George W. Sturm, Doing Business as George W. Sturm Associates v. The United States

421 F.2d 723, 190 Ct. Cl. 691, 1970 U.S. Ct. Cl. LEXIS 109
CourtUnited States Court of Claims
DecidedFebruary 20, 1970
Docket274-68
StatusPublished
Cited by55 cases

This text of 421 F.2d 723 (George W. Sturm, Doing Business as George W. Sturm Associates v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George W. Sturm, Doing Business as George W. Sturm Associates v. The United States, 421 F.2d 723, 190 Ct. Cl. 691, 1970 U.S. Ct. Cl. LEXIS 109 (cc 1970).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

DAVIS, Judge.

This is a little ease in which, once again, the Government’s contract suffers from the endemic disease of ambiguity and imprecision. The remedy, once again, is the conventional one taken from the standard legal pharmacopeia. In July 1963, George W. Sturm entered into a cost-plus-fixed-fee contract with the Maritime Administration to conduct a study on the feasibility of using plastic membranes in double-bottom tanks for ocean-going vessels. The agreement called for completion no later than six months after signing — this would bring it to January 3, 1964 — and established a limitation on expenses. This rigid ceiling was, however, made somewhat flexible by a provision, now in dispute, permitting exclusion of “all indirect expense incurred on the basis of final overhead rates * * * ” Originally, defendant was to pay Sturm a total of $12,250, comprised of work expenses of $11,449 and a fixed fee of $801. A memorandum, incorporated in the contract, set Sturm’s own direct labor charge at $150 a day, or $18.75 per hour. The contract also provided that if the contractor believed that his costs would exceed 75% of the estimated cost, during the life of the contract, he had to give 60 days written notice and a revised estimate to the Administration. The Government would not be obligated to pay such additional costs, nor would Sturm be required to continue work, in the absence of the agency’s written approval of the increase.

Early in performance, a Government accountant, attempting to calculate the anticipated overhead, concluded that various factors (irrelevant to this suit) complicated this computation to the point of rendering current overhead estimates impossible. Consequently, for some months Sturm’s invoices included direct labor costs only. In December 1963, he submitted a voucher covering overhead expenses through November 30th, and advised Maritime that he could not fulfill the contract as to time or price. He requested an extension to April 1, 1964, and a price increase of $4,000. The defendant agreed to the extension, and authorized an increase of $2,500, from $12,250 to $14,750, despite the contractor’s failure to give 60 days’ written notice. Even after this change became effective, the total current cost —$11,378 ($9,007.40 direct expenses and $2,370.64 indirect and overhead expenses) — exceeded 75% of the revised *725 estimated cost. However, the Government never complained that Sturm was delinquent with respect to the notice requirement.

The work was finally done, and the contracting officer ultimately testified that all of the costs were reasonable and allowable (putting the maximum limitation aside), that Sturm’s efforts were highly competent and valuable, and that defendant benefitted from the contract. But first there was a dispute as to overhead expenses. Defendant refused to pay certain billings, maintaining that the $150 direct labor charge included overhead. Plaintiff argued that overhead was independent of the labor expense. The issue was ultimately resolved by Maritime in plaintiff’s favor.

In March 1964, Sturm submitted his last invoice prior to completion. It listed direct costs of $10,944.17, indirect costs of $2,670.57, and a fixed fee of $801, for a total of $14,415.74 — which was a bit less than the then cost limitation of $14,750. But later, after completion, plaintiff presented a final invoice totalling $17,105.11:

Direct Labor:
Other Direct Charges:
Fee:
Overhead:
Total:
$13,042.83
488.40
$13,531.23
801.00
$14,332.23
2,772.88
$17,105.11

