Arrow Builders Supply Corp. v. Hudson Terrace Apartments, Inc.

105 A.2d 387, 15 N.J. 418, 1954 N.J. LEXIS 287
CourtSupreme Court of New Jersey
DecidedMay 17, 1954
StatusPublished
Cited by17 cases

This text of 105 A.2d 387 (Arrow Builders Supply Corp. v. Hudson Terrace Apartments, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arrow Builders Supply Corp. v. Hudson Terrace Apartments, Inc., 105 A.2d 387, 15 N.J. 418, 1954 N.J. LEXIS 287 (N.J. 1954).

Opinions

The opinion of the court was delivered by

Jacobs, J.

The defendant Hudson Terrace Apartments, Inc. owned land located in Fort Lee, New Jersey. As owner, it entered into a written contract with the contractor, Glen-wood Builders, Inc., for the construction of apartment buildings. Before the commencement of work or the delivery of materials the contract was duly filed pursuant to R. S. 2:60-115 (now N. J. S. 2A:44-75). The contractor entered into an agreement with the subcontractor’ ARA Construction Corporation for the masonry work required in the buildings and the subcontractor purchased building materials from the plaintiffs. The materials were delivered by the plaintiffs to the building site and they were actually used in the erection and completion of the buildings. The subcontractor failed and refused to pay the plaintiffs the balance due for the materials and they filed stop notices with the county clerk in accordance with N. J. S. 2A :44-77. Copies of the stop notices were served upon the owner in accordance with N. J. S. 2A :44-78, 79. The claims of the materialmen be[420]*420ing disputed, they instituted action against the subcontractor and obtained judgments against him. See N. J. S. 2A :44-83-When the plaintiffs filed their stop notices there was no money due from the contractor to the subcontractor; the latter had defaulted in the performance of its contract thereby requiring the contractor to complete the masonry work. However, when the stop notices were filed there was due or about to become due sufficient sums from the owner to the contractor to pay the full claims of the plaintiffs.

The plaintiffs instituted separate actions in the Superior Court, Law Division, claiming that under the terms of the Mechanics’ Lien Law the defendant owner was obligated to pay their claims from the unpaid sums due from him to the contractor. The defendant denied liability, contending that the stop notices filed and served by the plaintiffs did not establish any “right of recourse or lien against the funds in the hands of the Owner due to the Contractor.” The actions were consolidated and the parties submitted the agreed facts as aforestated to the trial court for legal determination. Judge Leap, sitting in the Superior Court by temporary assignment, found in the defendant’s favor although his opinion suggested that the pertinent statutory provisions required a contrary result which he would have reached were it not for the decision of the Court of Errors and Appeals in Mills & Co. v. Hegeman-Harris Co., 94 N. J. Eq. 802, 806 (E. & A. 1923). But see St. Michael’s, etc., Hopewell v. Conneen Constr. Co., 114 N. J. Eq. 276 (Ch. 1933), affirmed 115 N. J. Eq. 334 (E. & A. 1934). The plaintiffs appealed to the Appellate Division and we certified on our own motion.

Our first statutory enactment relating to mechanics’ liens was adopted early in the 19th Century (L. 1820, p. 124); since then there have been many enactments designed to afford liens to persons who contribute labor or materials used in the construction of buildings. See Luce, Mechanics’ Lien Law of New Jersey (3d ed. 1923), 6; Lodge, Mechanics’ Liens in New Jersey (1940), 5. Erom time to time our courts have expressed misgivings as to the policies iinderly[421]*421ing the preferential treatment thus afforded by the Legislature. Ayres v. Revere, 25 N. J. L. 474, 481 (Sup. Ct. 1856); McNab & Harlin Mfg. Co. v. Paterson Building Co., 71 N. J. Eq. 133, 139 (Ch. 1906), affirmed 72 N. J. Eq. 929 (E. & A. 1907). And with these misgivings they have sometimes applied rather strict rules of statutory interpretation. See Dalrymple v. Ramsey, 45 N. J. Eq. 494, 496 (Ch. 1889); Associates of Jersey Co. v. Davison, 29 N. J. L. 415, 423 (E. & A. 1860). But see Rizzolo v. Poysher, 89 N. J. L. 618, 622 (E. & A. 1916). However, as we view our proper judicial function, it is not to pass j'udgment on the wisdom or policy of the legislation or to apply strict rules of interpretation which defeat legislative wishes; the constitutionality of the legislation not being disputed here (cf. Gardner & Meeks Co. v. N. Y. Central & H. R. R. Co., 72 N. J. L. 257 (E. & A. 1905)), our only function is fairly to seek and effectuate the legislative purpose now expressed in N. J. S. 2A :44-77-80. See Gardner & Meeks Co. v. Herold, 76 N. J. L. 524, 529 (E. & A. 1909). Cf. Board of National Missions v. Neeld, 9 N. J. 349, 353 (1952); De Lorenzo v. City of Hackensack, 9 N. J. 379, 387 (1952); Grobart v. Grobart, 5 N. J. 161, 166 (1950).

