Lippert Brick Contracting v. State

43 Ill. Ct. Cl. 71, 1991 Ill. Ct. Cl. LEXIS 61
CourtCourt of Claims of Illinois
DecidedMay 30, 1991
DocketNo. 83-CC-1569
StatusPublished

This text of 43 Ill. Ct. Cl. 71 (Lippert Brick Contracting v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lippert Brick Contracting v. State, 43 Ill. Ct. Cl. 71, 1991 Ill. Ct. Cl. LEXIS 61 (Ill. Super. Ct. 1991).

Opinion

OPINION

Montana, C.J.

The Claimant, Lippert Brick Contracting, brought this claim seeking $24,332.69 in damages incurred due to delays Claimant encountered in the performance of two construction contracts with the Respondent’s Capital Development Board (hereinafter referred to as the CDB). The case was tried over many months by the Commissioner assigned to the case. The cause was consolidated for trial purposes only with claims by Guarantee Electrical Company, Lowry Electric Company, and K & S Associates, Inc.

In July and August of 1978, the CDB awarded two masonry contracts to Lippert Brick, a Delaware corporation, to perform masonry on the Skilled Training Center, Academic Building and Learning Resource Center of the East St. Louis Community College project. The Claimant, upon acceptance of its bid, was ready, willing and able to perform. The CDB in August of 1978 told the contractors to begin the project and authorized contractors to proceed. The project was to start August 30, 1978, and be finished in 730 days. In the contract documents, time was of the essence.

The plans and bid documents required the Claimant to start work on the Skilled Training Center on February 23,1979, and have completed its work on April 20, 1979. For the Academic Building, masonry was to start on April 20, 1979, and be completed on July 13, 1979. The masonry on the Learning Resource Center was to start on May 11, 1979, and be completed on August 10, 1979. Lippert Brick received notice of acceptance of its bid on the Skilled Training Center for $158,038.00 and the certificate of completion was to be before January 22,1980. Claimant received notice of the award on the Academic Building and Learning Resource Center on August 1,1978, and the final completion of the entire building was to be on August 1,1980.

Lippert Brick completed its masonry work within the time frames (length of time) specified in the awards, being eight weeks for the Skilled Training Center, fourteen weeks for the Academic Building, and twelve weeks for the Learning Resource Center. However, the work was not completed during the dates as specified in the project manual. In actuality, Claimant started its work on the Skilled Training Center on August 28,1978, and finished in May of 1980. On the Academic Building, actual masonry work commenced August 1, 1980, and was completed December 31,1981.

It is apparent from the entire record that Lippert Brick caused no delays on this project. The CDB had the obligation to obtain an excavator to begin the project. The project was to start on August 30, 1978. The CDB was unable to obtain a qualified excavator and the excavation was still incomplete over a year after the project began. The CDB’s utter failure to have the excavation start on time and continue as a major problem for over a year was one of the two major delays on the case. Because of the excavation problem, all of the project schedules were off from day one. This had a snowball effect as the delay caused the project to go through four winters rather than the scheduled two winters. Once the project was delayed by the excavation problem, all of the coordination and sequencing was out of sync and the architect/engineer and general contractor were not able to get the project back in sync.

Lippert Brick did everything it could do. They notified the CDB of the delays due to no excavation and the problems of not being able to work outside in the winter and the problems of no heat in the Skilled Training Center. The CDB was unable to clear up these problems and the project was delayed almost two years beyond its scheduled completion date for the entire project.

Because of the delays caused by CDB, the architect/ engineer, and the general contractor, Lippert Brick encountered increased union wages which were not included in their bid. The bid of Lippert Brick was made pursuant to the plans and specifications of the project. The Claimant proved increased costs for the Skilled Training Center of $3,049.00 for bricklayers due to the delays which all can be attributed in the first instance to the CDB’s failure to have the site excavated. A building cannot be built until the hole is dug for the pilings and foundation and the earth compacted. This major delay got the project off to a horrendous start that the architect/engineer and general contractor were incapable of solving. The increase was due to a $.55 per hour increase as of September 1,1979, for bricklayers and as of August 1, 1980, an increase of $1.65 per hour. The other wage increases were proven by exhibits of Claimant.