Defendant paid $14,750, but refused the balance of $2,355.11 on the ground that it constituted an unauthorized overrun, and was therefore not payable under the cost-limitation clause, Article 4 of the General Provisions [“General Article 4”]. Sturm appealed under the Disputes clause to the Maritime Administrator (the “head of the department”). The Hearing Examiner advised the Maritime Administrator that, on two grounds, plaintiff should receive the full amount. The examiner first held that there was no overrun, since overhead was not included in the total cost limitation by virtue of Article 4 of the Special Provisions, [“Special Article 4”], and the direct costs were less than the total estimate. In the alternative, he felt that, even if there was an over-run, the special circumstances — including the quality of plaintiff’s performance, the admitted benefit to defendant, the erroneous insistence that plaintiff’s daily charge included overhead, the lax approach to the contract requirements taken by both parties, and the impossibility of giving the contractual 60 days’ notice of the over-run — demanded that there be full payment to Sturm. The contracting officer appealed, in turn, to the Acting Maritime Administrator, who reversed the examiner. The contractor now brings the case here, and both sides have appropriately moved for summary judgment.

The controversy centers on the interaction of General Article 4 with Special Article 4. 1 It is plaintiff’s position that *726 he is entitled to all overhead costs, regardless of the expense ceiling fixed under General Article 4, since the special clause expressly excludes overhead from the limitation. On this interpretation, the direct costs, including the fixed fee, amounted to $14,332.23, well within the cost limitation. Defendant, on the other hand, urges that the purpose of the special provision is simply to enable the contractor to recover any increase between the estimated “billing” overhead and the final, actual overhead charges, and was inserted in view of the difficulty of accurately computing this cost factor in advance of or in the course of performance. Thus, defendant would allow, presumably, the difference between the $2,670.57 overhead charge in plaintiff’s March invoice, and the $2,772.88 figure for the same item in the final September billing. 2 Other than this $102.31 difference, defendant would deny all recovery since the combined direct and indirect costs exceed the new contract limit of $14,750.

The first paragraph of Special Article 4 begins by what appears to be an unqualified exclusion from the coverage of General Article 4 — “Notwithstanding the provisions of Article 4 of the General Provisions.” It then goes on to declare that the contractor is to be reimbursed “for all indirect expense incurred hereunder on the basis of final overhead rates” (emphasis added). This language may have actually been intended by the draftsman to provide for recovery (over and above the ceiling) only of the difference between the initially estimated overhead and the final actual overhead.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Govwave, LLC v. United States
Federal Claims, 2025
Per Aarsleff A/S v. United States
121 Fed. Cl. 603 (Federal Claims, 2015)
Stathis v. United States
120 Fed. Cl. 552 (Federal Claims, 2015)
Horn & Associates, Inc. v. United States
104 Fed. Cl. 121 (Federal Claims, 2012)
Chapman Law Firm, LPA v. United States
103 Fed. Cl. 28 (Federal Claims, 2012)
Oenga v. United States
96 Fed. Cl. 479 (Federal Claims, 2010)
Valley Realty Co. v. United States
96 Fed. Cl. 16 (Federal Claims, 2010)
Metropolitan Van & Storage, Inc. v. United States
92 Fed. Cl. 232 (Federal Claims, 2010)
Burchick Construction Co. v. United States
83 Fed. Cl. 12 (Federal Claims, 2008)
Bell BCI Co. v. United States
81 Fed. Cl. 617 (Federal Claims, 2008)
Veit & Co. v. United States
56 Fed. Cl. 30 (Federal Claims, 2003)
Metcalf Construction Co. v. United States
53 Fed. Cl. 617 (Federal Claims, 2002)
P.R. Burke Corp. v. United States
47 Fed. Cl. 340 (Federal Claims, 2000)
Independent Petroleum Ass'n of America v. Armstrong
91 F. Supp. 2d 117 (District of Columbia, 2000)
United States v. Schlesinger
88 F. Supp. 2d 431 (D. Maryland, 2000)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)
United International Investigative Services v. United States
40 Cont. Cas. Fed. 76,767 (Federal Claims, 1995)
McCarthy Brothers Co. v. State
47 Ill. Ct. Cl. 15 (Court of Claims of Illinois, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
421 F.2d 723, 190 Ct. Cl. 691, 1970 U.S. Ct. Cl. LEXIS 109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-w-sturm-doing-business-as-george-w-sturm-associates-v-the-united-cc-1970.