W.H. Stubbings Co. v. World's Columbian Exposition Co.

110 Ill. App. 210, 1903 Ill. App. LEXIS 610
CourtAppellate Court of Illinois
DecidedOctober 30, 1903
StatusPublished
Cited by21 cases

This text of 110 Ill. App. 210 (W.H. Stubbings Co. v. World's Columbian Exposition Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.H. Stubbings Co. v. World's Columbian Exposition Co., 110 Ill. App. 210, 1903 Ill. App. LEXIS 610 (Ill. Ct. App. 1903).

Opinion

Mr. Presiding Justice Freeman

delivered the opinion of the court.

FTumerous alleged errors are complained of by appellant’s counsel which relate to rulings of the trial court upon the admission of evidence, instructions given in favor of appellee and denying a motion for a new trial. It is insisted that the judgment is contrary to the weight of the evidence and to the law.

It is claimed in behalf of appellee that when the work was completed, appellant applied for final certificates as contemplated, by the contracts, and presented to the assistant chief of construction all of the claims involved in this suit, which were fully considered between the parties; that there had been a change in the plans of the Manufactures Building which caused a very material reduction in the amount of work as originally contemplated by that contract, amounting, it is said, to $10,320.58; and that upon consideration of the claims of appellee for a deduction of this sum from the original contract price, and of the claim of appellant for extra work and damages amounting to about $11,198.90, a compromise and settlement were effected by virtue of which appellee allowed and paid, and appellant accepted the full original contract price, without any reduction for the work not done; and that this was accepted by appellant as a settlement in full of the demands under that contract, to recover which this suit is brought. It is claimed by appellee, therefore, that the final certificate or voucher then paid by appellee was in satisfaction of all claims and demands between the parties, and a bar to future actions by either party, upon these unliquidated demands. On the other hand, appellant’s claim is that the changes in the Manufactures Building, instead of causing a reduction in the amount of work originally contemplated by the contract, compelled appellant to perform work and furnish material to the extent of $2,485 more than was called for by the original contract, plans and specifications. This is a question of fact upon which evidence is conflicting. 'It may be said, however, that the voucher and receipt introduced in evidence refer by their terms to the contract, and do not purport to be in settlement of anything but the written contract.

Appellant’s claims, as stated, arrange themselves in two general classes, and it will not be necessary in the view w-e take of the controversy to consider in detail the items for which recovery is sought. The first class includes claims for extra labor and material not embraced in the contract specifications, but afterward ordered by appellee’s agents in charge of the work; and the second, claims for damages caused mainly by advance in wages, which would not have affected appellant, except by reason of appellee’s failure to nave the buildings ready for appellant to proceed with its work before the expiration of the time provided for its completion in the written contracts.

Under the first of these heads comes the claim for priming on the interior of the Manufactures Building. The contract with appellant for that building called only for work to be done on the exterior. It is, however, claimed by appellant that it put one coat of paint upon the interior pursuant to an oral request made by Mr. Graham, the assistant director of works and assistant chief of construction, who had been put in charge of the buildings and gangs employed thereon, by a written order of his chief, Mr. Burnham, the director of works and chief of construction. The trial court excluded evidence offered to prove this alleged oral contract and what was. said with reference thereto between the parties, as well as testimony tending to prove that appellant had not been paid for that work. The same ruling was applied when appellant sought to show what agreement was made by the assistant chief about payment for a lot of broken glass replaced by appellant; and it is contended that this testimony was competent and should have been admitted. The court’s ruling excluding this evidence is sought to be justified by appellee’s attorneys on the ground that evidence tending to show oral orders given or agreements made was properly excluded because the parties who gave them were not shown to have had authority to 'make any such new contract and bind appellee. There seems, however, to be no dispute that appellant did put this coat of paint on the interior of the building, and did replace a quantity of broken glass.

Prior to the informal opening day, appellant was directed to have all the glass set in the Manufactures Building This was done. On that day the building was occupied by thousands of people, and a large quantity of the glass appears to have been broken. Appellant resumed work the next day and it is said was directed to, and did, replace this broken glass.

