L & W Supply Corp. v. DeSilva

57 A.3d 558, 429 N.J. Super. 179, 2012 N.J. Super. LEXIS 189
CourtNew Jersey Superior Court Appellate Division
DecidedDecember 19, 2012
StatusPublished
Cited by4 cases

This text of 57 A.3d 558 (L & W Supply Corp. v. DeSilva) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L & W Supply Corp. v. DeSilva, 57 A.3d 558, 429 N.J. Super. 179, 2012 N.J. Super. LEXIS 189 (N.J. Ct. App. 2012).

Opinion

The opinion of the court was delivered by

ASHRAFI, J.A.D.

This appeal requires our application of the Construction Lien Law, N.J.S.A. 2A:44A-1 to -38, where a subcontractor became insolvent and did not pay for all the materials it purchased for a building project. The Supreme Court held in Craft v. Stevenson Lumber Yard, Inc., 179 N.J. 56, 63, 843 A.2d 1076 (2004), that a materials supplier that seeks to file a construction lien has a duty [183]*183to apply payments correctly against several open accounts of a materials purchaser, such as a subcontractor, if the supplier has reason to know that the payment funds came from a particular building project. We now consider the obligation of the materials supplier “to ascertain the source of ... payments and to apply them accordingly.” Id. at 76, 843 A.2d 1076.

Plaintiff L & W Supply Corporation sold building materials on credit to a now-bankrupt subcontractor, Detail Contractors, Inc. When Detail failed to pay the full balance due for the materials, L & W filed a construction lien against the project for which the materials were supplied. Defendant Patock Construction Co., Inc. was the prime or general contractor for the project; defendant Extended Medical Care Corp./Meridian Health/Meridian Nursing & Rehabilitation (“Meridian”) was the owner of the property and of the construction project; and defendant Travelers Casualty and Surety Company of America was the surety. Defendants now appeal from summary judgment entered in favor of L & W on its lien claim. We reverse and remand for trial as to defendants Patock and Travelers, and we reverse the judgment outright as to defendant Meridian.

I.

A.

The Construction Lien Law allows a contractor or supplier who is owed payment for its work or materials to file a lien against the real property on which the improvements are constructed. N.J.S.A. 2A:44A-3a. The primary purpose of this law is to secure payment of monies due to contractors and suppliers of a construction project. Thomas Grp., Inc. v. Wharton Senior Citizen Hous., Inc., 163 N.J. 507, 517, 750 A.2d 743 (2000).

A secondary purpose is to “protect owners” against paying more than once for the same work or materials. Labov Mech., Inc. v. E. Coast Power, L.L.C., 377 N.J.Super. 240, 245, 872 A.2d 142 (App.Div.2005). To effect the second purpose, the statute [184]*184limits the lien to the amount available in the “lien fund,” which “shall not exceed the unpaid portion of the contract price of the claimant’s contract for the work, services, material or equipment provided.” N.J.S.A. 2A:44A-9a.

In the case of a supplier, the lien fund is defined as the lesser of (1) the amount of the prime contract price earned minus amounts already paid by the owner to the prime contractor, or (2) the amount the subcontractor has earned on the subcontract price minus amounts already paid by the prime contractor to the subcontractor. N.J.S.A. 2A:44A-9b(2).

When a lien claim is filed, the owner or prime contractor may pay the amount of a valid claim directly to the claimant and credit that payment against the subcontract price. N.J.S.A. 2A:44A-12. Alternatively, the owner or prime contractor may post a surety bond for 110% of the lien amount and release the owner’s property from the claim. N.J.S.A. 2A:44A-31a, -32.

B.

In this case, L & W filed a construction lien in July 2006 and, several months later, filed a complaint against defendants to collect on its lien claim.1 L & W alleged it had supplied materials ordered by Detail for Meridian’s construction project but that Detail had not paid all amounts due for those materials. After defendants answered the complaint, the litigation was delayed because of Detail’s bankruptcy case. Eventually, the remaining parties filed cross-motions for summary judgment. Viewed most favorably to the non-prevailing parties, that is, defendants, see R. 4:46—2(c); Brill v. Guardian Life Ins. Co. of Am., 142 N.J. 520, 540, 666 A.2d 146 (1995), the summary judgment record revealed the following facts.

[185]*185In December 2003, Meridian entered into a contract with Patock as the general contractor to build an assisted living facility in Wall Township (“the Meridian project”). Patock, in turn, subcontracted with Detail to perform the metal stud, drywall, and carpentry work for the Meridian project. Detail was one of several entities owned and operated by defendant Joe DeSilva. In November 2005, Patock and Detail executed a subcontract priced at $1.2 million. Change orders eventually raised Detail’s subcontract price to approximately $1,375 million.

L & W is a supplier of drywall, studs, and related materials. In 2003, L & W opened an account for Joe DeSilva to obtain materials on credit for his several business entities engaged in construction work. During 2006, DeSilva had open accounts with L & W for building projects other than the Meridian project. Through July 2006, L & W sold on credit to DeSilva materials for the Meridian project priced at $231,794.34.

From February 16 to July 10, 2006, Patock paid Detail $891,159.66 for the Meridian subcontract based on monthly requisitions from Detail, which included the costs of the materials supplied by L & W. In June 2006, Patock paid an additional $53,202.74 on behalf of Detail for past due fringe benefits owed to the carpenters’ union. Thus the payments from Patock to or on behalf of Detail as of July 2006 totaled $944,362.40.

During the same time period, Detail paid $207,000 to L & W and another DeSilva entity paid $10,000 to L & W. Of the total $217,000 it received, L & W credited $103,959.45 to the Meridian project and the remaining $113,040.55 to other DeSilva accounts. L & W’s accounting left a balance of $127,834.89 unpaid for materials it had delivered to the Meridian project. On July 26, 2006, L & W filed a construction lien in the last-stated amount against the Meridian project.

At the time the construction lien was filed, the lien fund—that is, the difference in the amount Patock owed on the subcontract and the amount it had paid Detail—was $380,407.60 (calculated as the adjusted subcontract price of $1,374,770.00 minus $944,362.40 [186]*186paid by Patoek to Detail). Thus, the amount of the lien fund was substantially more than L & W’s lien claim of $127,834.89.2

After receiving notice of the lien claim, Patoek, as principal, and Travelers, as surety, posted a construction lien bond, see N.J.S.A. 2A:44A-31a, thus discharging Meridian’s property from the lien, see N.J.S.A. 2A:44A-32. In November 2006, L & W commenced this action against all three defendants, as well as against Joe DeSilva and DeSilva’s business entities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
57 A.3d 558, 429 N.J. Super. 179, 2012 N.J. Super. LEXIS 189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-w-supply-corp-v-desilva-njsuperctappdiv-2012.