Loewenberg/Fitch Partnership v. State

38 Ill. Ct. Cl. 227, 1986 Ill. Ct. Cl. LEXIS 50
CourtCourt of Claims of Illinois
DecidedJune 11, 1986
DocketNo. 84-CC-0474
StatusPublished
Cited by17 cases

This text of 38 Ill. Ct. Cl. 227 (Loewenberg/Fitch Partnership v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loewenberg/Fitch Partnership v. State, 38 Ill. Ct. Cl. 227, 1986 Ill. Ct. Cl. LEXIS 50 (Ill. Super. Ct. 1986).

Opinion

Montana, C.J.

The Claimant filed its complaint against the State of Illinois on August 24, 1983. The original complaint sought $116,826.05 in damages based on a contract claim. The Claimant filed an amended complaint on March 28, 1984, seeking $127,417.25 in damages on its contract claim. Trial was held in this cause, the parties have fully briefed the issues, and Commissioner Robert Frederick has filed his report.

The claim is for additional work for certain architectural services for the construction of the Illinois Department of Agriculture office and laboratory building located on the Illinois State fairgrounds in Springfield, Illinois. The contracts which are in evidence were entered into on May 3, 1976, for the original contract, and August 8, 1978, for the revised contract. Certain modifications of the contract are also in evidence.

The State of Illinois did not file an answer but has apparently relied on Rule 10 of the Rules of the Court of Claims to enter a general denial to the complaint.

The claims of the Claimant are listed in its bill of particulars and will be addressed hereinafter in this report by their L/F number. The claims are for AGFX1 through AGFX-32. AGFX numbers 17, 19 and 22, totaling $2,696.40, are not at issue in this case pursuant to paragraph 6 of the amended complaint, wherein it was alleged the Respondent had paid or had agreed to pay these three small claims.

The Facts

The Claimant was the architect/engineer for the construction of the Illinois Department of Agriculture office and laboratory building. Ralph Hahn & Associates were its engineers for the project. The Capital Development Board hired its own separate construction manager. The project was supposed to take 22 months to complete but ended up taking close to five years. The Claimant is seeking only additional on-site time which it feels is mandated by the contract. It is not claiming any additional monies for contract administration. It is also claiming payment for extra work which was requested by the Capital Development Board. These items were billed to the Capital Development Board with documentation. Claimant was advised that there was no money to pay these claims. It could not document any deductions from contractors to generate any more monies and had to file a claim with the Court of Claims.

Frank Bernstein, the supervisor of construction management with the Capital Development Board (CDB hereinafter), was called as an adverse witness by Claimant. He had been in charge of the project for the agriculture building, and he is a registered architect. The project was the construction of a building of structural steel and masonry to house offices and laboratories with 150,000 square feet. The projects also included installation of high-tech solar heating and cooling.

The building was to be built at one site but had to be relocated due to subsurface mining problems. The building was built on the southwest portion of the Illinois State fairgrounds. The Claimant was the A/E, and Ralph Hahn & Associates were the consulting engineers on the project. The general contractor was C. Iber & Sons. Claimant’s exhibit No. 3 is the base contract between Claimant and Respondent. It included $76,858.00 for on-site observation. A modification of Number 4 was made which added $81,000.40, $10,129.50 of which was for an observer. The original contract had a full-time observer for $56,056.00. A second part-time observer was budgeted at $20,258.00. These positions were for 22 months. Mod 4 added a second observer for one day per week. With all modifications there was budgeted a total of a first observer for 32 months, five days a week, and a second observer three days a week for 22 months. A total of $112,716.15 was budgeted for on-site observation to March 31, 1983. The total amount budgeted was spent.

Section 3-3.2 of the contract allows for additional compensation beyond the contract completion date. The A/E absorbs the first 60 days beyond the completion time and the CDB is obligated to pay additional amounts if the delay is not the fault of the architect or engineer.

This project was started in August of 1978, was scheduled to be completed 22 months later in June of 1980, but was finally completed in June of 1983. The Claimant and Ralph Hahn & Associates presented exhibits Nos. 9, 10 and 11 to request additional compensation. These exhibits included the request and background information.

The A/E and CDB set the anticipated construction time. The completion time on this project was extended when the solar application was put into the contract. The A/E had input into this extension.

