Winkler v. Danna Pools, Inc.

2025 IL App (3d) 240424-U
CourtAppellate Court of Illinois
DecidedApril 15, 2025
Docket3-24-0424
StatusUnpublished

This text of 2025 IL App (3d) 240424-U (Winkler v. Danna Pools, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winkler v. Danna Pools, Inc., 2025 IL App (3d) 240424-U (Ill. Ct. App. 2025).

Opinion

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

2025 IL App (3d) 240424-U

Order filed April 15, 2025 ____________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

THIRD DISTRICT

RAYMOND WINKLER, ) Appeal from the Circuit Court ) of the 18th Judicial Circuit, Plaintiff-Appellant, ) Du Page County, Illinois, ) v. ) Appeal No. 3-24-0424 ) Circuit No. 20-L-1430 DANNA POOLS, INC., ) ) Honorable Defendant-Appellee. ) David E. Schwartz, ) Judge, Presiding. ____________________________________________________________________________

PRESIDING JUSTICE BRENNAN delivered the judgment of the court. Justices Hettel and Peterson concurred in the judgment. ____________________________________________________________________________

ORDER

¶1 Held: The trial court’s finding that plaintiff failed to prove damages in connection with defendant’s breach of contract was not against the manifest weight of the evidence. Affirmed.

¶2 Plaintiff, Raymond Winkler, appeals from the trial court’s judgment for defendant, Danna

Pools, Inc. (DPI), following a bench trial. Winkler argues that the court’s finding that he failed to

adequately prove the damages suffered in connection with DPI’s breach of contract regarding the construction of the swimming pool at Winkler’s residence was against the manifest weight of the

evidence. For the reasons set forth below, we affirm.

¶3 I. BACKGROUND

¶4 In February 2019, the parties entered into a contract providing that Winkler would pay DPI

$98,000 for DPI’s construction of an in-ground swimming pool at his residence. The payments

were to be made in installments at different stages of construction. Section 4 of the contract

provided, in relevant part, as follows:

“DPI guarantees its work to be free from defects in material and workmanship for a period

of (14) Months from the date pool is filled with water. *** If maintenance, service, or

warranty work is performed by anyone other than DPI ***, all warranties and guarantees

will be voided.”

The pool was filled with water in July 2019, and Winkler enjoyed it for the season.

¶5 A July 9, 2019, maintenance ticket shows that DPI provided vacuuming services and

conducted a chemical test on the pool. A July 15, 2019, service work order details that DPI

performed maintenance on the pool, delivered a customer maintenance kit, trained Winkler in

customer maintenance, showed Winkler “how to test water using test kit and salt strips” and

explained the appropriate chemical levels, and demonstrated how to clean the pump basket. The

work order also includes a note that Winkler “stated he knew how to maintain pool and would be

maint[ain]ing his own pool.” A corresponding maintenance ticket from the same day shows that

another vacuuming service and chemical test were performed by DPI, as well as “additional time

going over with [Winkler] how to use test kit, equipment, and vacuum.” Maintenance tickets dated

July 26, 2019, and September 17, 2019, reflect additional vacuuming and chemical tests by DPI.

A service work order dated September 17, 2019, shows that DPI addressed Winkler’s concern that

2 scale was blowing out of the return pipes and the heater was making a noise. And finally, a

November 22, 2019, invoice shows that DPI winterized Winkler’s pool at the end of the season.

¶6 In April 2020, Winkler pulled back the cover of the pool in anticipation of its opening, at

which time he noticed a crack in its foundation. Winkler testified that Daniel Kamide, DPI’s sole

shareholder, inspected the crack and suggested that DPI open the pool anyway and address the

problem at the end of the season. Realizing that his 14-month warranty would expire by the end

of the season, Winkler did not agree and, instead, drained the pool himself, revealing additional

cracks. The parties communicated about the cracks over the course of the next three months, with

DPI ultimately taking the position in a July 9, 2020, letter that Winkler “[k]nowingly voided the

warranty” in section 4 of the contract; “[r]efused [DPI’s] maintenance for most of 2019”; [r]efused

to contract with [DPI] to perform the opening, closing, maintenance and service for 2020”; and

“[i]gnored the warning about opening the pool with a hairline crack.” DPI asserted that Winkler’s

actions caused the damage to the pool and denied any liability. In its letter, DPI noted that it

“discussed assisting Winkler but he has rebuffed anything but a new pool.”

