Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker

CourtAppellate Court of Illinois
DecidedJuly 12, 2010
Docket1-09-0076 Rel
StatusPublished

This text of Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker (Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker, (Ill. Ct. App. 2010).

Opinion

FIRST DIVISION JULY 12, 2010

No. 1-09-0076

DOORNBOS HEATING AND AIR CONDITIONING, ) Appeal from the INC., an Illinois Corporation, ) Circuit Court of ) Cook County. Plaintiff and Counterdefendant-Appellee, ) ) v. ) ) JAMES D. SCHLENKER, M.D., S.C., an Illinois ) Corporation, KATHLEEN ELIZABETH SCHLENKER, ) as Trustee of the Kathleen Elizabeth Schlenker ) Declaration of Trust Dated November 10, 1992, ) ) No. 02CH19211 Defendants and Counterplaintiffs-Appellants ) . and Third-Party Plaintiffs ) ) ) (Facilities Design, Ltd., an Illinois Corporation, ) Don Chagnon, d/b/a Team Company, ) The Honorable ) Robert J. Quinn, Third-Party Defendants). ) Judge Presiding.

JUSTICE PATTI delivered the opinion of the court:

NATURE OF THE CASE AND ISSUES PRESENTED FOR REVIEW

Following a bench trial, the trial court entered judgment in favor of Doornbos Heating &

Air Conditioning, Inc. (Doornbos), on the mechanic’s lien claim that Doornbos filed against

defendants James Schlenker (Schlenker) and Kathleen Elizabeth Schlenker, as trustee of the 1-09-0076

Kathleen Elizabeth Schlenker Declaration of Trust Dated November 9, 1992, (Trust) (Schlenker

and Trust will collectively be referred to as Owners), as well as on the breach of contract

counterclaim filed by the Owners. The Owners appeal the circuit court’s judgment, arguing: (1)

Doornbos’ claims are barred by section 6 of the Mechanics Lien Act (Act) (770 ILCS 60/1 et seq.

(West 2006)); (2) Doornbos failed to prove that it substantially performed pursuant to the

contract; (3) Doornbos failed to prove its claim for extras by clear and convincing evidence and

failed to prove the amount of damages to which it was entitled; (4) the trial court erred in finding

in favor of Doornbos on the Owners’ breach of contract counterclaim; and (5) the trial court erred

in granting Doornbos’ motion in limine barring the Owners from presenting evidence pertaining

to delay damages. For the reasons contained herein, we affirm the judgment of the circuit court.

STATEMENT OF FACTS

The Trust is the owner in fee simple of the property located at 6311 West 95th Street in

Oak Lawn, Illinois, which originally consisted of a one-story medical center (hereinafter the

Property). In 1997, the Trust authorized Schlenker, lessee of the Property, to commence a

construction project (Project) to expand the existing medical facility located on the Property.

The Project initially called for a one-story addition with a surgery center located in the basement

of the facility, but was later expanded to consist of a three-story addition with a surgery center

located in the lower level. Because the Project involved the construction of a surgery center, it

was subject to the requirements of the Illinois Department of Public Health (IDPH), which has

stringent ventilation and fire protection standards for buildings containing such amenities. Don

Changnon, d/b/a Team Company (Changnon), was hired to be the general contractor of the

2 1-09-0076

Project, and Facilities Design, Ltd. (Facilities), was retained as the Project’s architect.

On July 15, 1998, Doornbos submitted a $75,000 budget estimate for the Project’s

heating, ventilation and air conditioning (HVAC) system. On January 5, 1999, Doornbos

submitted a $89,850 revised budget estimate, accounting for the provision of HVAC services for

the basement-level surgery center. Finally, on May 15, 2000, Doornbos submitted a final scope-

of- work estimate, which encapsulated Doornbos’ understanding of the necessary HVAC services

required for the expanded scope of the Project. Doornbos’ prior scope-of-work estimates were

merged into the May 15, 2000, estimate, which formed the basis for the parties’ contract.

Pursuant to the May 15, 2000, written contract, Doornbos agreed to provide the necessary labor

and materials to construct the HVAC system for the Project in exchange for payment of

$493,208. In addition to providing labor and materials, the contract called for Doornbos to

“design the complete [HVAC] system, provide drawings, submittals and schedules for approval.”

