St. Michael's v. Conneen Constr.

166 A. 458, 114 N.J. Eq. 276, 1933 N.J. Ch. LEXIS 127
CourtNew Jersey Court of Chancery
DecidedJune 1, 1933
StatusPublished
Cited by7 cases

This text of 166 A. 458 (St. Michael's v. Conneen Constr.) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Michael's v. Conneen Constr., 166 A. 458, 114 N.J. Eq. 276, 1933 N.J. Ch. LEXIS 127 (N.J. Ct. App. 1933).

Opinion

A contract was entered into by defendant Conneen Construction Company, a corporation, and complainant, St. Michael's Orphan Asylum and Industrial School, Hopewell, New Jersey, dated April 29th, 1931, for the construction and erection of an annex to St. Michael's orphan asylum.

Conneen company on May 21st, 1931, entered into a contract with Gandelman and Espenship, Incorporated, to furnish labor and materials for stone and brick masonry, hauling and setting cut stone, lathing, plastering, including a clip-on gypsum block ceiling for the said annex. Gandelman and Espenship, Incorporated, continued with the work under this contract until October 30th, 1931, when the men working on the job were called off by a union delegate for failure to pay wages.

Conneen company advanced $1,450 to Gandelman and Espenship, Incorporated, for payroll which was insufficient and on November 3d 1931, Mr. Conneen, president of the Conneen Construction Company, paid by checks, the workmen of Gandelman and Espenship, Incorporated, the wages then due them, and Conneen Construction Company then took over the work and completed it at a total cost, including that of the work then done by Gandelman and Espenship, of $39,414.28, being $1,414.28 above the amount called for in the contract of Gandelman and Espenship. Stop-notices under the provisions of section 3 of the Mechanics' Lien act as amended (Cum. Supp. Comp. Stat. 1925, 1930 p. 949, 951) were regularly filed by defendants materialmen who had furnished material in connection with the work contemplated under the Conneen-Gandelman and Espenship contract. Notices of dispute of these claims were served and suits were brought *Page 278 within the statutory time by all of them now interested except those who were prevented from doing so by the filing of a bill of interpleader by complainant.

The money due from the owner to the contractor to the extent of the claims of materialmen now disputed, has been paid into court pursuant to the prayer of the bill of interpleader and complainant has been discharged. The several defendants have filed statements of their respective claims against the funds. The amounts due the several claimants for materials furnished and the dates of filing of stop-notices were agreed upon and are determined as follows:

Nov. 24, 1931  Independent Brick Co. ...................  $217.36
Dec.  4, 1931  DeFlesco Bros. Co., Inc. ................   419.31
Dec.  5, 1931  A.S. Reid Brick Co. ..................... 4,033.00
Dec.  8, 1931  George B. Coursey .......................   107.40
Dec.  8, 1931  Concrete Specialties Co. ................ 2,381.13
Dec. 14, 1931  Tattersall Co. ..........................   478.25
Jan. 28, 1932  Rednor  Kline ..........................   542.66
June 13, 1932  J.B. Hill  Sons ........................   933.40
The contract entered into between Conneen Company and Gandelman and Espenship provided that Gandelman and Espenship should push the work vigorously and keep pace with all the other mechanics, and in case of delay or failure to keep pace with the other work and as required, Conneen company should have the right after five days' written notice to Gandelman and Espenship and their failure to comply therewith, to sublet all or any part of the work or furnish the material and labor and set other men to do the work and charge the cost against any balance that might be due or become due to Gandelman and Espenship on account of such contract for work done or material furnished.

There had been some complaint on the part of Conneen company about the progress of the work, and on October 26th, 1931, Conneen company wrote to Gandelman and Espenship a letter as follows:

"We have been very much discouraged and disappointed in the progress of the brick work of St. Michael's Orphanage at Hopewell, N.J., and hereby notify you that unless there are more men placed *Page 279 on this job and same rushed to an early completion, we will be compelled to take the initiative of giving you forty-eight (48) hours' notice and will have men on the job and charge same to your account. We are sick and tired with this job being delayed."

There was no other written notice by Conneen company to Gandelman and Espenship, and Conneen company took over the work because of the failure of Gandelman and Espenship to meet the payroll. Mr. Gandelman testified that, in a conversation which he had with Mr. Conneen, Mr. Conneen had promised to give him the money to meet the payroll and that he failed to keep his promise and that on the day before the workmen were paid by Conneen, "Mr. Conneen and Mr. McCloskey said to me, I either had to raise more money and finish the job and if I can't raise it he will take it over and do his own paying, complete the job, and assume the bills I owed on that job, he said, `I will pay everything, and anything that is left he will return to Gandelman and Espenship.'"

Gandelman and Espenship worked a day or two on the job after the work had been taken over by Conneen company and then left because they were to be paid no more money as appears by the testimony of Mr. Gandelman who says that Mr. Conneen said, "if you care to work without drawing a salary, you can work, but to draw anything you won't get nothing." And on the night of November 4th, 1931, Mr. Gandelman took his tools and left.

The contract between Conneen company and Gandelman and Espenship also contained a provision as follows:

"That all materials delivered to the said premises shall be regarded as the property of said party of the first part (Conneen Construction Company) and shall not be removed without their consent."

The materials for which the claimants in this cause claim payment were all delivered for the purposes of this work and under the terms of the contract they were regarded as the property of Conneen Construction Company and such of them as were on the premises and which were delivered on the premises after Conneen company actually took charge of the work were used and taken possession of by Conneen company. *Page 280 In this respect, at least, the case before me differs from the case of George A. Mills, c., Co. v. Hegeman-Harris Co.,94 N.J. Eq. 802, largely relied upon by the Conneen company, in which the court of errors affirmed the opinion of Vice-Chancellor Griffin in the case of Morris County Golf Club v.Hegeman-Harris Co., 121 Atl. Rep. 528. There the contractor made a subcontract with J.C. Raab Company for carpenter work. Raab abandoned the work and the same was completed by the contractor at a loss to itself of $3,000. Stop-notices were served on the owners for work done and materials furnished to Raab.

In the present case the materials furnished to Gandelman and Espenship immediately were regarded as the property of Conneen company upon their delivery upon the premises and could well be said to have been furnished to it as well as to Gandelman and Espenship. From the testimony and the circumstances surrounding the taking over of the work by Conneen company I may well conclude that Conneen company treated these materials as having been furnished for the purpose of carrying out its general contract with the owner.

Section 3 of the Mechanics' Lien act as amended (P.L. 1930 p.974), provides as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
166 A. 458, 114 N.J. Eq. 276, 1933 N.J. Ch. LEXIS 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-michaels-v-conneen-constr-njch-1933.