NOTICE 2025 IL App (5th) 241332-U NOTICE Decision filed 02/20/25. The This order was filed under text of this decision may be NO. 5-24-1332 Supreme Court Rule 23 and is changed or corrected prior to the filing of a Petition for not precedent except in the
Rehearing or the disposition of IN THE limited circumstances allowed the same. under Rule 23(e)(1). APPELLATE COURT OF ILLINOS
FIFTH DISTRICT ______________________________________________________________________________
TINDALL CONSTRUCTION, INC., ) Appeal from the an Illinois Corporation, ) Circuit Court of ) Madison County. Plaintiff-Appellee, ) ) v. ) ) No. 24-CH-42 SRI GANESH REALTY 2, LLC; ) NP TRADEPORT LAND HOLDINGS, LLC; ) MILLENNIUM BANK; and UNKNOWN ) OWNERS and NON-RECORD CLAIMAINTS, ) ) Defendants ) Honorable ) Ronald J. Foster Jr., (SRI Ganesh Realty 2, LLC, Defendant-Appellant). ) Judge, presiding. ______________________________________________________________________________
JUSTICE MOORE delivered the judgment of the court. Justices Boie and Sholar concurred in the judgment.
ORDER
¶1 Held: The circuit court erred in denying the motion to compel arbitration and stay the proceedings pending arbitration. We reverse the circuit court’s order of November 22, 2024, and remand with instructions to enter an order compelling arbitration and stay the proceedings.
¶2 The defendant, SRI Ganesh Realty 2, LLC (SRI), appeals the November 22, 2024, order
of the circuit court of Madison County which denied its motion to compel arbitration and stay the
proceedings until the completion of the arbitration. For the following reasons, we reverse the
circuit court’s order of November 22, 2024, and remand with instructions to enter an order
1 referring the matter to arbitration and stay the remaining proceedings until the arbitration is
completed.
¶3 I. BACKGROUND
¶4 On July 22, 2024, the plaintiff, Tindall Construction, Inc. (Tindall) filed a five-count
verified complaint in the circuit court of Madison County regarding improvements to five real
estate parcels located in Madison County referred to as “Lot 044,” “Lot 053,” “Lot 054,” and “Lot
055.” Count I sought to foreclose a mechanic’s lien against the defendant, NP Tradeport Land
Holdings, LLC (NP) related to Lot 044. Count II alleged an unjust enrichment claim against NP
related to Lot 044. Count III sought to foreclose a mechanic’s lien against defendants, SRI and
Millennium Bank (Bank), related to Lots 053, 054, and 055. Count IV alleged a breach of contract
claim against SRI regarding all of the lots. The complaint alleged that Tindall and SRI entered into
a contract on November 20, 2023. Count V alleged an unjust enrichment claim against SRI
regarding Lots 053, 054, and 055.
¶5 Tindall’s complaint included several exhibits. Exhibit A to the complaint was a document
titled “Construction Contract,” and which stated the date of the contract was November 20, 2023
(November contract). Exhibit B to the complaint was a May 17, 2024, letter from Tindall’s counsel
to SRI demanding payment for an outstanding balance. Exhibit C to the complaint was a verified
notice of subcontractor’s claim of mechanic’s lien regarding work performed on Lot 044 under “a
written contract, dated February 1, 2023.” The lien was executed on June 10, 2024, and recorded
in Madison County on July 10, 2024. Exhibit D to the complaint was a verified original
contractor’s mechanic’s lien regarding work performed on Lot 053 which provided, inter alia,
“[t]hat on February 1, 2023, Owner and Tindall entered into a contract whereby Owner agreed to
pay Tindall the total amount of $3,231,889.00 for construction and site improvement work at the
2 Property (the ‘Contract’).” The lien was executed on June 10, 2024, and recorded in Madison
County on July 10, 2024. Exhibit E to the complaint was a verified original contractor’s
mechanic’s lien regarding work performed on Lot 054 which provided, inter alia, “[t]hat on
February 1, 2023, Owner and Tindall entered into a contract whereby Owner agreed to pay Tindall
the total amount of $3,231,889.00 for construction and site improvement work at the Property (the
‘Contract’).” The lien was executed on June 10, 2024, and recorded in Madison County on July
10, 2024. Exhibit F to the complaint was a verified original contractor’s mechanic’s lien regarding
work performed on Lot 055 which provided, inter alia, “[t]hat on February 1, 2023, Owner and
Tindall entered into a contract whereby Owner agreed to pay Tindall the total amount of
$3,231,889.00 for construction and site improvement work at the Property (the ‘Contract’).” The
lien was executed on June 10, 2024, and recorded in Madison County on July 10, 2024.