Initially, Doornbos provided the HVAC services contemplated by its contract and

received timely payment therefor. Ultimately, however, problems developed between the

Owners and Doornbos. Accordingly, on September 19, 2002, Doornbos recorded a mechanic’s

lien claim with the Cook County recorder of deeds and filed a verified complaint to foreclose its

lien in the circuit court of Cook County on October 21, 2002. In its complaint, Doornbos alleged

that it “furnished all of the materials, services, labor, and equipment required” by the contract as

well as additional labor and materials totaling $100,909, bringing the total value of the labor and

materials that Doornbos provided to $591,117. Doornbos further alleged that it completed its

3 1-09-0076

work on the Project on July 17, 2002. As of that date, Doornbos had received partial payment

pursuant to the contract, but was still owed $53,013.65. Accordingly, Doornbos sought to

foreclose its mechanic’s lien totaling $53,013.65 and recoup the attorney fees and costs

associated with the commencement of bringing its action in the circuit court.

On February 4, 2003, the Owners filed an answer to Doornbos’ complaint to foreclose its

mechanic’s lien. In pertinent part, the Owners admitted that they had not paid the amount

demanded by Doornbos but denied the material allegations advanced in Doornbos’ complaint to

foreclose its lien. Moreover, the Owners asserted a breach of contract counterclaim against

Doornbos, contending that Doornbos breached its contract when it:

“(a) Failed to install a collecting system for the condensation from the

condensor coils on the roof, causing water to pour down and damage

ceiling tiles; (b) Caused the condensing unit to run in reverse, putting

additional wear and tear on the unit and interfering with its efficiency; (c)

Installed ductwork in violation of existing codes; (d) Installed ducts in the

operating room which caused the ceiling to have too little clearance; (e)

Multiple VAX boxes to not operate; (f) Fail[ed] to install the shut down

alarm system; (g) Fail[ed] to install adequate heating coils in the operating

room; (h) Fail[ed] to install an adequate exhaust fan in the operating room;

(i) Fail[ed] to install dampers in the verticle ducts; (j) Fail[ed] to install

dampers according to manufacturer’s specifications; (k) Fail[ed] to

provide adequate ventilation in the computer room; [and] (l) Fail[ed] to

4 1-09-0076

provide control of air conditioning units.”

The Owners further alleged that as a direct and proximate cause of Doornbos’ breach of contract,

they incurred damages in excess of $500,000.1

Thereafter, the parties engaged in discovery and the cause ultimately proceeded before a

bench trial. Prior to trial, Doornbos filed a motion in limine to bar the Owners from seeking

delay damages because they failed to specifically allege that they suffered those damages in their

breach of contract counterclaim. The circuit court granted Doornbos’ motion and trial

commenced on June 4, 2007. Trial testimony revealed the following:

Robert Doornbos, Doornbos’ owner, testified that his company was in the business of

providing HVAC services. Although he was not a mechanical engineer, Robert had previously

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gallagher v. Lenart
854 N.E.2d 800 (Appellate Court of Illinois, 2006)
Mani Electrical Contractors v. Kioutas
611 N.E.2d 1167 (Appellate Court of Illinois, 1993)
Kirkpatrick v. Strosberg
894 N.E.2d 781 (Appellate Court of Illinois, 2008)
Covinsky v. Hannah Marine Corp.
903 N.E.2d 422 (Appellate Court of Illinois, 2009)
Cordeck Sales, Inc. v. Construction Systems, Inc.
917 N.E.2d 536 (Appellate Court of Illinois, 2009)
CFC Investment, L.L.C. v. McLean
900 N.E.2d 716 (Appellate Court of Illinois, 2008)
Inter-Rail Systems, Inc. v. Ravi Corp.
900 N.E.2d 407 (Appellate Court of Illinois, 2008)
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Folk v. Central National Bank & Trust Co.
567 N.E.2d 1 (Appellate Court of Illinois, 1991)
Meade v. Kubinski
661 N.E.2d 1178 (Appellate Court of Illinois, 1996)
Fieldcrest Builders, Inc. v. Antonucci
724 N.E.2d 49 (Appellate Court of Illinois, 1999)
Robb v. Lindquist
318 N.E.2d 301 (Appellate Court of Illinois, 1974)
Evans and Associates, Inc. v. Dyer
615 N.E.2d 770 (Appellate Court of Illinois, 1993)
Carey v. American Family Brokerage, Inc.
909 N.E.2d 255 (Appellate Court of Illinois, 2009)
Weather-Tite, Inc. v. University of St. Francis
909 N.E.2d 830 (Illinois Supreme Court, 2009)
Buenz v. Frontline Transportation Co.
882 N.E.2d 525 (Illinois Supreme Court, 2008)
Clarendon America Insurance v. Aargus Security Systems, Inc.
870 N.E.2d 988 (Appellate Court of Illinois, 2007)
Addison Insurance v. Fay
905 N.E.2d 747 (Illinois Supreme Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dorrnbos-heating-and-air-conditioning-inc-v-schlen-illappct-2010.