Davinroy v. State

44 Ill. Ct. Cl. 268, 1991 Ill. Ct. Cl. LEXIS 29
CourtCourt of Claims of Illinois
DecidedOctober 28, 1991
DocketNo. 89-CC-2162
StatusPublished
Cited by2 cases

This text of 44 Ill. Ct. Cl. 268 (Davinroy v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davinroy v. State, 44 Ill. Ct. Cl. 268, 1991 Ill. Ct. Cl. LEXIS 29 (Ill. Super. Ct. 1991).

Opinion

OPINION

Raucci, J.

Claimant alleged that he entered into a contract with the State of Illinois Department of Transportation (Department) to be the general contractor to complete a project at the Bowman Avenue pump station in East St. Louis, Illinois. He further alleged that the contract provided for liquidated damages in the event of delays caused by the Claimant. The project was delayed 138 working days and the Department withheld liquidated damages from the Claimant. The Claimant alleged that he did not cause the delays. Claimant seeks $38,640.00 which he claims the Department improperly withheld pursuant to the contract.

The purported brief of Claimant is of little help to the Court in resolving the issues in the case. The Department’s failure to file a brief in support of its position is also not conducive to the resolution of the case. However, the Court will proceed to a decision in this case without the benefit of substantial input from the parties.

The Facts

The Claimant was awarded a contract with the State of Illinois on May 15,1980, to modify the Bowman Avenue pumping station in East St. Louis, Illinois. The work on the contract began on July 10, 1980. Claimant was the general contractor on the project. The project called for replacing and installing larger pumps in the station and to install a generator that would automatically start when power failed at the station. The pumping station kept highways, Routes 70 and 40, clear of water that would come onto a depression in the land.

Because the possibility existed that a vehicle with flammable liquids could overturn on the depressed area and flammables could enter the pumping station, a foam system with a sensor had to be installed. The original pumping station did not have this protection.

The project began in 1980 and ended in 1986. The total contract price was $1,680,214.00. A change order increased the total amount by $92,675.00. The Claimant’s company was involved in a portion of the work. Subcontractors were also used and Dron Electric had a contract for about 50% of the work.

When Claimant received final payment, the Illinois Department of Transportation assessed a penalty against Claimant. The penalty was for 138 working days and appears as liquidated damages in the Department’s authorization of contract charges. The penalty totaled $38,640.00. The penalty was for liquidated damages as defined in article 108.10 of the standard specifications. There were 160 working days assigned to the project. The project took 298 working days. Claimant’s Exhibit No. 1 indicates that Claimant concurred in the processing of the deduction. Claimant believed this agreement to concur still allowed Claimant to sue in the Court of Claims to recover the monies withheld.

Claimant testified the 138 days of delay were not within his control. Claimant asserts that section 108.04, section 5 does not allow working days to be charged against Claimant’s firm for conditions such as strikes, acts of God, problems with supplies, subcontractors, and other things out of his company’s control. Claimant believed the cause of the delays was attributable to Dron Electric and not Claimant. Claimant had problems with Dron Electric who was the supplier of the foam system. They also had problems with the sheet metal company that had the ventilating system contract. Claimant testified he brought the problems with Dron Electric to the Department’s attention. At some point, he also discussed bringing in a different electrical contractor to take over for Dron. Dron responded by indicating if anyone worked on their equipment, all warranties and guarantees would be revoked. They also threatened that if anyone took over Dron’s work, that this would constitute acceptance of Dron’s work. Dron Electric provided Claimant with a letter dated July 26, 1984, indicating a response to IDOT’s questions on the project. The response indicates some problems were Claimant’s responsibility and others were Dron s responsibility.

Claimant admitted that as general contractor he was responsible for the work of the subcontractors. Claimant also admitted the contract ran over about four years from the time it was to be completed. The Department of Transportation had early in the contract advised the Claimant that Claimant was not providing progress schedules as required in a timely fashion. The Department sent numerous letters to Claimant which showed the Department’s concern at the rate of the completion of the contract. The Department also sent Claimant correspondence indicating they had not received specifications for approval of equipment from Claimant as required.

Claimant testified that his work and responsibilities as contractor on this job did not depend upon Dron Electric completing work. It was an unusual contract in that the electrical part of the contract was 50%. The electrical end of the contract called for a longer completion time than Claimant’s own work did.

Claimant had 160 working days to complete his work. However, the Department cut off working from the first freeze until April or May. Claimant also testified he warned the Department at the pre-construction meeting that the supplier of the pumps could not manufacture the pumps in time.

While the contract ran over four years, Claimant was only penalized 138 working days. He believed that 98% of the 138 days was the fault of the suppliers and subcontractors. Dron Electric was accountable for 90% of the delay in Claimant’s opinion. Fairbanks-Morris Company, the supplier of the pumps, had some blame for the delay as a pump they provided failed and had to be taken out. Claimant believed that the sheet metal provider was two to three percent responsible for the delay. Claimant admitted that he was responsible for two to three percent of the delay.

The Respondent rested on the departmental report. The departmental report indicates that a pre-construction conference was held on June 11,1980. The Claimant was advised that he should specifically state what documentation was required from the manufacturer when ordering materials and he was informed that materials such as pumps must be approved by the district engineer prior to use on the project. On July 18, 1980, the Claimant was advised by the Department of the importance of a progress schedule and of equipment submittals. On July 31, 1980, the Claimant was again advised of the importance of a progress schedule and he was advised that the Department’s contract was solely with Claimant, and that Claimant was responsible for the work under the contract, the scheduling of subcontractors, and the obtaining of proper documentation.

The progress schedules submitted by Claimant were late and did not contain the proper detail and documentation. These inadequacies contributed to the delay on the project. The Department sent numerous letters to Claimant expressing concern for the completion of the project within the days assigned thereto. The Department also had numerous meetings with Claimant in this regard. On January 21, 1983, the Department requested Claimant to state his position on the delays and the Department’s assessment of working days in writing. The Claimant made no response. The Department continued assessing working days to the project. However, the Department’s letter of March 9,1983, indicates the following, in respect to Claimant’s performance of the contract,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Cape & Sons Co. v. State
52 Ill. Ct. Cl. 322 (Court of Claims of Illinois, 2000)
Genie Construction Co. v. State
51 Ill. Ct. Cl. 153 (Court of Claims of Illinois, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
44 Ill. Ct. Cl. 268, 1991 Ill. Ct. Cl. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davinroy-v-state-ilclaimsct-1991.