Barnes Electric Construction, Inc. v. Forsythe

2025 IL App (2d) 240479-U
CourtAppellate Court of Illinois
DecidedSeptember 11, 2025
Docket2-24-0479
StatusUnpublished

This text of 2025 IL App (2d) 240479-U (Barnes Electric Construction, Inc. v. Forsythe) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barnes Electric Construction, Inc. v. Forsythe, 2025 IL App (2d) 240479-U (Ill. Ct. App. 2025).

Opinion

2025 IL App (2d) 240479-U No. 2-24-0479 Order filed September 11, 2025

NOTICE: This order was filed under Supreme Court Rule 23(b) and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT ______________________________________________________________________________

BARNES ELECTRIC CONSTRUCTION, ) Appeal from the Circuit Court INC., ) of Lake County. ) Plaintiff-Appellee and Cross-Appellant, ) ) v. ) No. 21-CH-280 ) MARSHA L. FORSYTHE, Individually and as ) Trustee of the Marsha Lynn Forsythe Living ) Trust dated 8/26/21, ) ) Honorable Defendant-Appellant and ) Daniel L. Jasica, Cross-Appellee. ) Judge, Presiding. ______________________________________________________________________________

JUSTICE MULLEN delivered the judgment of the court. Presiding Justice Kennedy and Justice Jorgensen concurred in the judgment.

ORDER

¶1 Held: (1) The trial court did not err in allowing plaintiff to recover under a theory of quantum meruit; (2) the trial court’s award of damages under quantum meruit was not against the manifest weight of the evidence; (3) the trial court did not abuse its discretion in denying defendant’s petition for attorney fees; (4) the trial court did not err in denying plaintiff’s mechanics lien claim; and (5) plaintiff forfeited its challenge to the amount of damages awarded under its quantum meruit claim by failing to cite any authority in support thereof. 2025 IL App (2d) 240479-U

¶2 I. INTRODUCTION

¶3 Plaintiff, Barnes Electric Construction, Inc., filed a three-count complaint in the circuit

court of Lake County seeking to recoup allegedly unpaid invoices related to electrical work it

performed at the home of defendant, Marsha L. Forsythe, individually and as Trustee of the Marsha

Lynn Forsythe Living Trust dated 8/26/21. 1 Count I of the complaint was for the foreclosure of a

mechanics lien, count II was a claim for breach of contract, and count III sought recovery under a

theory of quantum meruit. Following a bench trial, the trial court rejected plaintiff’s claims for

foreclosure of a mechanics lien and for breach of contract. However, the court found in favor of

plaintiff on the quantum meruit count and awarded plaintiff $217,468.88. Subsequently, defendant

moved to reconsider the trial court’s ruling and filed a petition for attorney fees. The trial court

denied both filings. Defendant now appeals, challenging that portion of the trial court’s ruling

granting plaintiff relief under a theory of quantum meruit and denying her posttrial request for

attorney fees. In addition, plaintiff has filed a cross-appeal, challenging the amount of damages

awarded as well as the trial court’s denial of its mechanics lien claim. We affirm.

¶4 II. STATEMENT OF FACTS

¶5 A. Background

¶6 Early in 2015, Forsythe purchased a single-family residence located on Old McHenry Road

in Long Grove, Illinois (Old McHenry Residence). At the time of purchase, the Old McHenry

Residence consisted of a main house of approximately 14,000 square feet and an attached eight-

car garage. Prior to moving in, Forsythe began an extensive, multi-year project to remodel and

1 In 2022, title to the home was transferred from Martha L. Forsythe, individually, into the Marsha Lynn Forsythe Living Trust dated 8/26/21, for which Forsythe serves as the sole trustee and primary beneficiary. We will refer to Martha L. Forsythe individually as “Forsythe” and the Martha Lynn Forsythe Living Trust individually as the “Trust.” We will refer to Forsythe and the Trust collectively as “defendant.”

-2- 2025 IL App (2d) 240479-U

expand the Old McHenry Residence. To that end, Forsythe retained the services of an architect,

interior designers (Kelly Guinaugh and Gail Drury), a kitchen designer, and a project manager

(Brad Brechel, who was later replaced by Al Kitchens).

¶7 Robert Barnes (Barnes) is the chief executive officer and owner of plaintiff, an electrical

contractor. Barnes has known Forsythe since approximately 2010 because plaintiff performed

work in the past for the Forsythe family and the family’s business.

¶8 Forsythe hired John Marshall Construction, Inc. (Marshall Construction) to serve as the

general contractor for the project to remodel the Old McHenry Residence. Forsythe contacted

Barnes about plaintiff doing the electrical work. Plaintiff submitted a bid to Marshall Construction

and was eventually hired as the electric subcontractor. 2 Plaintiff began working on the Old

McHenry Residence in 2015. Plaintiff originally bid its work as a subcontractor for a fixed fee of

$74,500. However, due to changes in the scope of work, the subcontract price rose and, as of June

2016, Marshall Construction had paid plaintiff more than $200,000 for electrical work at the Old

McHenry Residence. During the time plaintiff was working at the Old McHenry Residence, it also

served as the electrical contractor for work on Forsythe’s sister’s home and another residence

owned by Forsythe on Bridlewood Court in Long Grove (Bridlewood Property).

