James Cape & Sons Co. v. State

52 Ill. Ct. Cl. 322, 2000 Ill. Ct. Cl. LEXIS 1
CourtCourt of Claims of Illinois
DecidedMarch 23, 2000
DocketNo. 96-CC-2899
StatusPublished

This text of 52 Ill. Ct. Cl. 322 (James Cape & Sons Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Cape & Sons Co. v. State, 52 Ill. Ct. Cl. 322, 2000 Ill. Ct. Cl. LEXIS 1 (Ill. Super. Ct. 2000).

Opinion

OPINION

Frederick, J.

This cause comes before the Court on Claimant, James Cape & Sons Co.s, verified complaint against Respondent, State of Illinois. The Court’s jurisdiction is pursuant to section 8(b) of the Court of Claims Act. (705 ILCS 50578(b) (1996).) The complaint includes nine counts with a combined prayer seeking an award of $1,870,747.69 for damages allegedly incurred by Claimant arising out of the performance of highway construction contract no. 86399 (hereinafter referred to as “contract”) between Claimant and the Department of Transportation (hereinafter referred to as “IDOT”). Claimant was awarded the contract on its bid of $10,593,467.22 for the construction of improvements to F.A.I. Route 80 in Grundy County. The work included the removal of existing pavement, recycling existing pavement into sub-base shoulders, subgrade preparation, and reconstruction of 6.25 miles of continuously reinforced Portland cement concrete pavement with Portland cement concrete shoulders for Interstate 80 located between Seneca and Morris, Illinois.

The contract required completion of most of the work and that the roadway be reopened on or before October 30,1993. The contract included two provisions, one being an assessment of liquidated damages against Claimant in the amount of $15,000 per day for each day after October 30, 1993, that the work was not completed, and the other being an incentive payment plan for payments to Claimant in the amount of $15,000 per day for each day, not to exceed 30 days, that the work was completed on or before October 30, 1993. The roadway was opened to traffic on October 27, 1993.

Claimant alleges that certain events, as listed in paragraph 16 of its complaint, cumulatively acted to increase the Claimant’s cost to perform the work by $1,870,747.69 and delayed opening of the roadway by 64 days. A summary of the nine-count complaint with a breakdown of alleged damages is as follows:

* Count I-$6,549.88 for direct costs of expanded traffic control;

* Count II-$42,227.67 for direct costs to perform additional lime modified soils;

s Count III-$477,429.19 for direct costs to perform earth excavation (special);

* Count IV-$12,254.01 for additional cement in drainage layer;

* Count V-$24,200 for additional quantity of drainage layer material;

* Count VI-$127,390.50 for width, depth and deductions for mainline concrete pavement;

” Count VII-$ 19,126.99 for improper rejection of pavement under Nettle School Road;

# Count VIII-$260,136.27 for direct costs of abnormally and unusually severe weather; and

* Count IX-$901,244.88 for acceleration and delay costs.

The cause was tried by our Commissioner in a three-day trial which was conducted February 9-11,1998.

On February 9, 1998, the “Narrative Section,” pages 11-42 of the departmental report (of the report volume), was ruled to be inadmissible pursuant to section 790.140 of the Court of Claims Regulations. (74 Ill. Adm. Code 790.140.) The exhibits volume of the departmental report was not affected by this ruling and all exhibits offered by Respondent as a part of the departmental report were admitted into the record. Respondent filed its motion to reconsider and.vacate the ruling and Claimant filed a response. Oral arguments on the motion were held. Claimants post-hearing memorandum was filed on October 15, 1998. On February 23, 1999, the Court entered an order denying respondents motion to reconsider and vacate.

At trial, Claimant presented four witnesses. The witnesses were: William Robert Cape, president and a stockholder of Claimant; James Sponem, an employee of Claimant during the bidding and work on the contract; Stanley E. Grabski, a project review engineer for IDOT; and Richard Ott, president of Trans Con Consulting, a construction management consulting firm, who was Claimants opinion witness.

