Burrink Commercial Services v. New Life Covenant Church

2024 IL App (1st) 220778-U
CourtAppellate Court of Illinois
DecidedMarch 29, 2024
Docket1-22-0778
StatusUnpublished

This text of 2024 IL App (1st) 220778-U (Burrink Commercial Services v. New Life Covenant Church) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burrink Commercial Services v. New Life Covenant Church, 2024 IL App (1st) 220778-U (Ill. Ct. App. 2024).

Opinion

2024 IL App (1st) 220778-U

SECOND DIVISION March 29, 2024

No. 1-22-0778, consolidated with 1-22-0780 and 1-22-0789

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

______________________________________________________________________________ IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT

BURRINK COMMERCIAL SERVICES, ) ) Plaintiff-Appellant, ) ) v. ) ) Appeal from NEW LIFE COVENANT CHURCH; and TOWER ) the Circuit Court CONTRACTING, LLC, ) of Cook County ) Defendants-Appellees, ) 2018-CH-00865, cons. with -------------------------------------------------------------------------- ) 2019-L-006974 T.H. DAVIDSON & CO., ) ) Honorable Counterplaintiff-Appellant, ) Anthony C. Kyriakopoulos, ) Judge Presiding v. ) ) TOWER CONTRACTING, LLC, and NEW LIFE ) COVENANT CHURCH, ) ) Counterdefendants-Appellees. )

JUSTICE McBRIDE delivered the judgment of the court. Presiding Justice Howse and Justice Cobbs concurred in the judgment.

ORDER

¶1 Held: Circuit court did not err in dismissing subcontractors’ factually deficient complaints to foreclose mechanics liens. 1-22-0778, cons. with 1-22-0780 and 1-22-0789 ¶2 In this consolidated appeal, we address the dismissal of mechanics lien claims that were

based on labor and materials provided by the plaintiffs to construct a temple for New Life Covenant

Church at 7261 South Greenwood Avenue in Chicago. The circuit court found that the claims did

not comply with the Illinois Mechanics Lien Act, 770 ILCS 60/0.01 et seq. (West 2018) (Act). In

Appeal 1-22-0778, subcontractor Burrink Commercial Services (Burrink) argues that its seventh

amended complaint did include the “brief statement of a claimant’s contract” that is required by

section 7 of the Act (770 ILCS 60/7(a) (West 2018)), even though the church argued that the

subcontractor was improperly characterizing two contracts as one. Burrink also seeks review of

the dismissal of its breach of contract claim. In Appeals 1-22-0780 and 1-22-0789, sub-sub-

subcontractor T.H. Davidson & Co., Inc. d/b/a Welsch Ready Mix, Inc. (Welsch) disputes the

findings that it (1) did not comply with section 11(b)’s requirement to sue “all persons in the chain

of contracts between the claimant and the owner” (770 ILCS 60/11(b) (West 2018)) when it did

not include the construction project’s subcontractor as a defendant and that suing “Unknown

Owners and Non-Record Claimants” did not suffice; and (2) failed to comply with section 24(a)’s

notice requirement (770 ILCS 60/24(a) (West 2018)), when it did not allege that it served a

subcontractor’s 90-day notice after completion of its work, but did allege that it had “performed

all conditions precedent” to bringing suit.

¶3 In its seventh amended complaint, Burrink alleged that New Life Covenant Church and

Tower Contracting reached an agreement in April 2016 regarding general contracting services for

the church’s construction project and, in turn, Tower Contracting subcontracted earth moving tasks

to Burrink. More specifically, the general contractor and the subcontractor came to an oral

agreement on or before August 1, 2017 for “site preparation work” on a “time and materials” basis

-2- 1-22-0778, cons. with 1-22-0780 and 1-22-0789 and then they reduced their agreement to writing “[a] short time after August 1, 2017” in a

document entitled “Purchase Order.” Burrink’s president, Brennden Burrink, executed the

“Purchase Order” “[o]n or about July 8, 2017 [(sic)]” (a date that is prior to the oral agreement,

the site preparation work, or the drafting of the written “Purchase Order”), and Tower

Contracting’s agent signed “[o]on or about August 9, 2017.” During the site preparation tasks,

Tower Contracting and Burrink discussed other tasks that “were not originally contemplated by

the parties to the Purchase Order at the time the original written agreement was negotiated.” Tower

Contracting then prepared a written “Subcontract” regarding $560,000 worth of “Contract Extras”

that included services such as backfilling surfaces, installing sanitary and storm water sewers and

irrigation lines, digging retention ponds, and placing seed mats. Mr. Burrink executed the

“Subcontract” on August 3, 2017, and Tower Contracting executed it on October 9, 2017.

