the Plaintiffs though ready, willing and prepared to do so, were unable to commence performance of the work to be done by them under said contract between the parties hereto because Defendant had failed to perform preliminary work required of him under his prime contract with the government for the installation of water and sewer utility lines which had to be placed under the streets and roads before the Plaintiffs could commence performance under their sub-contract to place the gravel thereon, a circumstance of which the Defendant was advised and knew.
“12. That by reason of the Defendant’s action in directing- the Plaintiffs to move in upon said job, before the same was in a condition for them to perform under their sub-contract, and by reason of the Defendant’s failure to perform the preliminary work on its part to be done under the prime contract with the government before the Plaintiffs could commence performance, until September 12, 1955, the Plaintiffs were required to, and did, expend in wages for its labormen at the Glasgow Air Force Base, the amount of Three Thousand One Hundred Eighty-Four Dollars and Forty-Two Cents ($3,184.42) during said delay period, commencing July 20, 1955, and ending September 12, 1955, for which Plaintiffs received no benefit; and, for the same reasons and for the same period, were required to hold in readiness upon said job their machinery and equipment necessary to perform the work to be done by them *474 under said sub-contract for which they received no benefit, and for which the reasonable rental value, or return thereon, during said delay period amounted to Twelve Thousand Fifty Seven Dollars and Six Cents ($12,057.06).
“13. That the evidence fails to show that the additional delay of approximately one and one-half months alleged by the Plaintiffs in the completion of the work done under said contract, after the same had been commenced, was entirely due to the Defendant’s action in delaying the commencement of the work to be done under the Plaintiffs’ subcontract until September 12, 1955.”

Judgment for the plaintiffs accordingly was entered upon the first cause of action in the sum of $2,-818.24 and judgment for $15,241.48 on the second cause of action. The court disallowed any damages by reason of the delay claimed by the plaintiffs due to cold weather conditions.

From this judgment the defendants have appealed to this court.

The letter mentioned by the court written by R. J. Studer to the Rasmussens is as follows:

“Billings, 7-5-55
“Whitey Rasmussen,
“Rasmussen Brothers:
“Thanks for returning the signed contract. I am enclosing your copy for your files.
“You can get going up there as soon as you wish to, but don’t figure on later than this week if possible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McMurry Oil Co. v. Deucalion Research, Inc.
842 P.2d 584 (Wyoming Supreme Court, 1992)
Wolin v. Walker
830 P.2d 429 (Wyoming Supreme Court, 1992)
Robinson v. Powers
777 S.W.2d 675 (Missouri Court of Appeals, 1989)
Albrecht v. Zwaanshoek Holding en Financiering, B.V.
762 P.2d 1174 (Wyoming Supreme Court, 1988)
Marcam Mortgage Corp. v. Black
686 P.2d 575 (Wyoming Supreme Court, 1984)
A. A. Baxter Corp. v. Colt Industries, Inc.
10 Cal. App. 3d 144 (California Court of Appeal, 1970)
Zanetti Bus Lines, Inc. v. Hurd
320 F.2d 123 (Tenth Circuit, 1963)
Lichter v. Mellon-Stuart Company
193 F. Supp. 216 (W.D. Pennsylvania, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
344 P.2d 990, 80 Wyo. 465, 1959 Wyo. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/studer-v-rasmussen-wyo-1959.