¶9 In 2016, while work at the Old McHenry Residence was still ongoing, Barnes, Marshall

Construction, and Forsythe (via Brechel) agreed that plaintiff would enter into a direct relationship

with Forsythe to provide electrical contracting services on a going-forward basis at the Old

McHenry Residence. This was done to eliminate a markup fee that Marshall Construction included

2 Plaintiff was also hired by Marshall Construction under a separate subcontract to provide electrical work for a new detached garage and apartment suite that was to be built adjacent to the Old McHenry Residence. The subcontract for the detached garage is not the subject of the underlying lawsuit or this appeal.

-3- 2025 IL App (2d) 240479-U

for all subcontractor work, a cost that was passed on to Forsythe. At that time, Barnes and Brechel

allocated certain remaining work as either (1) work to be paid for by Marshall Construction under

the existing subcontract with plaintiff or (2) additional work that would be billed directly by

plaintiff to Forsythe. Although plaintiff continued to perform electrical work on the project until

May 2020, Forsythe moved into the Old McHenry Residence in August 2018, at which time the

major remodeling work was completed and the house was livable.

¶ 10 B. Complaint

¶ 11 On August 5, 2021, plaintiff filed a complaint naming Forsythe as the sole party defendant.

The complaint was later amended multiple times, during which the Trust was added as a party

defendant. 3 According to the allegations of plaintiff’s third-amended complaint, on or about May

3, 2016, plaintiff entered into an oral contract with Forsythe to provide electrical construction,

labor, and materials “on a time and material basis.” On November 1, 2016, plaintiff issued an

account statement, invoice #1318, to Forsythe displaying the amount then due as $198,758.82.

Against the charges contained in invoice #1318, Forsythe paid plaintiff the sum of $120,000,

leaving a balance due on the invoice of $78,758.82. Forsythe did not contest in writing any of the

specific charges in invoice #1318. Thereafter, plaintiff continued to provide electrical work and

materials at the direction of Forsythe. In turn, plaintiff issued invoices to Forsythe describing the

services provided and the costs therefor. Plaintiff completed its work on the Old McHenry

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doug Hambel's Plumbing, Inc. v. Conway
831 So. 2d 704 (District Court of Appeal of Florida, 2002)
Beitner v. Marzahl
819 N.E.2d 1266 (Appellate Court of Illinois, 2004)
Enterprise Recovery Systems, Inc. v. Salmeron
927 N.E.2d 852 (Appellate Court of Illinois, 2010)
Weydert Homes, Inc. v. Kammes
917 N.E.2d 64 (Appellate Court of Illinois, 2009)
Haudrich v. Howmedica, Inc.
662 N.E.2d 1248 (Illinois Supreme Court, 1996)
Van C. Argiris & Co. v. FMC Corp.
494 N.E.2d 723 (Appellate Court of Illinois, 1986)
Fedco Electric Co. v. Stunkel
395 N.E.2d 1116 (Appellate Court of Illinois, 1979)
Lohmann Golf Designs, Inc. v. Keisler
632 N.E.2d 121 (Appellate Court of Illinois, 1994)
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Mascenic v. Anderson
369 N.E.2d 172 (Appellate Court of Illinois, 1977)
Century 21 Castles by King, Ltd. v. First National Bank of Western Springs
524 N.E.2d 1222 (Appellate Court of Illinois, 1988)
Eychaner v. Gross
779 N.E.2d 1115 (Illinois Supreme Court, 2002)
Bernstein & Grazian, P.C. v. Grazian & Volpe, P.C.
931 N.E.2d 810 (Appellate Court of Illinois, 2010)
Wolfram Partnership, Ltd. v. LaSalle National Bank
765 N.E.2d 1012 (Appellate Court of Illinois, 2002)
People v. Rolston
448 N.E.2d 965 (Appellate Court of Illinois, 1983)
Dayan v. McDonald's Corp.
466 N.E.2d 945 (Appellate Court of Illinois, 1984)
Village of Bloomingdale v. CDG Enterprises, Inc.
752 N.E.2d 1090 (Illinois Supreme Court, 2001)
Hayes Mechanical, Inc. v. First Industrial, L.P.
812 N.E.2d 419 (Appellate Court of Illinois, 2004)
Tefco Construction Co. v. Continental Community Bank & Trust Co.
829 N.E.2d 860 (Appellate Court of Illinois, 2005)
Barry Mogul & Associates, Inc. v. Terrestris Development Co.
643 N.E.2d 245 (Appellate Court of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
2025 IL App (2d) 240479-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barnes-electric-construction-inc-v-forsythe-illappct-2025.