¶4 Burrink further alleged that by January 26, 2018, it had completed all of the “Purchase

Order work it was allow[ed] to perform” and some of the “Contract Extras.” Also, the “work

performed pursuant to the Purchase Order and the Contract Extras” created a “permanent and

valuable improvement and enhancement” to the real estate, consisting of $353,972.71 in value that

was attributable to the “Purchase Order” tasks and $85,539.50 in value that was attributable to the

“Contract Extras.” Tower Contracting paid $193,407.43 pursuant to the “Purchase Order” and

$12,000 for the “Contract Extras.” Burrink gave Tower Contracting a credit of $486,460.50 for

“unfinished work pursuant to the Contract Extras, leaving a balance due in the amount of

[$234,104.78].”

¶5 In Count I, entitled “Action to Foreclose Its Mechanics Lien Claim,” Burrink sought

$234,104.78 due and owing on “the outstanding balance” and supported by the pleading’s Exhibit

-3- 1-22-0778, cons. with 1-22-0780 and 1-22-0789 E, which was a copy of an amended contractor’s lien that had been filed with the county’s recorder

of deeds on or about December 1, 2021. We point out that in the recorded document, quoted below,

Burrink (1) used the term “Purchase Order” interchangeably with the term “Contracted Work,” (2)

alleged that subsequently needed “additional services” were described in the “Change Order”

which the parties had “labeled as the ‘Subcontract,’ ” and, (3) without differentiating between the

two agreements, stated that $234,104.78 was “justly due and owing,” exclusive of interest charges

and court costs:

“AMENDED CONTRACTOR’S MECHANICS LIEN NOTICE AND CLAIM

***

The undersigned claimant, Burrink Commercial Services, Inc., by Brennden Burrink,

president, of the Village of Lynwood, County of Cook, State of Illinois (the ‘Claimant’),

hereby claims a Contractor’s mechanics lien pursuant to the Mechanics Lien Act of the

State of Illinois, 770 ILCS 60/1, et seq. against New Life Covenant Church SE

(‘NLCCSE’), Tower Contracting, LLC (‘Tower’), any Unknown Owners and Non-

Record Claimants, regarding the property commonly known as 7621 South Greenwood,

Chicago, County of Cook, State of Illinois (the “Property”), and states as follows

2. On or before August 1, 2017, *** Michael Jarigese, authorized agent of Tower on

behalf of Tower and NLCCSE, orally offered to pay Brennden Burrink, the authorized

representative of Claimant, a fair and reasonable price, based upon time and materials, to

begin performing site preparation work at the property, the oral offer was later reduced to

a written request for the mobilization of earthmoving equipment to start work on July 31

-4- 1-22-0778, cons. with 1-22-0780 and 1-22-0789 2017 using 2 CAT 263 D or 272D Skid Steers with buckets for loading and grading, and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nuccio v. Chicago Commodities, Inc.
628 N.E.2d 1134 (Appellate Court of Illinois, 1993)
Swansea Concrete Products, Inc. v. Distler
467 N.E.2d 388 (Appellate Court of Illinois, 1984)
Hill Behan Lumber Co. v. Irving Federal Savings & Loan Ass'n
459 N.E.2d 1066 (Appellate Court of Illinois, 1984)
CANDICE CO. INC. v. Ricketts
666 N.E.2d 722 (Appellate Court of Illinois, 1996)
Evers v. Edward Hospital Ass'n
617 N.E.2d 1211 (Appellate Court of Illinois, 1993)
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Teter v. Clemens
492 N.E.2d 1340 (Illinois Supreme Court, 1986)
Ronning Engineering Co. v. Adams Pride Alfalfa Corp.
537 N.E.2d 1032 (Appellate Court of Illinois, 1989)
Wingler v. Niblack
374 N.E.2d 252 (Appellate Court of Illinois, 1978)
Talbert v. Home Sav. of America, FA
638 N.E.2d 354 (Appellate Court of Illinois, 1994)
Bale v. Barnhart
798 N.E.2d 750 (Appellate Court of Illinois, 2003)
In Re Marriage of Takata
709 N.E.2d 715 (Appellate Court of Illinois, 1999)
Air Safety, Inc. v. Teachers Realty Corp.
706 N.E.2d 882 (Illinois Supreme Court, 1999)
McCarty v. Verson Allsteel Press Co.
411 N.E.2d 936 (Appellate Court of Illinois, 1980)
Eichengreen v. Rollins, Inc.
757 N.E.2d 952 (Appellate Court of Illinois, 2001)
Delaney Elec. Co., Inc. v. Schiessle
601 N.E.2d 978 (Appellate Court of Illinois, 1992)
Wait v. First Midwest Bank/Danville
491 N.E.2d 795 (Appellate Court of Illinois, 1986)
Tefco Construction Co. v. Continental Community Bank & Trust Co.
829 N.E.2d 860 (Appellate Court of Illinois, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2024 IL App (1st) 220778-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burrink-commercial-services-v-new-life-covenant-church-illappct-2024.