A & H Plumbing & Heating Co. v. State

42 Ill. Ct. Cl. 195, 1990 Ill. Ct. Cl. LEXIS 11
CourtCourt of Claims of Illinois
DecidedJune 8, 1990
DocketNos. 86-CC-0929, 87-CC-1318, 89-CC-3279 cons.
StatusPublished
Cited by10 cases

This text of 42 Ill. Ct. Cl. 195 (A & H Plumbing & Heating Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A & H Plumbing & Heating Co. v. State, 42 Ill. Ct. Cl. 195, 1990 Ill. Ct. Cl. LEXIS 11 (Ill. Super. Ct. 1990).

Opinion

Montana, C.J.

Claimants A & H Plumbing and Heating Company, Inc., F. E. Moran, Inc., and Thorlief Larsen & Son, Inc., brought these claims seeking compensation for construction work done for the Respondent’s Capital Development Board (hereinafter referred to as the CDB) on Project 810-072-001, the Oakton Community College.

A & H Plumbing and Heating Company, Inc., filed its claim on October 25,1985. In relevant part, it alleged in its verified complaint the following:

1. On or about September 9, 1977, it was awarded a contract by the Capital Development Board (CDB) to perform certain plumbing work at Oakton Community College, Phase I. A copy of said contract awarding such work is attached hereto and incorporated herein by reference as Exhibit 1.
2. Pursuant to the contract, the original contract price was $698,650.00 for the work to be performed thereunder, but during the course of construction, additions were made increasing the amount of the contract price by an additional $18,678.92 and deductions were made in the amount of $3,756.88 resulting in an adjusted contract price of $713,572.04.
3. The CDB has made payments to A & H in the amount of $675,942.91 leaving an unpaid contract balance due A & H of $37,629.13 after allowing all credits and deductions.
4. A & H has performed all work and all conditions precedent required of it under its contract with the CDB and the aforesaid $37,629.13 is now due and owing to A & H by the CDB.
5. A & H has not assigned or transferred this claim for said unpaid contract balances and is the true owner of the claim now brought against the CDB.
6. Although often demanded, the CDB has failed and refused to pay any portion of the contract balance currently owed to A & H.

F.E. Moran, Inc., filed its claim on December 10, 1986, seeking $30,997.01. In relevant part, F.E. Moran, Inc., alleged in its verified complaint the following:

1. Moran is an Illinois corporation with offices at 2265 Carlson Drive, Northbrook, Illinois.
2. On or about September 9, 1977, Moran and CDB entered into a contract wherein Moran was to furnish certain ventilation and air distribution work at Oakton Community College for which Moran was to be paid the sum of $863,600 (attached and incorporated herein is a copy of said contract).
3. From time to time during the performance of Moran’s duties certain changes in the contract were agreed to by the parties. The total agreed-upon contract price including the agreed-to changes was $893,889.53.
4. Moran has fully and completely performed all of the work agreed to and all of its responsibilities under the contract.
5. CDB has paid Moran $862,892.52.
6. After demand, CDB has refused to pay the remaining unpaid balance of $30,997.01.

Thorlief Larsen & Son, Inc., filed its claim on April 20, 1989, seeking $536,469.63. Thorlief Larsen & Son, Inc., filed a standard lapsed appropriation form complaint alleging that it made demand for payment to the CDB but the demand was refused on the grounds that the funds appropriated for the payment have lapsed. Incorporated in and attached to the form complaint was another complaint wherein the Claimant further explained the nature of the claim. In relevant part, the Claimant made the following verified allegations:

1. This claim is for breach of contract and recovery is sought under section 8(b) of the Court of Claims Act. (111. Rev. Stat., ch. 37, par. 493.8(b).)
2. Claimant is a corporation organized and existing under the laws of the State of Illinois with its principal place of business located in Itasca, Illinois. The Respondent is an agency created by the State of Illinois.
3. As of September 9, 1977, Claimant and Respondent entered into a written contract for the construction of the project described as “General Work Oakton Community College Phase I.” A true and correct copy of the contract is attached hereto and made a part hereof as Exhibit 1.
4. The contract provides that Claimant is to be paid a base contract price of $5,361,780 subject to adjustment for change order additions and deletions and for fees on change order work of assigned contractors.
5. During the course of Claimant’s work on the project, the contract price was adjusted by change order word by a net increased amount of $409,817.59. Of that amount, $370,492.24 represents change orders which have been processed by Respondent and $39,415.35 represents change orders which have not yet been processed by Respondent.
6. In addition, Claimant has earned $4,486.97 in fees on the change order work of contractors assigned to it under the contract.
7. Based upon the foregoing adjustments, the adjusted contract price is $5,776,084.56. To date Claimant has been paid $5,229,735.50 leaving due and unpaid $546,349.06.
8. Claimant has previously submitted on February 2, 1989, and then again on March 13,1989, to the Respondent to the attention first, of Robert Pierce and then of Bruce Boncyzk a request for payment of the $546,349.06. On April 3, 1989, Respondent denied the request because of lapsed appropriations.
9. Respondent’s failure to act and failure to pay the $536,469.63 constitutes a breach of the contract.
10. Claimant has satisfactorily performed its obligations under the contract, or in the alternative, is excused from strict performance.
11. Claimant is the owner of the claim asserted herein by virtue of being a party to the contract.
12. Claimant has made no assignment or transfer of the claim.
13. Claimant is justly entitled to the amount claimed herein after allowing Respondent all just credits.
14. Claimant believes the facts alleged in this complaint to be true.
15. Neither this claim nor any claim arising out of the contract has been previously presented to any person, corporation or tribunal other than the State of Illinois except that Claimant is alleging that, to the extent the contract balance is not paid by Respondent, it is entitled to a set-off in the case entitled Board of Trustees of Community College District No. 535 v. Perkins & Will Architects, Inc., docketed in the circuit court of Cook County, Illinois, as No. 82 L 3456. No credits on account of the allegation of set-off have yet been realized.

Attached to this complaint were various letters and documents supporting the allegations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Cape & Sons Co. v. State
52 Ill. Ct. Cl. 322 (Court of Claims of Illinois, 2000)
Fru-Con Corp. v. State
50 Ill. Ct. Cl. 50 (Court of Claims of Illinois, 1996)
De Leo v. State
46 Ill. Ct. Cl. 256 (Court of Claims of Illinois, 1993)
All States Painting, Inc. v. State
43 Ill. Ct. Cl. 231 (Court of Claims of Illinois, 1991)
Guarantee Electrical Co. v. State
43 Ill. Ct. Cl. 35 (Court of Claims of Illinois, 1991)
Lowry Electric Co. v. State
43 Ill. Ct. Cl. 52 (Court of Claims of Illinois, 1991)
Lippert Brick Contracting v. State
43 Ill. Ct. Cl. 71 (Court of Claims of Illinois, 1991)
K & S Associates, Inc. v. State
43 Ill. Ct. Cl. 117 (Court of Claims of Illinois, 1991)
Altman Construction Co. v. State
44 Ill. Ct. Cl. 7 (Court of Claims of Illinois, 1991)
Thorlief Larsen & Son, Inc. v. State
43 Ill. Ct. Cl. 334 (Court of Claims of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
42 Ill. Ct. Cl. 195, 1990 Ill. Ct. Cl. LEXIS 11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-h-plumbing-heating-co-v-state-ilclaimsct-1990.