In 1835 the Legislature adopted “An Act Securing to Mechanics, and others, payment for their labor and materials in erecting any house, or other building, within the limits therein mentioned.” L. 1835, p. 148. Section 3 thereof provided the remedy by stop notice but it was available only to wage' claimants journeymen and laborers) and applied to funds due their employer from the owner of the building. Later enactments extended the terms of section 3 to persons who furnished materials used in the erection of the building but were refused payment by the contractor engaged by the owner. L. 1853, p. 438; L. 1863, p. 275. In 1895 section 3 was amended to provide that when stop notices were duly served by journeymen, laborers or materialmen the owner shall pay their claims upon the contractor’s continued refusal of payment, from funds then or thereafter due from the owner to the contractor. L. 1895, p. 313; L. 1898, p. [422]*422538. In 1905 section 3 was amended to extend to subcontractors; it provided that whenever any contractor refused to pay any person who furnished materials to him “or any sub-contractor, journeyman or laborer employed by him in erecting or constructing any building” then the stop notice remedy against the owner was available as therein prescribed. L. 1905, p. 311. See also L. 1910, p. 500. Cf. Stevenson, V. C. in McNab & Harlin Mfg. Co. v. Paterson Building Co., supra, 71 N. J. Eq. at page 144: “That the Legislature of this state had continuously for years favored the lien of the materialman by stop notice is quite apparent.”

In Carlisle v. Knapp, 51 N. J. L. 329 (E. & A. 1889), the Court had occasion to consider whether, under the legislation then in force, persons who furnished materials to subcontractors could seek recourse under section 3 against funds due or to become due from the owner to the contractor. The Court held that they could not upon the view that section 3 should be construed as affording protection only to creditors of the contractor and as not extending to creditors of subcontractors engaged by the contractor. However, in 1917 section 3 was again amended to enlarge its protective scope and this time it embodied language which was directly designed to protect materialmen and laborers who were employed by and were creditors of contractors other than the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burris v. Hilton Hotels Corp.
518 A.2d 511 (New Jersey Superior Court App Division, 1986)
Van Horn v. William Blanchard Co.
438 A.2d 552 (Supreme Court of New Jersey, 1981)
Newark Bldg. Assoc. v. Dir., Div. of Taxation
320 A.2d 867 (New Jersey Superior Court App Division, 1974)
Shore Block Corp. v. Lakeview Apartments
377 F.2d 835 (Third Circuit, 1967)
Martin v. Leonard Motor-El Paso
402 P.2d 954 (New Mexico Supreme Court, 1965)
Chesebro-Whitman Co., Inc. v. EDENBORO APTS.
207 A.2d 186 (New Jersey Superior Court App Division, 1965)
Lemke v. Bailey
196 A.2d 523 (Supreme Court of New Jersey, 1963)
Park v. Employment Security Commission
94 N.W.2d 407 (Michigan Supreme Court, 1959)
Breen v. Peck
146 A.2d 665 (Supreme Court of New Jersey, 1958)
Casale v. Housing Authority, City of Newark
125 A.2d 895 (New Jersey Superior Court App Division, 1956)
Moskowitz v. Herman
108 A.2d 426 (Supreme Court of New Jersey, 1954)
Arrow Builders Supply Corp. v. Hudson Terrace Apartments, Inc.
105 A.2d 387 (Supreme Court of New Jersey, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
105 A.2d 387, 15 N.J. 418, 1954 N.J. LEXIS 287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arrow-builders-supply-corp-v-hudson-terrace-apartments-inc-nj-1954.