Craft v. Stevenson Lumber Yard, Inc.

843 A.2d 1076, 179 N.J. 56, 2004 N.J. LEXIS 147
CourtSupreme Court of New Jersey
DecidedMarch 23, 2004
StatusPublished
Cited by18 cases

This text of 843 A.2d 1076 (Craft v. Stevenson Lumber Yard, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Craft v. Stevenson Lumber Yard, Inc., 843 A.2d 1076, 179 N.J. 56, 2004 N.J. LEXIS 147 (N.J. 2004).

Opinion

The opinion of the Court was delivered by

LONG, Justice.

This appeal presents us with an opportunity to revisit the Construction Lien Law, (CLL or Act), N.J.S.A. 2A:44A-1 to -38, a statute that was enacted primarily to secure payment for contractors, subcontractors, and suppliers who furnish labor or materials used to enhance the value of the property of others. The case involves a “lien claim” (N.J.S.A. 2A:44A-9), which constitutes the value of the labor or materials provided, and a “lien fund” (N.J.S.A. 2A:44A-10, 23), which is the measure of what is recoverable pursuant to a lien.

With respect to the hen claim, the question is whether an innocent property owner is hable to a suppher when the owner has paid his general contractor for supplies, which payments were transferred to the suppher without being earmarked, and were not recognized by the suppher as satisfying that property owner’s account balance. We hold that a suppher has a duty to determine which of a contractor’s projects is the source of its payment and to allocate the payment accordingly. Having failed in that duty, the suppher here was unable to verify the existence of a debt as required under the CLL and thus, no hen claim against the owner’s property can be advanced.

Regarding the hen fund, at issue is the measure of the amount that is available to a subcontractor or suppher with a hen claim when the contractor has abandoned the job at a point at which the property owner has made all of the progress payments to date. We hold that the measure of the amount available to the hen *64 claimant in such circumstances is determined in accordance with N.J.S.A. 2A:44A-10 and -23 by subtracting the payments made to date from the “total contract price” agreed upon in writing by the parties.

I

Because the case comes to us on appeal from the grant of summary judgment in favor of the lien claimants, we view the facts in a light most favorable to the nonmoving party, the property owner. R. 4:46-2. So viewed, the facts are as follows: On March 18, 1998, plaintiff, Emory Craft, Jr. retained Aladieh Builders, Inc. (Aladieh) to construct a residence for him at a total cost of $220,000.00. In preparation for and during the job, Aladieh purchased supplies from Stevenson Lumber Yard, Inc. (Stevenson), among others. 1 As the job progressed, Craft paid Aladieh for labor and materials when payments became due. During the same period, Aladieh had several construction projects ongoing and purchased building materials from Stevenson to supply all of its different jobs.

When Aladieh made a payment to Stevenson and, more particularly, when it paid Stevenson the money it had received from Craft, Aladieh did not specify for which construction project the payment was intended and Stevenson simply applied the payments to the oldest outstanding Aladieh invoice.

Aladieh eventually ceased working on the Craft job after Craft had paid $166,980.00. At that point, according to Craft, he owed Aladieh nothing for the work that had been performed. Michael Aladieh, the principal of Aladieh, then filed for personal bankruptcy. Although the corporation did not file for bankruptcy, it was nonetheless insolvent by late summer of 1999 according to Michael Aladieh.

*65 On June 16, 1999, Stevenson filed a Construction Lien Claim against the real property owned by Craft in the amount of $53,019.59. 2 When Stevenson’s lien claim was filed, Aladieh owed it approximately $75,000 for all of the projects for which Stevenson had provided supplies.

In August 1999, Craft filed a Complaint against Stevenson demanding a judgment dismissing the Construction Lien Claim. Stevenson answered and counterclaimed, requesting that Craft’s Complaint be dismissed and claiming the right to file the lien against Craft’s property. In addition, in a Third Party Complaint, Stevenson sought judgment against Aladieh for approximately $75,000. Craft answered Stevenson’s Counterclaim, demanding dismissal. An arbitrator determined that Craft was not liable to Stevenson on the construction lien, and Stevenson requested a trial de novo pursuant to Rule 4:21A-6.

