Brown v. Home Development Co.

18 A.2d 742, 129 N.J. Eq. 172, 1941 N.J. Ch. LEXIS 74, 28 Backes 172
CourtNew Jersey Court of Chancery
DecidedMarch 13, 1941
DocketDocket 122/636
StatusPublished
Cited by25 cases

This text of 18 A.2d 742 (Brown v. Home Development Co.) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Home Development Co., 18 A.2d 742, 129 N.J. Eq. 172, 1941 N.J. Ch. LEXIS 74, 28 Backes 172 (N.J. Ct. App. 1941).

Opinion

It has been stipulated that I decide this case on bill, answers, replications and transcript of testimony taken in open court. Final hearing was had before the late Vice-Chancellor Francis B. Davis and, prior to his death, briefs had been filed and arguments of counsel heard. I requested and have had the benefit of oral re-argument. *Page 174

The bill here filed was in the nature of an interpleader bill. Complainant contracted with Home Development Company for the erection of a dwelling in Woodbury, Gloucester county, to cost $17,800. Contract and specifications were filed July 20th, 1937. The contractor abandoned work late in January or early in February, 1938. On January 4th, 1938, Suburban Lumber Company filed notice with the owner that it had furnished materials to the amount of $4,953.67, which sum, after demand, remained unpaid, and, on the same day, filed its stop-notice. The owner thereupon withheld payment from the contractor of the balance due under the contract, $8,012.30. Thereafter, between January 5th, 1938, and May 21st, 1938, other stop-notices were filed by laborers and materialmen on claims aggregating, approximately, $14,000.

In January, 1938, complainant took possession of his new dwelling. He has lived continuously therein all of the three years which have intervened. Nine months later, on September 16th, 1938, he filed the bill of complaint herein praying that the stop-notice claimants interplead and determine their rights to a balance of $5,703.89, which he admitted was available to them. He asked that he be allowed to retain from the balance of $8,012.30, the sum of $1,308.41 already expended by him to complete the contract, and "not more than the sum of $1,000," as necessary to be expended to remedy poor workmanship and materials furnished by the contractor. As to this latter item he asked leave to have it approved by arbitration in law. He also asked that proceedings, by claimants, be stayed until judgment on arbitration was given, and tendered himself as willing to pay into this court the balance due.

Complainant testified that there was "much, much delay" in the arbitration matter. Judgment was not had therein until March 15th, 1940. Thereafter this cause was brought on for final hearing, not at the instance of the complainant but at the instance of one of the defendants, Suburban Lumber Company.

Complainant is a member of the bar of this state. When this matter came on for final hearing before Vice-Chancellor Davis, more than two years after the filing of the bill of complaint, it was found that a decree pro confesso had not *Page 175 been entered as to the non-answering defendants. The Vice-Chancellor offered to make the decree. Upon re-argument before me, two years and four months after the filing of the bill, the decree pro confesso had still not been entered and complainant's counsel asked for a further delay to make proof of non-military service, which proof would not have been necessary had the decree been entered in due course prior to the enactment of the Soldiers' and Sailors' Civil Relief act of 1940.

Defendants, laborers and materialmen, have now waited more than three years for payment of their undisputed claims. They ask that complainant pay interest on the amount he alleged in his bill would be due them and which, it is agreed, is due. He resists this claim.

Complainant took the initiative in the matter of litigation, seeking relief in equity against a possible multiplicity of suits by laborers and materialmen in the law courts. Those laborers and materialmen, from the moment they contributed to the erection of complainant's home, had obtained an inchoate lien upon his liability to the contractor. Donnelly v. Johnes (Court ofChancery), 58 N.J. Eq. 442; 44 Atl. Rep. 180; Slingerland v.Binns (Court of Errors and Appeals), 56 N.J. Eq. 413.

When stop-notices were served in accordance with the requirements of the statute, the owner was obliged to retain, for the benefit of noticing creditors, all money which might thereafter come to be payable under the contract. Mayer v.Mutchler (Court of Errors and Appeals), 50 N.J. Law 162. A stop-notice, served, operates as an assignment pro tanto of the contract price owing by the owner to the contractor. R.S.2:60-117; Kreutz v. Cramer (Court of Chancery), 64 N.J. Eq. 648; 54 Atl. Rep. 535.

