Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker

Appellate Court of Illinois·Decided July 12, 2010·No. 1-09-0076 Rel·Published

Opinion

FIRST DIVISION

JULY 12, 2010

No. 1-09-0076

DOORNBOS HEATING AND AIR CONDITIONING, ) Appeal from the INC., an Illinois Corporation, ) Circuit Court of ) Cook County.

Plaintiff and Counterdefendant-Appellee, )

)

v. )

)

JAMES D. SCHLENKER, M.D., S.C., an Illinois ) Corporation, KATHLEEN ELIZABETH SCHLENKER, ) as Trustee of the Kathleen Elizabeth Schlenker ) Declaration of Trust Dated November 10, 1992, )

) No. 02CH19211

Defendants and Counterplaintiffs-Appellants ) .

and Third-Party Plaintiffs )

)

)

(Facilities Design, Ltd., an Illinois Corporation, ) Don Chagnon, d/b/a Team Company, ) The Honorable ) Robert J. Quinn,

Third-Party Defendants). ) Judge Presiding.

JUSTICE PATTI delivered the opinion of the court:

NATURE OF THE CASE AND ISSUES PRESENTED FOR REVIEW Following a bench trial, the trial court entered judgment in favor of Doornbos Heating & Air Conditioning, Inc. (Doornbos), on the mechanic’s lien claim that Doornbos filed against defendants James Schlenker (Schlenker) and Kathleen Elizabeth Schlenker, as trustee of the

Kathleen Elizabeth Schlenker Declaration of Trust Dated November 9, 1992, (Trust) (Schlenker and Trust will collectively be referred to as Owners), as well as on the breach of contract counterclaim filed by the Owners. The Owners appeal the circuit court’s judgment, arguing: (1) Doornbos’ claims are barred by section 6 of the Mechanics Lien Act (Act) (770 ILCS 60/1 et seq. (West 2006)); (2) Doornbos failed to prove that it substantially performed pursuant to the contract; (3) Doornbos failed to prove its claim for extras by clear and convincing evidence and failed to prove the amount of damages to which it was entitled; (4) the trial court erred in finding in favor of Doornbos on the Owners’ breach of contract counterclaim; and (5) the trial court erred in granting Doornbos’ motion in limine barring the Owners from presenting evidence pertaining to delay damages. For the reasons contained herein, we affirm the judgment of the circuit court.

STATEMENT OF FACTS

The Trust is the owner in fee simple of the property located at 6311 West 95th Street in Oak Lawn, Illinois, which originally consisted of a one-story medical center (hereinafter the Property). In 1997, the Trust authorized Schlenker, lessee of the Property, to commence a construction project (Project) to expand the existing medical facility located on the Property. The Project initially called for a one-story addition with a surgery center located in the basement of the facility, but was later expanded to consist of a three-story addition with a surgery center located in the lower level. Because the Project involved the construction of a surgery center, it was subject to the requirements of the Illinois Department of Public Health (IDPH), which has stringent ventilation and fire protection standards for buildings containing such amenities. Don Changnon, d/b/a Team Company (Changnon), was hired to be the general contractor of the

Project, and Facilities Design, Ltd. (Facilities), was retained as the Project’s architect.

On July 15, 1998, Doornbos submitted a $75,000 budget estimate for the Project’s heating, ventilation and air conditioning (HVAC) system. On January 5, 1999, Doornbos submitted a $89,850 revised budget estimate, accounting for the provision of HVAC services for the basement-level surgery center. Finally, on May 15, 2000, Doornbos submitted a final scope- of- work estimate, which encapsulated Doornbos’ understanding of the necessary HVAC services required for the expanded scope of the Project. Doornbos’ prior scope-of-work estimates were merged into the May 15, 2000, estimate, which formed the basis for the parties’ contract. Pursuant to the May 15, 2000, written contract, Doornbos agreed to provide the necessary labor and materials to construct the HVAC system for the Project in exchange for payment of $493,208. In addition to providing labor and materials, the contract called for Doornbos to “design the complete [HVAC] system, provide drawings, submittals and schedules for approval.”

Initially, Doornbos provided the HVAC services contemplated by its contract and received timely payment therefor. Ultimately, however, problems developed between the Owners and Doornbos. Accordingly, on September 19, 2002, Doornbos recorded a mechanic’s lien claim with the Cook County recorder of deeds and filed a verified complaint to foreclose its lien in the circuit court of Cook County on October 21, 2002. In its complaint, Doornbos alleged that it “furnished all of the materials, services, labor, and equipment required” by the contract as well as additional labor and materials totaling $100,909, bringing the total value of the labor and materials that Doornbos provided to $591,117. Doornbos further alleged that it completed its

work on the Project on July 17, 2002. As of that date, Doornbos had received partial payment pursuant to the contract, but was still owed $53,013.65. Accordingly, Doornbos sought to foreclose its mechanic’s lien totaling $53,013.65 and recoup the attorney fees and costs associated with the commencement of bringing its action in the circuit court.