¶6 On August 16, 2024, SRI filed a motion to compel arbitration and stay the action until the
arbitration was completed. SRI’s motion to compel arbitration denied entering into the November
20, 2023, contract but acknowledged entering into a contract with Tindall on February 1, 2023, for
the same work covered by the purported November contract. SRI attached the February contract
as an exhibit to its motion to compel. SRI argued that the February contract and the purported
November contract contained identical general conditions. Section 18 of the general conditions
contained an arbitration clause, which provides:
“18. Resolution of Disputes: Any claim, dispute, or controversy between Owner
[SRI] and Contractor [Tindall] arising out of or relating to the Contract or other Contract
Documents, or the breach thereof, shall, in the sole discretion of Owner, be decided by
arbitration in accordance with the AAA’s Construction Industry Arbitration Rules and
Mediation Procedures. The arbitration tribunal shall determine the rights and obligations
3 of the parties according to the laws of Illinois, excluding its conflict of laws principles;
provided, however, the law applicable to the validity of the arbitration clause, the
enforcement of any award, and any other question of arbitration law or procedure shall be
the Federal Arbitration Act, 9 U.S.C.A. § 2. The award rendered by the arbitrator(s) shall
be final and binding and judgment may be entered upon it in accordance with applicable
law in any court of competent jurisdiction. Contractor shall promptly proceed with Work
pending resolution of any claim, dispute or controversy, and failure to do so is a material
breach of the Contract.”
¶7 Tindall filed a response in opposition to the motion to compel arbitration and stay litigation.
Tindall argued that since SRI denied entering into the November contract that it could not enforce
the arbitration clause contained within said contract.
¶8 On November 14, 2024, the circuit court held a nonevidentiary hearing on the motion to
compel arbitration and stay the proceedings. The circuit court agreed with Tindall and by written
order entered on November 22, 2024, denied the motion to compel arbitration and stay the
litigation because SRI denied entering into the November contract. The circuit court’s order did
not make findings of fact. SRI filed a timely notice of interlocutory appeal.
¶9 II. ANALYSIS
¶ 10 On appeal, SRI contends that the circuit court erred in denying its motion to compel
arbitration and stay the proceedings. SRI points to the arbitration agreement contained in both the
February contract and the purported November contract.
Free access — add to your briefcase to read the full text and ask questions with AI
NOTICE 2025 IL App (5th) 241332-U NOTICE Decision filed 02/20/25. The This order was filed under text of this decision may be NO. 5-24-1332 Supreme Court Rule 23 and is changed or corrected prior to the filing of a Petition for not precedent except in the
Rehearing or the disposition of IN THE limited circumstances allowed the same. under Rule 23(e)(1). APPELLATE COURT OF ILLINOS
FIFTH DISTRICT ______________________________________________________________________________
TINDALL CONSTRUCTION, INC., ) Appeal from the an Illinois Corporation, ) Circuit Court of ) Madison County. Plaintiff-Appellee, ) ) v. ) ) No. 24-CH-42 SRI GANESH REALTY 2, LLC; ) NP TRADEPORT LAND HOLDINGS, LLC; ) MILLENNIUM BANK; and UNKNOWN ) OWNERS and NON-RECORD CLAIMAINTS, ) ) Defendants ) Honorable ) Ronald J. Foster Jr., (SRI Ganesh Realty 2, LLC, Defendant-Appellant). ) Judge, presiding. ______________________________________________________________________________
JUSTICE MOORE delivered the judgment of the court. Justices Boie and Sholar concurred in the judgment.
ORDER
¶1 Held: The circuit court erred in denying the motion to compel arbitration and stay the proceedings pending arbitration. We reverse the circuit court’s order of November 22, 2024, and remand with instructions to enter an order compelling arbitration and stay the proceedings.
¶2 The defendant, SRI Ganesh Realty 2, LLC (SRI), appeals the November 22, 2024, order
of the circuit court of Madison County which denied its motion to compel arbitration and stay the
proceedings until the completion of the arbitration. For the following reasons, we reverse the
circuit court’s order of November 22, 2024, and remand with instructions to enter an order
1 referring the matter to arbitration and stay the remaining proceedings until the arbitration is
completed.
