Young v. Wilkinson

2022 IL App (4th) 220302, 213 N.E.3d 486, 464 Ill. Dec. 449
Appellate Court of Illinois·Decided November 14, 2022·No. 4-22-0302·Published·Cited by 13 cases

Opinion

2022 IL App (4th) 220302 FILED November 14, 2022

NO. 4-22-0302 Carla Bender 4th District Appellate

IN THE APPELLATE COURT Court, IL

OF ILLINOIS

FOURTH DISTRICT

GABE YOUNG and ANNETTA YOUNG, ) Appeal from the Plaintiffs-Appellees, ) Circuit Court of v. ) Carroll County DUSTIN WILKINSON, d/b/a Hammer It Construction, ) No. 19L7 Defendant-Appellant. )

) Honorable

) Scott Brinkmeier,

) Judge Presiding.

JUSTICE DOHERTY delivered the judgment of the court, with opinion.

Justices Steigmann and Zenoff concur in the judgment and opinion.

OPINION

¶1 Plaintiffs Gabe and Annetta Young contracted with defendant Dustin Wilkinson, doing business as Hammer It Construction, to build a residence. The home was built in 2014, but the Youngs asserted that certain items were either not completed or were built in an unworkmanlike manner. This dispute about the quality of the construction led to the initial litigation with the parties in 2015. The Youngs initiated that litigation but voluntarily dismissed their claims before trial. The 2015 litigation went to hearing only on Wilkinson’s counterclaim for breach of contract (count I) and mechanic’s lien foreclosure (count II) seeking the outstanding balance on the contract. The Youngs prevailed on both of Wilkinson’s 2015 claims.

¶2 The instant litigation commenced in September 2019, when the Youngs refiled their breach of contract claim. Wilkinson unsuccessfully moved for dismissal of the 2019 complaint on

res judicata grounds. Following a bench trial, the trial court found for the Youngs on their breach of contract claim and awarded them $168,223.44 in damages plus court costs.

¶3 Wilkinson appeals from the trial court’s verdict, arguing that res judicata barred the Youngs’ 2019 complaint. Alternatively, he seeks a remand to recalculate damages.

¶4 We affirm.

¶5 I. BACKGROUND

¶6 In March 2014 the Youngs contracted with Wilkinson (and his then-partner, Chad Gallagher) for the construction of a residence in Mt. Carroll, Illinois, to be “completed in a substantial workmanlike manner” for the sum of $253,400. Construction of the residence began in June 2014. In September of that year, the Youngs raised concerns with Wilkinson and Gallagher about the porch settling. By that time, the Youngs had paid all but $10,000 of the contract price. The Youngs met with Wilkinson concerning the construction defects and told him they would not make the final payment until the items were corrected. Wilkinson did not return to the property to address the defects.

¶7 A. The 2015 Complaint

¶8 In late 2015 the Youngs filed a breach of contract complaint against Wilkinson and Gallagher, doing business as Hammer It Construction, which alleged, in part, that “despite the obligations created by their Contract” and “despite receiving substantially full payment,” Wilkinson failed or refused to fulfill his contractual obligations. They allege that Wilkinson improperly constructed a concrete porch; installed electrical wiring out of compliance with the applicable code; improperly installed light fixture junction boxes, windows, and hot water piping; failed to install a floor drain; failed to install a proper seal around the chimney; refused to complete

the interior work; and improperly constructed foundations/footings for the house and garage. It further alleged Wilkinson failed to perform the work in a workmanlike manner.

¶9 B. The 2015 Counterclaim

¶ 10 Count I of Wilkinson’s 2015 counterclaim alleged breach of contract and alleged that, “although all of the work was performed in a workmanlike manner” and “all contract specifications were met,” the Youngs “refused to pay” the final $10,000 on the contract. Count II alleged compliance with the mechanic’s lien statute and sought foreclosure of the mechanic’s lien to recover the outstanding $10,000 remaining on the contract, as well as interest, costs, and statutory attorney fees.

¶ 11 In March 2019, the Youngs voluntarily dismissed their 2015 complaint. Although the full record from the 2015 case was not provided to this court as part of the record on appeal, the pleadings in the 2019 case reflect that the docket entry of the voluntary dismissal stated as follows:

“03/19/2019 Attorney Guzzardo present for the Petitioners. Attorney Potter present with the Defendants. Conference held in chambers. Plaintiffs’ Motion heard and denie[d]. Plaintiff taking volunt[ary] nonsuit. Previously set date for April 22, 2019 to remain.”

This ruling was elaborated on by the trial court in its April 26, 2019, order (the final disposition of 2015 case), wherein the court stated, “Of course, the Youngs’ damages claim for money damages was voluntarily dismissed but still could be refiled in a new proceeding.”

