Metcalf Construction Co. v. United States

53 Fed. Cl. 617, 2002 U.S. Claims LEXIS 250, 2002 WL 31116691
CourtUnited States Court of Federal Claims
DecidedJuly 2, 2002
DocketNo. 02-55C
StatusPublished
Cited by70 cases

This text of 53 Fed. Cl. 617 (Metcalf Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metcalf Construction Co. v. United States, 53 Fed. Cl. 617, 2002 U.S. Claims LEXIS 250, 2002 WL 31116691 (uscfc 2002).

Opinion

OPINION

REGINALD W. GIBSON, Senior Judge.

INTRODUCTION

Procedural Posture

This post-award bid protest case is before the court on cross-motions for summary judgment based upon the administrative record.2 The U.S. Court of Federal Claims has jurisdiction to hear post-award bid protest cases pursuant to 28 U.S.C. § 1491(b). At the time plaintiff Metcalf filed its initial motions and complaint,3 the defendant had previously agreed to defer issuance of a Notice to Proceed with performance of the contract until April 26, 2002. A status hearing on plaintiffs initial filings was held on January 23, 2002, whereby the court adopted the parties’ jointly proposed schedule for the briefing of dispositive motions and oral argument. Additionally, the court sanctioned defendant’s modified agreement to abstain from issuing a Notice to Proceed with performance by the awardee of the contract in this case until April 26, 2002, or the date the court issues its decision on the merits, whichever is later, thereby obviating the need for a temporary restraining order.4

Consistent with the agreed upon procedural schedule, defendant filed the administrative record with this court on February 5, 2002, and following thereon both parties filed their respective dispositive motions, pursuant to RCFC 56.1, on February 26, 2002. A motion to intervene as a defendant was filed by the awardee, Lend Lease Actus (“LLA”), on February 27, 2002, and was granted on March 14, 2002. Reply briefs were filed on March 14, 2002, and oral argument on subject motions was heard on April 16, 2002.

Factual Background

Plaintiff Metcalf is a small, Historically Underutilized Business Zone (“HUBZone”) contractor,5 and defendant is the U.S. Department of the Navy (“Navy”). On or about April 5, 2001, defendant issued Request for Proposal No. N62742-00-R-1345 (“RFP” or “Solicitation”) for the design and construction of military housing at the Marine Corps Base in Kaneohe Bay, Hawaii.6 The RFP called for the design and construction of 30 military family housing units beginning in the fiscal year (“FY”) 2001, which is referred to as the Base Item or Item 0001. Two construction options were also provided for in the RFP, to wit, Option 0001, exercisable within 180 days of contract award for the construction of 158 additional units in FY 2002, and Option 0002 was exercisable within 545 days of contract award, and provided for the construction of another 24 units in FY 2003.

On or about May 24, 2001,7 three offerors submitted initial proposals in response to the RFP. Those offerors were Lend Lease Actus (“LLA”), Metcalf Construction Company, Inc. (“Metcalf’), and an Unnamed Corporation.8 The Base Item of the contract was ultimately awarded to LLA, on September 28, 2001, subject to the exercise of Options [621]*6210001 and 0002 by defendant to the benefit of the awardee. Upon notice of the award to LLA, Metcalf immediately requested a debriefing, which was held on October 2, 2001. During the debriefing, Metcalf learned that it had been eliminated from the competition solely because it had exceeded the alleged “budget ceiling” for Option 0002 in Section 1A.7 of the Solicitation.

Acting upon the discovery that it had been eliminated from award consideration, Met-calf filed a protest on October 5, 2001 with the U.S. General Accounting Office (“GAO”), forthwith, contending, inter alia, that Section 1A.7 of the Solicitation was “ambiguous at best” and that the Navy had no reasonable basis for eliminating it from award consideration. The GAO found in favor of the Navy, and thereby denied Metcalfs protest on or about January 14, 2002. Shortly thereafter, Metcalf duly invoked this court’s jurisdiction to hear its post-award bid protest claim by filing its complaint on January 18, 2002.