The Respondent presented five witnesses. They were: Wayne Lyle Phillips, a physical test engineer for IDOT; Dan L. Mestelle, construction engineer for IDOT at the time of the contract; Ken R. Lang, area-supervising engineer for IDOT during the Claimant contract; Chris Manor, project manager for Claimant during the project; and Stanley E. Grabski.

William Cape was presented by Claimant as a witness in rebuttal. The trial record also consists of numerous documents. Both parties have filed briefs; however, neither party cited any case authority.

The Facts

Contract no. 86399 was advertised in the department service bulletin dated December 11, 1992, for letting to be held on January 8, 1993. Prior to formal advertisement, the department held a pre-bid conference on November 16,1992, in order to provide advance information to potential bidders about the work to be performed.

Claimant is a Wisconsin corporation that has been engaged in the construction industry since the 1880s. Claimant is experienced in concrete paving and reconstruction, but also performs earthwork, concrete crushing and building construction. Prior to this contract, Claimant had worked on 15 to 20 interstate reconstruction projects throughout the country.

The contract was subject to the standard specifications for road and bridge construction adopted July 1, 1988 as supplemented pursuant to the contract check sheet for supplemental specifications and recurring special provisions adopted December 2, 1991. The contract includes the plans and special provisions.

The project was to be accomplished in two stages. The eastbound lanes of 1-80 would be diverted onto the westbound lanes in a two-way, two-lane pattern. Traffic diverted would cross over by means of a temporary roadway between the eastbound and westbound lanes. The reverse process would later direct westbound traffic into the eastbound lanes by means of a second temporary cross-over.

The contract was established on February 16, 1993, when IDOT accepted and executed the contract. The special provisions provided for a completion date of October 30, 1993, and advised the contractor that said completion date was based on an expedited work schedule. The special provisions provided for liquidated damages of $15,000 for each day beyond October 30, 1993, during which the work remained incomplete and allowed for incentive payment in the same amount for each day of early completion up to 30 days.

A portion of the special provisions provides, in part:

“Should the contractor be delayed in the commencement, prosecution or completion of the work for any reason, there shall be no extension of the incentive payment calculation date even though there may be granted an extension of time for completion of the work unless significant extra work is added to the contract by the Department.”

Article 108.09(b) provides that timely completion is an essential element of the contract and defines the circumstances allowing for an extension of the completion date:

“108.09 Determination and Extension of Contract Time.
# O #

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walsh v. State
24 Ill. Ct. Cl. 441 (Court of Claims of Illinois, 1964)
Fruin-Colnon Contracting Co. v. State
26 Ill. Ct. Cl. 138 (Court of Claims of Illinois, 1967)
James McHugh Construction Co. v. State
27 Ill. Ct. Cl. 232 (Court of Claims of Illinois, 1969)
Ude, Inc. v. State
35 Ill. Ct. Cl. 384 (Court of Claims of Illinois, 1982)
Loewenberg/Fitch Partnership v. State
38 Ill. Ct. Cl. 227 (Court of Claims of Illinois, 1986)
Johnson County Asphalt, Inc. v. State
39 Ill. Ct. Cl. 36 (Court of Claims of Illinois, 1987)
J. F. Inc. v. State
41 Ill. Ct. Cl. 5 (Court of Claims of Illinois, 1988)
A & H Plumbing & Heating Co. v. State
42 Ill. Ct. Cl. 195 (Court of Claims of Illinois, 1990)
Dimmitt & Owens Financial, Inc. v. Department of Children & Family Services
44 Ill. Ct. Cl. 25 (Court of Claims of Illinois, 1991)
Davinroy v. State
44 Ill. Ct. Cl. 268 (Court of Claims of Illinois, 1991)
Illinois Constructors Corp. v. State
45 Ill. Ct. Cl. 124 (Court of Claims of Illinois, 1993)
Gordon v. State
47 Ill. Ct. Cl. 5 (Court of Claims of Illinois, 1995)
Fru-Con Corp. v. State
50 Ill. Ct. Cl. 50 (Court of Claims of Illinois, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
52 Ill. Ct. Cl. 322, 2000 Ill. Ct. Cl. LEXIS 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-cape-sons-co-v-state-ilclaimsct-2000.