The contract was between the State of Illinois and Loewenberg & Loewenberg. The State had no contract with Ralph Hahn & Associates. Ralph Hahn & Associates were hired by Loewenberg & Loewenberg, the Claimant herein. C. Iber & Sons, the general contractor, did a very poor job of contractor coordination. The first observer was to be there every day. The second observer was there as necessary for specific problems. Mr. Bernstein was later recalled as an adverse witness and testified in summary as follows:

An engineer bills the architect and the architect bills the CDB in the normal course of events. The claims in this case were made by Loewenberg to the CDB on June 28,1983. The CDB requested additional documentation and supplementary information was given to CDB. On the claims for which Loewenberg was making a request for payment, the work actually was done by its subcontractor, the consulting engineer, Ralph Hahn & Associates. AGFX 17, 19 and 22 were paid by CDB to Loewenberg through deductions from contractors. There was money available to pay the other claims. (RP 242.) This would have been through a methodology of proving a claim to deduct money from contractors causing the delays. (RP 243.) This is through the “standard documents for construction” which is referred to in the contract. However, in paragraph 3.8, the contract states that payments withheld from contractors shall not affect the A/E’s right of payment. Other than monies from deductions from contractors there was no money available in the budget to pay the claims of Loewenberg. (RP 245.) The architect is charged with the duty to administer the standard documents of construction. The CDB may withhold payments in whole or in part if it reasonably determines that the contractor’s work is not in accordance to the contract or plans. (RP 248.) These claims were paid to the A/E (17, 19, 22) because the A/E documented to CDB that the specific contractor was at fault by clear evidence.

Mr. Bernstein testified that all those claims still existing in AGFX 1-23 were not paid because it was part of the responsibility of the A/E to administer these types of items under the basic contract. The A/E did not substantiate the claims. They submitted man hours without specific allocations as to time of incident and what it was for.

The CDB did not make further deductions from contractors because the documentation was not qualitative enough, (RP 261.)

Ralph Hahn testified in summation as follows:

He is president of Ralph Hahn & Associates and they are consulting engineers. They were the mechanical, electrical and civil engineers for this project. They were hired by Loewenberg & Loewenberg.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burrink Commercial Services v. New Life Covenant Church
2024 IL App (1st) 220778-U (Appellate Court of Illinois, 2024)
James Cape & Sons Co. v. State
52 Ill. Ct. Cl. 322 (Court of Claims of Illinois, 2000)
Boyd Bros. v. State
52 Ill. Ct. Cl. 191 (Court of Claims of Illinois, 1998)
Fru-Con Corp. v. State
50 Ill. Ct. Cl. 50 (Court of Claims of Illinois, 1996)
McCarthy Brothers Co. v. State
47 Ill. Ct. Cl. 15 (Court of Claims of Illinois, 1995)
Vogt v. Bartels-Meyer
636 N.E.2d 1185 (Appellate Court of Illinois, 1994)
Graham, O'Shea & Hyde v. State
44 Ill. Ct. Cl. 175 (Court of Claims of Illinois, 1992)
All States Painting, Inc. v. State
43 Ill. Ct. Cl. 231 (Court of Claims of Illinois, 1991)
La Salle National Bank v. State
43 Ill. Ct. Cl. 266 (Court of Claims of Illinois, 1991)
Guarantee Electrical Co. v. State
43 Ill. Ct. Cl. 35 (Court of Claims of Illinois, 1991)
Lowry Electric Co. v. State
43 Ill. Ct. Cl. 52 (Court of Claims of Illinois, 1991)
Lippert Brick Contracting v. State
43 Ill. Ct. Cl. 71 (Court of Claims of Illinois, 1991)
K & S Associates, Inc. v. State
43 Ill. Ct. Cl. 117 (Court of Claims of Illinois, 1991)
Fencel Construction Co. v. State
44 Ill. Ct. Cl. 322 (Court of Claims of Illinois, 1991)
Altman Construction Co. v. State
44 Ill. Ct. Cl. 7 (Court of Claims of Illinois, 1991)
First National Bank v. State
43 Ill. Ct. Cl. 1 (Court of Claims of Illinois, 1990)
J. F. Inc. v. State
41 Ill. Ct. Cl. 5 (Court of Claims of Illinois, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
38 Ill. Ct. Cl. 227, 1986 Ill. Ct. Cl. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loewenbergfitch-partnership-v-state-ilclaimsct-1986.