McCarthy Brothers Co. v. State

47 Ill. Ct. Cl. 15, 1995 Ill. Ct. Cl. LEXIS 2
CourtCourt of Claims of Illinois
DecidedFebruary 21, 1995
DocketNos. 82-CC-0565, 84-CC-0375 cons.
StatusPublished
Cited by2 cases

This text of 47 Ill. Ct. Cl. 15 (McCarthy Brothers Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCarthy Brothers Co. v. State, 47 Ill. Ct. Cl. 15, 1995 Ill. Ct. Cl. LEXIS 2 (Ill. Super. Ct. 1995).

Opinion

OPINION

Frederick, J.

These two cases arose from the construction of the Basic Science Building for the University of Illinois College of Veterinary Medicine in Urbana, Illinois. The claims were consolidated into one claim from two original claims filed respectively by McCarthy Brothers Company in 1981 and the Waldinger Company in 1983. McCarthy Brothers Company (hereinafter referred to as “McCarthy”) filed its complaint with the Court of Claims on October 13, 1981, seeking $97,633.95 in damages from the State of Illinois, through its agency, capital development board (hereinafter referred to as “CDB”), for damages it incurred as a result of the Respondent’s alleged breach of contract. The Waldinger Company (hereinafter referred to as “TWC”) filed its complaint in the Court of Claims on September 1, 1983. TWC then amended its complaint on September 24, 1983, seeking $709,929.03 in damages from the State for damages incurred as a result of the breach of contract by the Respondent. The Court consolidated the two claims on May 11, 1984.

A trial was held before the Commissioner assigned to the case on the following dates: July 13 through 14, 1992, and July 20, 1992. The evidence in this case is voluminous and consists of hundreds of pages of contract documents, award letters, construction plans and designs, correspondence among the parties and other contractors, engineers and architects, photographs of the construction site, depositions, joint stipulations to uncontested facts, and the report of the proceedings.

The Facts

The construction project which is the subject of this litigation is the Basic Science Building of the College of Veterinary Medicine at the University of Illinois in Urbana, Illinois. In 1979, the Capital Development Board issued a series of contracts to the significant contractors as required under Illinois law. Construction was to proceed under two distinct phases, being Phase I and Phase II. Phase I involved site preparation and the erection of structural steel and concrete frame. Phase II principally involved the exterior and interior finishing of the structure.

McCarthy was awarded the contract to perform Phase I structural work and entered into a contract dated July 27, 1979, with CDB. In addition to erecting the structural frame for the building, McCarthy was to provide the Phase I “Temporary Utilities.” The CDB set forth all requirements in the project manual. Howard Peters was in charge of the field work for McCarthy. TWC entered prime contracts under both phases of the construction. Under Phase I, TWC entered a contract with the CDB for the construction of underground utilities. Under Phase II of the project, TWC entered contracts with CDB for heating and ventilation. Richard Wyninger was in charge of the field work for TWC. The work began in the early fall of 1979.

CDB s senior project manager for the project was Eugene Barish. As the senior project manager, he was the employee of CDB. Mr. Barish was responsible for monitoring the progress of the work. He was also acting as liaison between the architect-engineer, the prime contractors, the using agency, CDB and each of them for acting on any changes and work orders.

The architect-engineer for the project was Lester B. Knight & Associates, Inc. (hereinafter referred to as “Knight”). As architect-engineer, Knight was CDB s representative for the purpose of observing the work for conformance with the plans and specifications. Knight was also responsible for processing and approving all change orders issued in connection with the work on the project. Knight’s contract provided that the “Architect-Engineer shall prepare when authorized by CDB, minor modifications and applications for change orders * 8 * and shall review and make recommendations on contractor’s proposals.” John Larson was the on-site representative for Knight. Scott Lawson was the designated Knight project architect.

In performance of its Phase I contract, TWC interfaced with McCarthy’s work and certain of TWC’s work was dependent upon the prior completion by McCarthy of its work. The same was true with respect to the Phase II contracts of TWC. McCarthy was responsible for constructing the basement foundation walls, the basement floor slab, driving certain pilings immediately adjacent to the basement walls, and backfilling the walls. A third contractor, C. Ibe'r and Sons, was responsible for the placement of the first floor concrete slab.

McCarthy commenced work on the project on October 1, 1979. During the performance of its Phase I work, McCarthy failed to maintain its scheduled performance, due to a problem in the driving sequence of certain piles causing movement of the adjacent walls. This delayed the performance of other Phase I and Phase II contractors, such as TWC. The problem with the driving sequence is at the heart of this litigation. The construction plan contained a Drawing S-l which set the special pile driving sequence McCarthy was instructed to follow. Drawing S-l specified that McCarthy would not drive the pilings immediately adjacent to the foundation walls until after the walls were poured and backfilling was complete.

As work proceeded through 1979, McCarthy informed CDB that the special driving sequence posed serious problems and should be changed. McCarthy specifically noted the sequence would cause delays in the completion of work and that if the walls were backfilled prior to driving the piles, the walls would move during the pile-driving sequence. Beginning in November 1979, McCarthy requested CDB and Knight to change the sequence; however, the requests were denied.

Pursuant to Drawing S-l, Foundations, section 2, McCarthy was contractually required to brace the basement walls * * to resist soil pressure until floor systems are completely poured.” Included in its bid price was the only bracing system and materials described in the contract documents and actually provided to the project, to wit: a conventional lumber bracing system typically used on similar type projects with shoring on the top walls. On January 15, 1980, McCarthy advised CDB and Knight that the pressure exerted on the basement walls as a result of the pile-driving operation would greatly exceed the pressure of the soil. McCarthy restated that they were only required to provide bracing sufficient to resist soil pressure, not to resist the force resulting from the pile driving. At this time, McCarthy requested Knight and CDB to provide it with direction for bracing the basement walls to resist the force of the pile-driving sequence.

On January 16, 1980, Knight advised McCarthy that it would provide McCarthy with direction respecting the bracing needed to resist the force of the pile driving. Two days later, Knight changed its mind and informed McCarthy it would not give any direction on bracing. McCarthy repeatedly through February 13, 1980, to July 1980 requested that it be permitted to drive the pile before the basement walls were poured and backfilled in order to avoid the problem. C. Iber and Sons, Inc. joined McCarthy in these requests. Knight refused all requests to change the pile driving sequence.

Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Genie Construction Co. v. State
51 Ill. Ct. Cl. 153 (Court of Claims of Illinois, 1999)
American Janitorial Services, Inc. v. State
50 Ill. Ct. Cl. 208 (Court of Claims of Illinois, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
47 Ill. Ct. Cl. 15, 1995 Ill. Ct. Cl. LEXIS 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccarthy-brothers-co-v-state-ilclaimsct-1995.