¶3 I. BACKGROUND
¶4 On July 22, 2024, the plaintiff, Tindall Construction, Inc. (Tindall) filed a five-count
verified complaint in the circuit court of Madison County regarding improvements to five real
estate parcels located in Madison County referred to as “Lot 044,” “Lot 053,” “Lot 054,” and “Lot
055.” Count I sought to foreclose a mechanic’s lien against the defendant, NP Tradeport Land
Holdings, LLC (NP) related to Lot 044. Count II alleged an unjust enrichment claim against NP
related to Lot 044. Count III sought to foreclose a mechanic’s lien against defendants, SRI and
Millennium Bank (Bank), related to Lots 053, 054, and 055. Count IV alleged a breach of contract
claim against SRI regarding all of the lots. The complaint alleged that Tindall and SRI entered into
a contract on November 20, 2023. Count V alleged an unjust enrichment claim against SRI
regarding Lots 053, 054, and 055.
¶5 Tindall’s complaint included several exhibits. Exhibit A to the complaint was a document
titled “Construction Contract,” and which stated the date of the contract was November 20, 2023
(November contract). Exhibit B to the complaint was a May 17, 2024, letter from Tindall’s counsel
to SRI demanding payment for an outstanding balance. Exhibit C to the complaint was a verified
notice of subcontractor’s claim of mechanic’s lien regarding work performed on Lot 044 under “a
written contract, dated February 1, 2023.” The lien was executed on June 10, 2024, and recorded
in Madison County on July 10, 2024. Exhibit D to the complaint was a verified original
contractor’s mechanic’s lien regarding work performed on Lot 053 which provided, inter alia,
“[t]hat on February 1, 2023, Owner and Tindall entered into a contract whereby Owner agreed to
pay Tindall the total amount of $3,231,889.00 for construction and site improvement work at the
2 Property (the ‘Contract’).” The lien was executed on June 10, 2024, and recorded in Madison
County on July 10, 2024. Exhibit E to the complaint was a verified original contractor’s
mechanic’s lien regarding work performed on Lot 054 which provided, inter alia, “[t]hat on
February 1, 2023, Owner and Tindall entered into a contract whereby Owner agreed to pay Tindall
the total amount of $3,231,889.00 for construction and site improvement work at the Property (the
‘Contract’).” The lien was executed on June 10, 2024, and recorded in Madison County on July
10, 2024. Exhibit F to the complaint was a verified original contractor’s mechanic’s lien regarding
work performed on Lot 055 which provided, inter alia, “[t]hat on February 1, 2023, Owner and
Tindall entered into a contract whereby Owner agreed to pay Tindall the total amount of
$3,231,889.00 for construction and site improvement work at the Property (the ‘Contract’).” The
lien was executed on June 10, 2024, and recorded in Madison County on July 10, 2024.
¶6 On August 16, 2024, SRI filed a motion to compel arbitration and stay the action until the
arbitration was completed. SRI’s motion to compel arbitration denied entering into the November
20, 2023, contract but acknowledged entering into a contract with Tindall on February 1, 2023, for
the same work covered by the purported November contract. SRI attached the February contract
as an exhibit to its motion to compel. SRI argued that the February contract and the purported
November contract contained identical general conditions. Section 18 of the general conditions
contained an arbitration clause, which provides:
“18. Resolution of Disputes: Any claim, dispute, or controversy between Owner
[SRI] and Contractor [Tindall] arising out of or relating to the Contract or other Contract
Documents, or the breach thereof, shall, in the sole discretion of Owner, be decided by
arbitration in accordance with the AAA’s Construction Industry Arbitration Rules and
Mediation Procedures. The arbitration tribunal shall determine the rights and obligations
3 of the parties according to the laws of Illinois, excluding its conflict of laws principles;
provided, however, the law applicable to the validity of the arbitration clause, the
enforcement of any award, and any other question of arbitration law or procedure shall be
the Federal Arbitration Act, 9 U.S.C.A. § 2. The award rendered by the arbitrator(s) shall
be final and binding and judgment may be entered upon it in accordance with applicable
law in any court of competent jurisdiction. Contractor shall promptly proceed with Work
pending resolution of any claim, dispute or controversy, and failure to do so is a material
breach of the Contract.”
¶7 Tindall filed a response in opposition to the motion to compel arbitration and stay litigation.
Tindall argued that since SRI denied entering into the November contract that it could not enforce
the arbitration clause contained within said contract.