In both its complaint and subsequent RCFC 56.1 motion, Metcalf raised and averred a six (6)-count argument against the Navy’s conduct of the subject solicitation as follows:

COUNT I: Section 1A.7 Ambiguity Renders The Solicitation Defective
COUNT II: Bidders Were Treated Unequally
COUNT III: The SSB Improperly Downgraded Metcalfs Rating For Factor C: Small Business Utilization
COUNT IV: The Navy Employed An Unstated Evaluation Scheme And Failed To Conduct A Best Value Analysis
COUNT V: Elimination Of Metcalf Under The Circumstances Was Unreasonable
COUNT VI: The Navy Failed To Properly Apply The HUBZone Evaluation Preference.

Plaintiff also seeks permanent injunction and a declaratory judgment. In its cross-motion, the defendant, correspondingly and categorically, opposes each of plaintiffs Counts. It further denies any right of plaintiff to injunctive and/or declaratory relief.

Disposition

Having addressed each of the six Counts below, seriatim, whereupon the court considered all briefs and papers filed by the parties, oral arguments, and all record evidence including the entire administrative record, the court has found with respect to each Count as follows:

(I) Section 1A.7 is patently ambiguous rendering the solicitation defective. Plaintiffs duty to inquire was negated by defendant’s duty, on this record, to notify; the failure of which prejudiced the plaintiff. The Navy, thereby, failed to act in accordance with law.

(II) The Bidders were treated unequally, thus unfairly, when one bidder received unequivocal clarification regarding the “budget ceilings” and the other bidders did not, constituting arbitrariness and acts by defendant not in accordance with law.

(III) Although the Navy improperly evaluated plaintiffs overall rating for Factor C: Small Business Utilization due to its “NR” rating in subfactor 1, the result was harmless error.

(TV) The Navy acted arbitrarily when it ranked plaintiff third technically, as said ranking is not supported in the record.

(V) The Navy acted arbitrarily, and otherwise not in accordance with law, when it eliminated Metcalf for exceeding a line-item budget ceiling, but did not eliminate another bidder who had previously committed the identical error.

(VI) The Navy properly applied the 10% HUBZone preference for price evaluations, in accordance with law.

Based upon all of the foregoing, and as discussed in detail below, the court hereby:

(1) Grants plaintiffs motion for summary judgment as to Counts I, II, IV and V, and denies plaintiffs motion as to Counts III and VI;

(2) Denies defendant’s motion for judgment as to Counts I, II, IV and V, and grants defendant’s motion as to Counts III and VI;

[622]*622(3) Grants plaintiffs motion for permanent injunction and declaratory judgment; and

(4) Awards plaintiff its costs.

STANDARD OF REVIEW

Administrative Record

Actions brought under the court’s bid protest jurisdiction must be reviewed pursuant to the standards set forth in the APA, 5 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T Square Logistics Services Corporation v. United States
134 Fed. Cl. 550 (Federal Claims, 2017)
Shaw v. United States
131 Fed. Cl. 181 (Federal Claims, 2017)
Tetra Tech Amt v. United States
128 Fed. Cl. 169 (Federal Claims, 2016)
Per Aarsleff A/S v. United States
829 F.3d 1303 (Federal Circuit, 2016)
AvKARE, Inc. v. United States
125 Fed. Cl. 193 (Federal Claims, 2016)
Caddell Construction Company v. United States
125 Fed. Cl. 30 (Federal Claims, 2016)
Raytheon Company v. United States
809 F.3d 590 (Federal Circuit, 2015)
Per Aarsleff A/S v. United States
121 Fed. Cl. 603 (Federal Claims, 2015)
Clinicomp International, Inc. v. United States
117 Fed. Cl. 722 (Federal Claims, 2014)
Science and Management Resources, Inc. v. United States
117 Fed. Cl. 54 (Federal Claims, 2014)
Cherokee Nation Technologies, LLC v. United States
116 Fed. Cl. 636 (Federal Claims, 2014)
Am General, LLC v. United States
115 Fed. Cl. 653 (Federal Claims, 2014)
CBY Design Builders v. United States
105 Fed. Cl. 303 (Federal Claims, 2012)
HP Enterprise Services, LLC v. United States
104 Fed. Cl. 230 (Federal Claims, 2012)
Bayfirst Solutions, LLC v. United States
102 Fed. Cl. 677 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
53 Fed. Cl. 617, 2002 U.S. Claims LEXIS 250, 2002 WL 31116691, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metcalf-construction-co-v-united-states-uscfc-2002.