¶ 12 C. Trial of Counterclaims

¶ 13 With the Youngs’ 2015 complaint voluntarily dismissed, the 2015 case proceeded to a bench trial on Wilkinson and Gallagher’s counterclaims. Because no transcripts were provided

for the first trial, we rely on the facts set forth in the trial court’s April 26, 2019, order to glean what took place.

¶ 14 During Wilkinson and Gallagher’s case, the testimony revealed that the Youngs met with Wilkinson in October 2014 and informed him they would not pay the final $10,000 until certain defects were rectified. Wilkinson prepared a “punch list” of items needing correction, and the Youngs added further items, including leaking windows, loose support posts, and that the porch was “settling.” Wilkinson told the Youngs the porch repairs would need to wait until spring to allow the porch to finish settling. It also came to light that Wilkinson had credited back $5000 to the Youngs for work not performed, leaving the total balance Wilkinson sought in his counterclaim at $5000.

¶ 15 At the close of the contractors’ case-in-chief on the counterclaims, a directed verdict was entered against Gallagher without opposition from his counsel.

¶ 16 As part of their defense to the counterclaims, the Youngs presented the testimony of two licensed professional home inspectors and a professional fireplace installer, which the trial court later characterized as “demonstrating, without establishing a measure of damages, that the newly constructed home was plagued with several substantial construction defects in need of expensive remedy.” Some of the issues included the settling porch, steps pulling away from the porch, unstable posts, soffits not being cut for lights, a sewer line “clean out” that ran into the middle of the front porch, exposed nail heads on the metal roof, water issues, and an improperly constructed fireplace chimney. There was also testimony that the foundation and footings were improperly constructed and that the electrical box was improperly wired for 100 amps, rather than 200 amps as required by code.

¶ 17 According to the trial court’s order:

“Mr. Wilkinson was required to prove substantial performance of his obligations under the contract to construct the Youngs’ new home. But given the proof described above, particularly that the attached garage was without proper footings and was not properly attached to the house, the porch was likewise without footings, the “I-joists” had been weakened, and the chimney was such a fire danger that it had to be replaced, it cannot be concluded that Mr. Wilkinson has[ ] met his burden of proving substantial performance to support his counterclaim.”

¶ 18 The trial court concluded that the deficiencies were “more than just ‘some omissions or deviations from the contract.’ ” Judgment was entered against Wilkinson and in favor of the Youngs on both counts of the counterclaim; no appeal was taken from that order.

¶ 19 D. The 2019 Complaint

Free access — add to your briefcase to read the full text and ask questions with AI

Young v. Wilkinson, 2022 IL App (4th) 220302, 213 N.E.3d 486, 464 Ill. Dec. 449 (Ill. Ct. App. 2022).

2022 IL App (4th) 220302 (Young v. Wilkinson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

People v. Powell
Appellate Court of Illinois, 2026
Walters v. Ogle County Sheriff
Appellate Court of Illinois, 2026
Lugo v. Woodford County
Appellate Court of Illinois, 2026
Faulkner v. Faulkner
2026 IL App (1st) 251311-U (Appellate Court of Illinois, 2026)
Davie and Associates Dermatopathology P.A. v. Reditus Laboratories, LLC
2026 IL App (4th) 4241374 (Appellate Court of Illinois, 2026)
Sciarrone v. Village of Island Lake, Illinois
2025 IL App (2d) 240153 (Appellate Court of Illinois, 2025)
Nieukirk v. OSF Healthcare System
2025 IL App (4th) 241175-U (Appellate Court of Illinois, 2025)
Winkler v. Danna Pools, Inc.
2025 IL App (3d) 240424-U (Appellate Court of Illinois, 2025)
Central Illinois Mortuary Services, Ltd. v. Abts
2025 IL App (4th) 240775-U (Appellate Court of Illinois, 2025)
People v. Bruketta
2024 IL App (4th) 241088-U (Appellate Court of Illinois, 2024)
OG Plumbing, LLC v. Basecamp Old Irving Park, LLC.
2024 IL App (1st) 221813-U (Appellate Court of Illinois, 2024)
Karris v. Keybank National Ass'n
2024 IL App (1st) 231471-U (Appellate Court of Illinois, 2024)
Rowsey v. Breitman
2024 IL App (4th) 230742 (Appellate Court of Illinois, 2024)
Lopez v. Wallenberg
2024 IL App (1st) 230861-U (Appellate Court of Illinois, 2024)
Doe v. Fritch
2024 IL App (4th) 230585-U (Appellate Court of Illinois, 2024)
In re Estate of Baker
2023 IL App (4th) 221033-U (Appellate Court of Illinois, 2023)
Alwan v. Kickapoo-Edwards Land Trust
2023 IL App (4th) 220088-U (Appellate Court of Illinois, 2023)