It appears that Mr. .Graham was assistant director of works, and was, by written order from Mr. Burnham, who was the director of works for appellee, instructed to “assume charge of all buildings and gangs employed on the same,” and it was ordered that “ superintendents in this service will report directly to him.” It is conceded that Graham was thereafter on the grounds of the defendant company supervising the work and superintending the construction of the buildings, apparently acting with full authority of and from Mr. Burnham, his chief, who is, in the contracts under consideration, spoken of as “ Chief of Construction,” his official title being “ Director of Works.” Graham, his “ Assistant Director of Works,” acted under Burnham's orders as assistant chief of construction in actual charge of these buildings.

It is said by appellee’s attorneys that there is no evidence of “ express authority in Graham or Updike to make a cop tract.” Updike was superintendent of construction of the Manufactures Building under Graham. The original written contract provided that the contractor waived all claims to allowances for extra work unless “ furnished upon a written order signed by the chief or his subordinate duly authorized.” The contract therefore contemplated allowances for extra work upon a written order signed by Graham as assistant chief, if the latter was “ duly authorized; ” and it will scarcely be seriously contended that the order placing him in charge of the buildings and men employed thereon and requiring the superintendents in the building service to report directly to him, was not an authorization to represent and act for the chief in reference to such extra work and materials as should, become necessary to supplement the contract and properly complete the work on the buildings which the contract contemplated. If he had authority to give such order in writing, but gave it orally instead, and the work and material were furnished accordingly and accepted by appellee, the requirement that the order should be in writing will be deemed to have been waived. As said in City of Elgin v. Joslyn, 36 Ill. App. 301, if it was intended to enforce the requirement of a written order against the contractor, it was the duty of appellee’s agent to comply therewith himself. The neglect to do so must be regarded a waiver of the requirement. C. & E. I. R. R. Co. v. Moran, 85 Ill. App. 543, affirmed in 187 Ill. 316-324.

Acceptance of the work done pursuant to such verbal order is equivalent to acquiescence in and ratification of the act of the agent in giving the order.

But some part, at least, of the extra work for which appellant seeks to recover is apparently not within the terms of the written contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mendelson v. Ben A. Borenstein & Co.
608 N.E.2d 187 (Appellate Court of Illinois, 1992)
Amp-Rite Electric Co. v. Wheaton Sanitary District
580 N.E.2d 622 (Appellate Court of Illinois, 1991)
Guarantee Electrical Co. v. State
43 Ill. Ct. Cl. 35 (Court of Claims of Illinois, 1991)
Lippert Brick Contracting v. State
43 Ill. Ct. Cl. 71 (Court of Claims of Illinois, 1991)
K & S Associates, Inc. v. State
43 Ill. Ct. Cl. 117 (Court of Claims of Illinois, 1991)
J. F. Inc. v. State
41 Ill. Ct. Cl. 5 (Court of Claims of Illinois, 1988)
J.F., Inc. v. S. M. Wilson & Co.
504 N.E.2d 1266 (Appellate Court of Illinois, 1987)
J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority
340 N.E.2d 572 (Appellate Court of Illinois, 1975)
John Kubinski & Sons, Inc. v. Dockside Development Corp.
339 N.E.2d 529 (Appellate Court of Illinois, 1975)
Roosevelt University v. Mayfair Construction Co.
331 N.E.2d 835 (Appellate Court of Illinois, 1975)
Consumers Construction Co. v. County of Cook
275 N.E.2d 696 (Appellate Court of Illinois, 1971)
Studer v. Rasmussen
344 P.2d 990 (Wyoming Supreme Court, 1959)
Town of Milford v. O'Neil Bros., Inc.
8 Conn. Super. Ct. 403 (Connecticut Superior Court, 1940)
First Savings & Trust Co. v. Milwaukee County
148 N.W. 22 (Wisconsin Supreme Court, 1914)
Winslow Bros. v. Robinson
173 Ill. App. 84 (Appellate Court of Illinois, 1912)
Headley v. Cavileer
82 A. 908 (Supreme Court of New Jersey, 1912)
Manufacturers' Fuel Co. v. White
130 Ill. App. 29 (Appellate Court of Illinois, 1906)
Hart v. Carsley Manufacturing Co.
116 Ill. App. 159 (Appellate Court of Illinois, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
110 Ill. App. 210, 1903 Ill. App. LEXIS 610, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wh-stubbings-co-v-worlds-columbian-exposition-co-illappct-1903.