Tefco Construction Co. v. Continental Community Bank & Trust Co.

829 N.E.2d 860, 357 Ill. App. 3d 714, 293 Ill. Dec. 935
CourtAppellate Court of Illinois
DecidedMay 12, 2005
Docket1-04-1480
StatusPublished
Cited by21 cases

This text of 829 N.E.2d 860 (Tefco Construction Co. v. Continental Community Bank & Trust Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tefco Construction Co. v. Continental Community Bank & Trust Co., 829 N.E.2d 860, 357 Ill. App. 3d 714, 293 Ill. Dec. 935 (Ill. Ct. App. 2005).

Opinion

JUSTICE QUINN

delivered the opinion of the court:

Plaintiff Tefco Construction Company, Inc. (Tefco Construction), appeals from an order of the circuit court of Cook County granting summary judgment in favor of defendants Randhurst Crossing, LLC; Wachovia Bank; National Association; and Boston Market Corporation. On appeal, plaintiff contends that the circuit court erred in granting summary judgment where the court ignored the purpose of the Mechanics Lien Act (Act) (770 ILCS 60/1 et seq. (West 2002)) and relied solely on the fact that plaintiff’s claim for lien against defendants was not verified as required by the Act. 770 ILCS 60/7 (West 2002). For the following reasons, we affirm the decision of the circuit court granting summary judgment in favor of defendants.

I. Background

Tefco Construction, an Illinois corporation, is in the business of furnishing labor, materials and services for general contracting work. On August 20, 2001, Tefco Construction entered into a contract with defendant Randhurst Currency Exchange, Inc. (Randhurst), to construct a currency exchange in a shopping center located in Mount Prospect, Illinois. The shopping center was owned by defendant KapSum Properties (Kap-Sum) and was located at 1 West Rand Road in Mount Prospect, Illinois.

Per its agreement with Randhurst, Tefco Construction was to furnish labor, materials and services to construct the currency exchange for the sum of $144,000. Specifically, Tefco Construction was to provide labor and materials for general contracting work, which included the building of a new currency exchange, the erection of a bulletproof safety cage, plumbing work, electrical work, and the installation of custom millwork, an alarm system, a sprinkler system, and the heating and air-conditioning system. Upon completion of the construction, the total contract price, accounting for credits to the contract and additional work performed by Tefco Construction, was $143,107.46. Randhurst submitted payment in the amount of $62,831 against this amount.

On February 14, 2002, Tefco Construction filed a claim for a mechanic’s lien on the said improved property for the unpaid balance of $80,276.46. The claim for lien was completed on a preprinted legal form and contained a legal description of the property, commonly known address of the property, a brief statement of the contract, and the balance due after allowing all credits. The lien was signed by the president of Tefco Construction, Thomas Flanagan, and no other signatures were present on the document.

On July 1, 2002, Tefco Construction filed a complaint to foreclose on the mechanic’s lien. Counts I and III addressed properties not at issue in this appeal. Count II of the complaint alleged that Tefco Construction entered into a contract with Randhurst to construct a new currency exchange and completed the necessary construction on October 19, 2001. The complaint further alleged that Randhurst, through its agents Garapolo Maynard Architects, Inc., Ronald Kaine, and Debbie King, entered change orders which both cancelled certain work from the contract and required Tefco Construction to provide additional work on the project. Tefco Construction alleged that the total cost for construction was $140,351 plus a sum of $2,756 for the cost of the additional work and materials Tefco Construction provided under the change orders. The complaint also alleged that the defendant paid $62,831 and claimed a mechanic’s hen on the premises to the extent of the unpaid balance of $80,276.

On November 4, 2002, the property was conveyed to defendant Randhurst Crossing, LLC (Randhurst Crossing). On December 6, 2002, Tefco Construction filed its amended complaint to foreclose its claim for mechanic’s lien and other relief. Tefco Construction added defendants Randhurst Crossing, Wachovia Bank National Association (Wachovia Bank), Kap-Sum and Boston Market Corporation (Boston Market) to its claim for lien as a result of said defendants’ alleged interest in the premises as hen creditors, tenants, judgment creditors, encumbrances, trustees and purchasers.

Flanagan, in his capacity as president of Tefco Construction, filed an affidavit for prove up for judgment against Randhurst Currency Exchange, Inc., as to count II of the amended complaint on January 2, 2004. On January 12, 2004, judgment was entered against Randhurst in favor of Tefco Construction for the amount of $80,276.