As the trial approached, Craft, Stevenson, and DuBell filed cross-motions for summary judgment — Craft to discharge the lien and Stevenson and DuBell to enforce it. The trial court ruled in favor of Stevenson and DuBell on the motions.

Craft appealed, challenging the legitimacy of Stevenson’s lien claim and the existence of a lien fund in connection with the claims of both Stevenson and DuBell. The Appellate Division affirmed the grant of summary judgment in favor of Stevenson and DuBell. In so doing, the court recognized an inequity in the scheme, but held that, under the statute, the innocent homeowner must bear the financial burden caused by a defaulting contractor, despite paying for his supplies in full and despite having no knowledge that the contractor had outstanding accounts with its supplier.

*66 We granted Craft’s petition for certification. 177 N.J. 221, 827 A.2d 289 (2003). We also accorded amicus curiae status to the Building Contractors Association of New Jersey (BCA/NJ) and to the Northern New Jersey Chapter, Inc., National Electrical Contractors Association (ÑECA). We now reverse.

II

Craft raises two fundamental arguments. First, there is no construction lien fund when a homeowner already has paid for all the work that has been completed, has not made advance payments for unperformed work, and the contractor has walked off the job over the homeowner’s objection. Second, there is no construction lien claim when a supplier pyramids construction monies from one project to finance another.

Stevenson counters that, under the CLL, the lien fund in this case was the amount of the outstanding balance on the contract between Craft and Aladich at the time Stevenson’s lien claim was filed (approximately $53,000), and that Aladich’s later walk-off did not affect that calculation. DuBell joins in that argument. Stevenson also contends that, as a creditor, it was entitled to apply Aladich’s payments to its account in any manner it chose so long as the payments were made without specific direction to the contrary.

BCA/NJ argues that a property owner who has paid its contractor in full for the work that has been completed cannot be subjected to the lien claims of suppliers under the CLL. In that respect, BCA/NJ contends that the contract amount between Craft and Aladich, for purposes of calculating the fund, should reflect valid adjustments. Specifically, because Aladich walked off the job after performing $166,980 worth of work, for which Craft had paid in full, that figure and not $220,000 is the “contract” amount. According to BCA/NJ, because Craft “owed” no money, no lien fund exists. Finally, BCA/NJ contends that in order to invoke the beneficial and extraordinary remedial provisions of the *67

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diamond Beach, LLC v. Mar. Assocs., Inc.
199 A.3d 306 (New Jersey Superior Court App Division, 2018)
NRG Rema LLC v. Creative Envtl. Solutions Corp.
186 A.3d 904 (New Jersey Superior Court App Division, 2018)
L & W Supply Corp. v. DeSilva
57 A.3d 558 (New Jersey Superior Court App Division, 2012)
Henry v. New Jersey Department of Human Services
9 A.3d 882 (Supreme Court of New Jersey, 2010)
Schadrack v. KP BURKE BUILDER, LLC
970 A.2d 368 (New Jersey Superior Court App Division, 2009)
Eastern Concrete Materials, Inc. v. Tarragon Edgewater Associates, LLC
955 A.2d 962 (New Jersey Superior Court App Division, 2008)
Tefco Construction Co. v. Continental Community Bank & Trust Co.
829 N.E.2d 860 (Appellate Court of Illinois, 2005)
Labov Mechanical, Inc. v. East Coast Power, L.L.C.
872 A.2d 142 (New Jersey Superior Court App Division, 2005)
Kramer v. Alston (In Re Alston)
322 B.R. 265 (D. New Jersey, 2005)
Kvaerner Process v. Barham-McBride
845 A.2d 692 (New Jersey Superior Court App Division, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
843 A.2d 1076, 179 N.J. 56, 2004 N.J. LEXIS 147, Counsel Stack Legal Research, https://law.counselstack.com/opinion/craft-v-stevenson-lumber-yard-inc-nj-2004.