¶8 On November 14, 2024, the circuit court held a nonevidentiary hearing on the motion to
compel arbitration and stay the proceedings. The circuit court agreed with Tindall and by written
order entered on November 22, 2024, denied the motion to compel arbitration and stay the
litigation because SRI denied entering into the November contract. The circuit court’s order did
not make findings of fact. SRI filed a timely notice of interlocutory appeal.
¶9 II. ANALYSIS
¶ 10 On appeal, SRI contends that the circuit court erred in denying its motion to compel
arbitration and stay the proceedings. SRI points to the arbitration agreement contained in both the
February contract and the purported November contract.
¶ 11 An order of the circuit court granting or denying a motion to compel arbitration is
injunctive in nature and appealable under Illinois Supreme Court Rule 307(a)(1) (eff. Nov. 1,
2017). Salsitz v. Kreiss, 198 Ill. 2d 1, 11 (2001). Generally, the standard of review for a decision
4 on a motion to compel arbitration is whether there was a showing sufficient to sustain the circuit
court’s order. Keefe v. Allied Home Mortgage Corp., 393 Ill. App. 3d 226, 229 (2009). However,
like in the present matter, where “the circuit court rendered its decision without an evidentiary
hearing and without findings of fact, the standard of review is de novo. Id.
¶ 12 “A motion to compel arbitration and stay the proceedings is essentially a section 2-
619(a)(9) [of the Code of Civil Procedure] motion to stay an action in the trial court based on an
affirmative matter—the exclusive remedy of arbitration.” Gaines v. Ciox Health, LLC, 2024 IL
App (5th) 230565, ¶ 25. The party seeking arbitration has the initial burden to establish the parties
made a valid agreement to arbitrate and the controversy is within the scope of the arbitration
agreement. Id.
¶ 13 The purported arbitration agreement that SRI seeks to enforce is governed by the United
States Arbitration Act (9 U.S.C. § 2 (2024)), commonly known as the Federal Arbitration Act
(FAA), and the arbitration proceedings would be conducted in accordance with the rules of the
American Arbitration Association (AAA). “Under the FAA, state courts and federal courts are
authorized to stay an action and compel arbitration upon being satisfied that the issue involved in
the action or proceeding is referable to arbitration under a written agreement to arbitrate.” Gaines,
2024 IL App (5th) 230565, ¶ 26. When considering a motion to compel arbitration, the circuit
court must decide whether a valid arbitration agreement exists. Id.
¶ 14 “A fact admitted in a verified pleading is considered a judicial admission, conclusive
against the pleader, and dispenses with proof on that fact.” Id. ¶ 35. Exhibits are a part of the
complaint to which they are attached, and “the factual allegations contained within an exhibit
attached to a complaint serve to negate inconsistent allegations of fact contained within the body
of the complaint.” Burton v. Airborne Express, Inc., 367 Ill. App. 3d 1026, 1034 (2006).
5 ¶ 15 In this case, Tindall filed a verified complaint with exhibits. Exhibits C, D, E, and F
consisted of verified mechanic’s liens. The first prerequisite for bringing a contractor’s mechanic’s
lien is a valid contract. Tefco Construction Co. v. Continental Community Bank & Trust Co., 357
Ill. App. 3d 714, 719 (2005). Additionally, a mechanic’s lien is required to be verified. Id. at 722.
¶ 16 The verified mechanic’s liens which were attached to the complaint in the present action
state they are pursuant to a contract entered into on February 1, 2023. The liens were sworn on
oath and signed by Christopher Tindall. These verified statements are binding judicial admissions.
¶ 17 The circuit court focused on the dispute regarding the purported November contract. SRI
met its initial burden to establish the parties made a valid agreement to arbitrate and the controversy
is within the scope of the arbitration agreement with its motion to compel that provided the
February contract. Then when we examine Tindall’s own complaint and exhibits, SRI’s claim that
a February contract was entered into cannot be refuted based on the binding judicial admissions
contained within the mechanic’s liens. The February contract contains an agreement to arbitrate
“[a]ny claim, dispute, or controversy between Owner [SRI] and Contractor [Tindall] arising out of
or relating to the Contract or other Contract Documents, or the breach thereof.” Accordingly, the
parties’ dispute regarding an alleged breach of contract and whether the February contract was
amended or superseded should be referred to arbitration.
¶ 18 III. CONCLUSION
¶ 19 For the reasons stated, the circuit court’s order denying the motion to compel arbitration
and stay the proceedings is reversed. The cause is remanded with instructions to enter an order
referring the matter to arbitration and stay the remaining proceedings until the arbitration is
¶ 20 Reversed and remanded.