On February 4, 2003, the Owners filed an answer to Doornbos’ complaint to foreclose its mechanic’s lien. In pertinent part, the Owners admitted that they had not paid the amount demanded by Doornbos but denied the material allegations advanced in Doornbos’ complaint to foreclose its lien. Moreover, the Owners asserted a breach of contract counterclaim against Doornbos, contending that Doornbos breached its contract when it:

“(a) Failed to install a collecting system for the condensation from the condensor coils on the roof, causing water to pour down and damage ceiling tiles; (b) Caused the condensing unit to run in reverse, putting additional wear and tear on the unit and interfering with its efficiency; (c)

Installed ductwork in violation of existing codes; (d) Installed ducts in the operating room which caused the ceiling to have too little clearance; (e)

Multiple VAX boxes to not operate; (f) Fail[ed] to install the shut down alarm system; (g) Fail[ed] to install adequate heating coils in the operating room; (h) Fail[ed] to install an adequate exhaust fan in the operating room;

(i) Fail[ed] to install dampers in the verticle ducts; (j) Fail[ed] to install dampers according to manufacturer’s specifications; (k) Fail[ed] to provide adequate ventilation in the computer room; [and] (l) Fail[ed] to

provide control of air conditioning units.”

The Owners further alleged that as a direct and proximate cause of Doornbos’ breach of contract, they incurred damages in excess of $500,000.1 Thereafter, the parties engaged in discovery and the cause ultimately proceeded before a bench trial. Prior to trial, Doornbos filed a motion in limine to bar the Owners from seeking delay damages because they failed to specifically allege that they suffered those damages in their breach of contract counterclaim. The circuit court granted Doornbos’ motion and trial commenced on June 4, 2007. Trial testimony revealed the following:

Free access — add to your briefcase to read the full text and ask questions with AI

Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker, (Ill. Ct. App. 2010).

Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker (Dorrnbos Heating and Air Conditioning, Inc. v. Schlenker) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gallagher v. Lenart
854 N.E.2d 800 (Appellate Court of Illinois, 2006)
Mani Electrical Contractors v. Kioutas
611 N.E.2d 1167 (Appellate Court of Illinois, 1993)
Kirkpatrick v. Strosberg
894 N.E.2d 781 (Appellate Court of Illinois, 2008)
Covinsky v. Hannah Marine Corp.
903 N.E.2d 422 (Appellate Court of Illinois, 2009)
Cordeck Sales, Inc. v. Construction Systems, Inc.
917 N.E.2d 536 (Appellate Court of Illinois, 2009)
CFC Investment, L.L.C. v. McLean
900 N.E.2d 716 (Appellate Court of Illinois, 2008)
Inter-Rail Systems, Inc. v. Ravi Corp.
900 N.E.2d 407 (Appellate Court of Illinois, 2008)
Cordeck Sales, Inc. v. Construction Systems, Inc.
887 N.E.2d 474 (Appellate Court of Illinois, 2008)
Folk v. Central National Bank & Trust Co.
567 N.E.2d 1 (Appellate Court of Illinois, 1991)
Meade v. Kubinski
661 N.E.2d 1178 (Appellate Court of Illinois, 1996)
Fieldcrest Builders, Inc. v. Antonucci
724 N.E.2d 49 (Appellate Court of Illinois, 1999)
Robb v. Lindquist
318 N.E.2d 301 (Appellate Court of Illinois, 1974)
Evans and Associates, Inc. v. Dyer
615 N.E.2d 770 (Appellate Court of Illinois, 1993)
Carey v. American Family Brokerage, Inc.
909 N.E.2d 255 (Appellate Court of Illinois, 2009)
Weather-Tite, Inc. v. University of St. Francis
909 N.E.2d 830 (Illinois Supreme Court, 2009)
Buenz v. Frontline Transportation Co.
882 N.E.2d 525 (Illinois Supreme Court, 2008)
Clarendon America Insurance v. Aargus Security Systems, Inc.
870 N.E.2d 988 (Appellate Court of Illinois, 2007)
Addison Insurance v. Fay
905 N.E.2d 747 (Illinois Supreme Court, 2009)