The balance of the contract price, as of the time the contract was abandoned, was $8,012.30. Complainant then expended $1,308.41 to complete the building and claimed that it would be necessary to expend, in addition, not more than $1,000 to make good inferior workmanship and materials. The claim of an owner, who completes a building, to an unexpended balance of the contract, is superior to that of *Page 176 stop-notice claims. Post v. Geldziler (Court of Errors andAppeals), 105 N.J. Law 370; 145 Atl. Rep. 323. As to the balance of $5,703.89, which complainant admitted to be due laborers and materialmen, an offer of tender into court was made in the bill of complaint but the money has never been paid over.

When a stop-notice has been served and money becomes due under the contract from the owner to the general contractor sufficient to pay that claim, the statute is mandatory that the owner pay the stop-notice claimant on being satisfied of the correctness of the demand. R.S. 2:60-119; Ford v. Roman Catholic Church ofOur Lady of Mt. Carmel, 9 N.J. Mis. R. 505; 154 Atl. Rep. 403. So continuing, the owner must pay in the order in which notices have been filed, R.S. 2:60-119, for stop-notices operate in succession and in the order of time of service, R.S. 2:60-119.Donnelly v. Johnes, supra. The owner is protected if he so pays. R.S. 2:60-120; St. Michael's Orphan Asylum, c., Hopewell v. Conneen Construction Co. (Court of Chancery), 114 N.J. Eq. 276; 166 Atl. Rep. 458; affirmed, 115 N.J. Eq. 334;170 Atl. Rep. 649.

Complainant has not contested any claim filed; in fact, he admits every claim to be correct in amount and to be justly due. He paid the claims of four laborers upon receipt of stop-notices from them and took assignments of their claims. He could have paid $5,703.89 to other claimants or into court. Instead, he retained the money and has had the benefit of holding that fund ever since. While he testified that he had the money in a separate account, he did not testify that he had not used any part thereof, that he had not received interest thereon or that retention of the money had not provided him with ready funds for any emergency.

Complainant suggests that he should not be now charged with interest because he was required to pay interest on the money he withheld. That is immaterial. His testimony is that he obtained a mortgage commitment, the money to become available when the building was completed. When $5,703.89 became payable to stop-notice claimants he had this money. Had they been paid, to the exhaustion of the *Page 177

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Goione
595 B.R. 477 (D. New Jersey, 2019)
Labov Mechanical, Inc. v. East Coast Power, L.L.C.
872 A.2d 142 (New Jersey Superior Court App Division, 2005)
Legge Ind. v. Kushner Hebrew Acad.
756 A.2d 608 (New Jersey Superior Court App Division, 2000)
Interchange State Bank v. Rinaldi
696 A.2d 744 (New Jersey Superior Court App Division, 1997)
Stewart v. Harris Structural Steel Co., Inc.
486 A.2d 1265 (New Jersey Superior Court App Division, 1984)
Tobin v. Jersey Shore Bank
460 A.2d 195 (New Jersey Superior Court App Division, 1983)
Davis Cattle Co., Inc. v. Great Western Sugar Company
393 F. Supp. 1165 (D. Colorado, 1975)
Busik v. Levine
307 A.2d 571 (Supreme Court of New Jersey, 1973)
Banish v. City of Hamtramck
157 N.W.2d 445 (Michigan Court of Appeals, 1968)
Jos. L. Muscarelle, Inc. v. Central Iron Mfg. Co.
379 F.2d 715 (Third Circuit, 1967)
McGlynn v. Schultz
218 A.2d 408 (New Jersey Superior Court App Division, 1966)
Cannon v. Bingman
383 S.W.2d 169 (Missouri Court of Appeals, 1964)
Lohmann v. Lohmann
154 A.2d 741 (New Jersey Superior Court App Division, 1959)
Jardine Estates, Inc. v. Donna Brook Corp.
126 A.2d 372 (New Jersey Superior Court App Division, 1956)
Thorp v. American Aviation & General Ins.
113 F. Supp. 764 (E.D. Pennsylvania, 1953)
Sawyer v. E. F. Drew & Co.
113 F. Supp. 527 (D. New Jersey, 1953)
JAS. FALCONE PLUMBING & HEATING CO. INC. v. Pasquale
97 A.2d 720 (New Jersey Superior Court App Division, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
18 A.2d 742, 129 N.J. Eq. 172, 1941 N.J. Ch. LEXIS 74, 28 Backes 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-home-development-co-njch-1941.