¶7 On December 10, 2020, Winkler filed a complaint against DPI for breach of contract.

Specifically, Winkler alleged, inter alia, that DPI failed to honor its 14-month warranty and repair

the pool. Winkler claimed that he hired a contractor who informed him that, if only the plaster

needed repair, the cost of repair would be $40,000, but that “[i]f the cracks extended through the

concrete/gunite material[,] more extensive repairs would be required that could cost in excess of

$100,000.”

¶8 DPI denied that it breached the contract and asserted two affirmative defenses: (1) failure

to mitigate damages and (2) invalidation. In support of failure to mitigate, DPI argued that, despite

obtaining estimates to repair the cracks, Winkler did not take any action to repair them. As to

3 invalidation, DPI alleged that, in violation of section 4 of the contract, Winkler serviced his own

pool when he opened it for the 2020 season and, in doing so, “drained the pool without checking

and removing the hydrostatic valve located within main drain at bottom of pool which caused

pressure to the pool resulting in the crack(s).” DPI also claimed that Winkler improperly used

chemicals in the pool during 2019 because he did not have a DPI maintenance contract and,

therefore, DPI was “not responsible for the check cracking.”

¶9 In response to the affirmative defense of failure to mitigate damages, Winkler clarified,

inter alia, that, while “he spoke to an engineer and a pool contractor regarding the cracks[,]” he

never received an estimate to repair them. Regarding invalidation, Winkler denied that he

“serviced” the pool within the meaning of section 4 of the contract and denied causing the cracks.

¶ 10 The bench trial commenced on April 8, 2024. Winkler testified to his discovery of the

cracks and his subsequent communications with Kamide. He further testified that he understood

that DPI training him to vacuum the pool and test the chemical levels meant that he was allowed

to so without voiding the warranty. He also confirmed that he put the necessary chemicals into the

pool himself. However, contrary to DPI’s notes on the July 15, 2019, service work order, Winkler

denied that he told DPI that he was going to maintain his own pool. He further denied refusing

DPI’s maintenance services in 2019, being offered a written service contract, or taking any actions

that were not permitted under the warranty. Winkler testified that, prior to DPI’s July 9, 2020,

letter, Kamide suggested that the cracking could have been caused by DPI’s receipt of improper

cement but that it needed to be “engineered” to be sure. This was not done. On cross-examination,

Winkler testified that, as of the date of trial, he had not had any work done on the cracks but that

he had an engineer and a pool contractor come to his residence in 2020. He testified that he did

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Razor v. Hyundai Motor America
854 N.E.2d 607 (Illinois Supreme Court, 2006)
Bowman v. Zimny
628 N.E.2d 384 (Appellate Court of Illinois, 1993)
Mayfield v. Swafford
435 N.E.2d 953 (Appellate Court of Illinois, 1982)
Naiditch v. Shaf Home Builders, Inc.
512 N.E.2d 1027 (Appellate Court of Illinois, 1987)
Meeker v. Gray
492 N.E.2d 508 (Appellate Court of Illinois, 1986)
Midwest Software, Ltd. v. Willie Washer Manufacturing Co.
630 N.E.2d 1088 (Appellate Court of Illinois, 1994)
Eychaner v. Gross
779 N.E.2d 1115 (Illinois Supreme Court, 2002)
Meade v. Kubinski
661 N.E.2d 1178 (Appellate Court of Illinois, 1996)
Shaw v. Bridges-Gallagher, Inc.
528 N.E.2d 1349 (Appellate Court of Illinois, 1988)
Park v. Sohn
433 N.E.2d 651 (Illinois Supreme Court, 1982)
In re Illinois Bell Link-Up II & Late Charge Litigation
2013 IL App (1st) 113349 (Appellate Court of Illinois, 2013)
King v. Find-A-Way Shipping, LLC
2020 IL App (1st) 191307 (Appellate Court of Illinois, 2020)
Young v. Wilkinson
2022 IL App (4th) 220302 (Appellate Court of Illinois, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2025 IL App (3d) 240424-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winkler-v-danna-pools-inc-illappct-2025.