On the Academic Building and Learning Resource Center, the increase for bricklayers was $10,104.60, for hodcarriers $5,328.75, and for equipment operators $975.80, for a total of $16,409.15. Lippert Brick also claims $4,874.54 for insurance, overhead, and profit. The total damages claimed are $24,332.69.

The testimony is devoid of any blame for delay on Lippert Brick. They caused no delays. In fact, Lippert Brick even did some of their own grading to set up staging which was not their task. They did so however to speed up the masonry work. This project was unusual in that the CDB usually has five prime contractors. In the instant case, they had 36 prime contractors. The contracts were broken down into small contracts so that minority contractors could be used. Such a situation required great coordination skills which were not apparent in the CDB, the architect/engineer, and the general contractor. Once the excavation did not proceed as scheduled, the entire project was ill-fated. The CDB failed to take appropriate steps to obtain a competent excavator and the project suffered. CDB officials admitted it was their obligation to obtain an excavator.

Lippert Brick sued K & S Associates, Inc. in the circuit court of Illinois but dismissed their suit. Lippert’s position was that their contract was with the CDB and not with K & S. Therefore, the proper venue was the Court of Claims. As will be discussed later, Claimant had no obligation to sue K & S and this claim is properly before the Court of Claims. There was considerable testimony and fingerpointing in the joint trial as to the cause of the delays. Other opinions will deal in more detail as to the cause of the delays and liability therefore, but suffice it to say that Lippert Brick was not a cause of the delay. The CDB was a major cause of the delay in allowing the excavation problem to continue so long, having an architect/engineer not up to the job, and failing to terminate K & S Associates, Inc. when it became painfully obvious that the general contractor could not sequence the job once it got off to the bad start. CDB also had at least five project managers over the course of the project for various reasons which contributed to the delays.

It is obvious that the Claimant could not proceed with its masonry work until certain other phases of the construction were completed. There was evidence that the Claimant notified the CDB in writing that delays were occurring and costs were mounting. On April 30, 1979, the CDB was warned by Lippert Brick of the impending wage increases. Other letters by Lippert document the delays and cost increases.

Claimant’s contract was with the CDB. The CDB has the primary responsibility for making the work site available to the contractor in time for the contractor to do the work. As owner, the CDB is legally liable for the contractor to do the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.F., Inc. v. S. M. Wilson & Co.
504 N.E.2d 1266 (Appellate Court of Illinois, 1987)
J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority
340 N.E.2d 572 (Appellate Court of Illinois, 1975)
W.H. Stubbings Co. v. World's Columbian Exposition Co.
110 Ill. App. 210 (Appellate Court of Illinois, 1903)
Egizii Electric, Inc. v. State
32 Ill. Ct. Cl. 93 (Court of Claims of Illinois, 1978)
Ude, Inc. v. State
35 Ill. Ct. Cl. 384 (Court of Claims of Illinois, 1982)
Aurora College v. State
37 Ill. Ct. Cl. 321 (Court of Claims of Illinois, 1985)
Loewenberg/Fitch Partnership v. State
38 Ill. Ct. Cl. 227 (Court of Claims of Illinois, 1986)
Board of Trustees of Southern Illinois University v. State
40 Ill. Ct. Cl. 146 (Court of Claims of Illinois, 1988)
J. F. Inc. v. State
41 Ill. Ct. Cl. 5 (Court of Claims of Illinois, 1988)
Bojko v. State
41 Ill. Ct. Cl. 202 (Court of Claims of Illinois, 1989)
A & H Plumbing & Heating Co. v. State
42 Ill. Ct. Cl. 195 (Court of Claims of Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
43 Ill. Ct. Cl. 71, 1991 Ill. Ct. Cl. LEXIS 61, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lippert-brick-contracting-v-state-ilclaimsct-1991.