On March 2, 2004, defendants Randhurst Crossing, Boston Market, and Wachovia Bank filed a motion for summary judgment. The defendants moved for summary judgment on the grounds that there was a material defect on the face of Tefco Construction’s claim for mechanic’s lien that rendered the lien unenforceable. The motion specifically alleged that Tefco Construction’s claim for lien was unenforceable because it was not verified by the affidavit of the claimant, or his or her agent or employee, as required under section 7 of the Act (770 ILCS 60/7 (West 2002)).

In its response to the motion for summary judgment, Tefco Construction argued that “the purpose of the Act is to protect trade contractors and materialmen who in good faith furnish valuable labor and material, and no third party was prejudiced by the error.” Tefco Construction also claimed that granting summary judgment “cut[s] against the remedial purpose of the Mechanics Lien Act” and is “inherently inconsistent with the goals of Section 39 of the Act,” which provides that the Act shall be “liberally construed as a remedial act.” 770 ILCS 60/39 (West 2002).

The circuit court granted the defendants’ motion for summary judgment on April 19, 2004. Tefco Construction now appeals.

II. Analysis

On appeal, Tefco Construction contends that the circuit court erred in granting summary judgment in favor of defendants. Tefco Construction specifically argues that a claim for mechanic’s lien, signed by an agent or employee of the lien claimant but not verified, is enforceable where there is no prejudice to any third parties and because a holding to the contrary would defeat the purpose of the Act and result in a windfall to defendants.

A motion for summary judgment should be granted when there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. 735 ILCS 5/2 — 1005(c) (West 2002); Dardeen v. Kuehling, 213 Ill. 2d 329, 335 (2004). The nonmoving party will survive a motion for summary judgment if the party presents “a factual basis that would arguably entitle him to a judgment.” Carollo v. Al Warren Oil Co., 335 Ill. App. 3d 172, 179 (2004), citing Allegro Services, Ltd. v. Metropolitan Pier & Exposition Authority, 172 Ill. 2d 243, 256 (1996).

The use of summary judgment is encouraged as an aid in the expeditious disposition of a lawsuit; however, it is a drastic measure and should only be allowed when the right of the moving party is clear and free from doubt. American States Insurance Co. v. Hamer, 352 Ill. App. 3d 521, 525 (2004); Purtill v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnes Electric Construction, Inc. v. Forsythe
2025 IL App (2d) 240479-U (Appellate Court of Illinois, 2025)
Tindall Construction, Inc. v. SRI Ganesh Realty 2, LLC
2025 IL App (5th) 241332-U (Appellate Court of Illinois, 2025)
Portage Park Capital, LLC v. A.L.L. Masonry Construction Co.
2024 IL App (1st) 240344 (Appellate Court of Illinois, 2024)
Burrink Commercial Services v. New Life Covenant Church
2024 IL App (1st) 220778-U (Appellate Court of Illinois, 2024)
Young v. Wilkinson
2022 IL App (4th) 220302 (Appellate Court of Illinois, 2022)
Pepper Construction Co. v. Palmolive Tower Condominiums, LLC
2021 IL App (1st) 200753 (Appellate Court of Illinois, 2021)
Father & Sons Home Improvement II, Inc. v. Stuart
2016 IL App (1st) 143666 (Appellate Court of Illinois, 2016)
North Shore Community Bank & Trust Co. v. Sheffield Wellington, LLC
2014 IL App (1st) 123784 (Appellate Court of Illinois, 2014)
North Shore Community Bank and Trust Company v. Sheffield Wellington, LLC
2014 IL App (1st) 123784 (Appellate Court of Illinois, 2014)
National City Mortgage v. Bergman
939 N.E.2d 1 (Appellate Court of Illinois, 2010)
Doornbos Heating & Air Conditioning, Inc. v. Schlenker
932 N.E.2d 1073 (Appellate Court of Illinois, 2010)
Inter-Rail Systems, Inc. v. Ravi Corp.
900 N.E.2d 407 (Appellate Court of Illinois, 2008)
Cordeck Sales v. Construction Systems
Appellate Court of Illinois, 2008
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Calderon v. Residential Homes of America, Inc.
Appellate Court of Illinois, 2008

Cite This Page — Counsel Stack

Bluebook (online)
829 N.E.2d 860, 357 Ill. App. 3d 714, 293 Ill. Dec. 935, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tefco-construction-co-v-continental-community-bank-trust-co-illappct-2005.