National Radiator Co. v. Chelsea Housing Corp.

37 A.2d 279, 22 N.J. Misc. 193, 1944 N.J. Misc. LEXIS 14
CourtAtlantic County Circuit Court, N.J.
DecidedMarch 29, 1944
StatusPublished
Cited by1 cases

This text of 37 A.2d 279 (National Radiator Co. v. Chelsea Housing Corp.) is published on Counsel Stack Legal Research, covering Atlantic County Circuit Court, N.J. primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Radiator Co. v. Chelsea Housing Corp., 37 A.2d 279, 22 N.J. Misc. 193, 1944 N.J. Misc. LEXIS 14 (N.J. Ct. App. 1944).

Opinion

Burling, C. C. J.

This is a suit by three materialmen against the owner, general contractor and subeonstractor arising out of the construction of a private housing project in Atlantic City, Mew Jersey, under a filed contract. R. S. 2:60-115, et seq.; N. J. S. A. 2:60-115, et seq.

Motion has been made by the general contractor for a rule dropping it as a party defendant pursuant to R. S. 2:27-31; N. J. S. A. 2:27-31, and Supreme Court rule 41 N. J. S. A. tit. 2, as not being a proper party and that it has been misjoined. '

To decide the motion herein, immediate confrontment occurs with the problem as to whether a stop-notice of a materialman who furnishes to a subcontractor acts as assignment pro tanto of funds due a general contractor where a default in performance by the subcontractor has occurred and the cost of completion of that subcontract has wiped out any money otherwise due to the subcontractor from the contractor.

Subject to the cost to the owner to complete upon the default of the general contractor, a stop-notice of the material-men who furnished to the general contractor acts as an assignment pro tanto of the contract price owing by the owner to the contractor. Brown v. Home Development Co. (Court of Chancery, 1941), 129 N. J. Eq. 172; 18 Atl. Rep. (2d) 742.

The motion is resisted by the plaintiffs and it is contended by them that in the light of the opinion in St. Michael’s, &c., Hopewell v. Conneen Construction Co. (Court of Chancery, 1933), 114 N. J. Eq. 276; 166 Atl. Rep. 458; affirmed (Court of Errors and Appeals, 1933), 115 N. J. Eq. 334; 170 Atl. Rep. 649, such is the law of the State of Mew Jersey, and that the Mechanics’ Lien statute as a result of amendment in 1917 (chapter 241) and subsequent amendments thereto, now R. S. 2:60-116; N. J. S. A. 2:60-116, is so intended tó protect such materialmen and have their claims paid out of moneys due by the owner to the general contractor.

In the case of Carlisle v. Knapp (Court of Errors and [195]*195Appeals, 1889), 51 N. J. L. 329 (at p. 331); 17 Atl. Rep. 633, the inconvenience that would be placed upon a general contractor if such were the law was recognized in the construction of a former act which was held to limit relief to materialmen of the general contractor. Subsequent to the enactment of the amendment of the Mechanics’ Lien Statute of 1917 (chapter 241) hereinbefore referred to, adjudication construing this statute was made in the case of Morris County Golf Club v. Hegeman-Harris Co., hereinafter referred to as the Golf Club case (Court of Chancery, 1923), 121 Atl. Rep. 528 (not reported otherwise), and which was affirmed in the Court of Errors and Appeals without syllabus upon the opinion below, George A. Mills Co. v. Hegeman-Harris Co. (Court of Errors and Appeals, 1923), 94 N. J. Eq. 802; 122 Atl. Rep. 926; 125 Id. 127, and is controlling in the present situation. In that case in paragraph 1 of the syllabus of the opinion the following statement is made:

“Where subcontractor had not been paid in full when he abandoned work and the amount unpaid was insufficient to meet claims of materialmen filed under 3 Comp. Stat. 1910, p. 3294, § 3, as amended by Act March 29th, 1917 (Pamph. L., p. 821 [N. J. S. A. 2:60-116]), and the principal contractor’s loss in completing the subcontractor’s work exceeded the balance due the subcontractor, the principal contractor’s claim for such loss was superior to those of materialmen, and he was entitled to the whole of the sum due the subcontractor.”

And in the body of the opinion the following:

“As the fund is insufficient to pay the contractor, it is entitled to the whole fund, unless by reason of the Mechanics’ Lien Act (3 Comp. Stat. 1910, p. 3290, et seq. [N. J. S. A. 2:60-l 05, et seq.), the claims of the claimants under stop-notices take precedence of the claim of the contractor. * * * “The only point that can be asserted in favor of these claimants is that, in certain instances the contractor paid in advance of the terms of its contract to Taab.”

The plaintiffs contend that the effect of the decisions in the ease of St. Michael’s, &c., Hopewell v. Conneen Construction Co., supra, hereinbefore referred to is to overrule the construction placed upon the pertinent statute in the Golf [196]*196Club case, and that the statute is clearly intended to protect the materialmen and to have their claims paid out of the money due by the owner to the general contractor, regardless of the default of the subcontractor with whom they contracted, and that the cost of the completion of that subcontract has wiped out any moneys due otherwise to the subcontractor from the general contractor.

The plaintiffs contend that the reasoning of the United States District Court Judge for the District of New Jersey, in an unreported opinion in Nolan v. Chelsea Housing Corp., in a cause of action relating to this very project, gives effect to the legislative intent in the following language:

“The effect of this later decision [St. Michael's, &c., Hopewell v. Conneen Construction Co., 114 N. J. Eq. 276; 166 Atl. Rep. 458; affirmed, 115 N. J. Eq. 334; 170 Atl. Rep. 649], as I see it, is contrary to the principle established in the Golf Club case. It is sure that to some extent it relies upon the clause in the contract as to the passing of ownership of delivered materials to the contractor, and yet a careful reading indicates that the Vice-Chancellor did not agree with the determination in the former case. This latter case was affirmed by the Court of Errors and Appeals without opinion in that court, and by a divided court — eleven for affirmance, three for reversal.

“I believe I am following the latest decision of the Court of Errors and Appeals when I determine that plaintiff is entitled to the amount claimed as principal with interest.”

The soundness of this construction was attacked in an appeal from the said decision of the United States District Court for the District of New Jersey, and the Circuit Court of Appeals held that the rule in the Mills & Co. v. Hegeman-Harris Co., hereinbefore referred to as the Golf Club case (supra) remained undisturbed as the law. This opinion is reported in 128 Fed. Rep. (2d) 872 (U. S. Court of Appeals, Third District, 1942).

It has been contended by the plaintiffs that this decision is not binding in the state court in this cause of action, and while such is the case still the weight and dignity of that opinion is not to be lightly disregarded.

[197]*197The decision in the Golf Club case remained undisturbed and without judicial deviation therefrom until 1933, in the St. Michael’s, &c., Hopewell v. Conneen Construction Co., supra, case, and no other pertinent adjudications have been made subsequent to the St. Michael’s, &c., Hopewell v. Conneen Construction Co., supra, case.

To avoid the effect of the decision in the Golf Club case, it is necessary to differentiate the facts in a given ease.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arrow Builders Supply Corp. v. Hudson Terrace Apartments, Inc.
105 A.2d 387 (Supreme Court of New Jersey, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
37 A.2d 279, 22 N.J. Misc. 193, 1944 N.J. Misc. LEXIS 14, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-radiator-co-v-chelsea-housing-corp-njcirctatlantic-1944.