Raytheon Company v. United States

809 F.3d 590, 2015 U.S. App. LEXIS 18458, 2015 WL 6405390
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 23, 2015
Docket2015-5086
StatusPublished
Cited by29 cases

This text of 809 F.3d 590 (Raytheon Company v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raytheon Company v. United States, 809 F.3d 590, 2015 U.S. App. LEXIS 18458, 2015 WL 6405390 (Fed. Cir. 2015).

Opinion

TARANTO, Circuit Judge.

The United States awarded a procurement contract to one of three bidders. A General Accountability Office review process, launched by the losing bidders’ protests, then led the government to conclude, among other things, that it had given the bidders disparate information on an important subject, thereby violating a regulation that governs the bidding process. When the government reopened the bidding, the initial winning bidder protested the government’s reopening decision. The Court of Federal Claims denied the protest. Raytheon Co. v. United States, 121 Fed.Cl. 135 (2015) (public version of opinion). We affirm, concluding that the reopening decision was proper based on the disparate-information violation. We need not and do not address a second basis for the government’s decision to reassess its original award.

BACKGROUND

The United States Air Force solicited bids from private companies to supply the complex mix of equipment and services the government was seeking to acquire in order to build a new radar system. Raytheon, 121 Fed.Cl. at 138. The procurement process had several stages. Raytheon Company, Northrop Grumman Systems Corporation, and Lockheed Martin Corporation cleared early-stage hurdles, allowing them to proceed to the next stage. Id. at 140; J.A. 290. The Air Force issued to the three companies (and only them) a solicitation for proposals for Engineering and Manufacturing Development. Raytheon, 121 Fed.Cl. at 140; J.A. 336-513.

Each bidder, in supporting the price it offered, had to provide detailed estimates of the costs it would incur in performing the contract. J.A. 362-75. More specifically, the bidders all had to “identify and support their proposed cost reductions,” Raytheon, 121 Fed.Cl. at 140, ie., their means of lowering the price they would charge to the Air Force under this contract while still performing all work needed to get the job done. See id. at 163; J.A. 369-74. The Air Force made clear from the start, and repeatedly, that it would scrutinize each bidder’s estimates, including any cost-reduction means (or “affordability initiative”), to try to ensure that it did not choose a supplier whose price was unrealistic: an unrealistic price could indicate that the firm did not understand what was needed to do the job and could end up delaying completion or raising the cost of the radar system. Raytheon, 121 Fed.Cl. at 141, 143 (Air Force notice to Raytheon and Northrop: “It is imperative the Offeror substantiate and the Govern *593 ment fully understand any claimed initiative which the Offeror desires to incorporate into its proposed cost/price.”); J.A. 362, 394, 398-99, 1209, 1214, 1228, 50839-40.

Raytheon, Northrop, and Lockheed submitted bids. Raytheon, 121 Fed.Cl. at 142. The Air Force thereafter sent Evaluation Notices to Raytheon and Northrop that addressed one means of reducing the costs that had to be built into the price for the radar-system contract — namely, treatment of certain costs as independent research and development (IR & D) costs. That classification addresses research conducted by a contractor but not specifically for a particular government project. See 48 C.F.R. §§ 31.205-18, 9904.420. Although such work is contract-independent, its fruits can actually help the contractor deliver the goods and services promised in a particular contract. When that is so, the cost of work implicitly needed for a particular contract, which otherwise might have to be built into the price for that contract, may instead be treated as an IR & D cost, in which case the contractor may recover it through other means (such as, where allowed, by allocation across a wide range of government or private contracts). 48 C.F.R. § 31.205-18. The result is a “cost reduction” for the particular contract without compromising the contractor’s ability to fulfill its promises in that contract.

In this case, the Air Force, citing a Federal Acquisition Regulation (FAR) provision, stated in its initial notices to Raytheon and Northrop on the subject: “In accordance with (IAW) FAR 31.205-18 and 10 USC 2320 [sic], any cost claimed or considered to be IR & D or a capital investment shall not be allowable as indirect charges for work implicitly required for performance (necessary to perform the contract) or explicitly required to be done by the terms of the contract.” J.A. 1210, 1215, quoted in Raytheon, 121 Fed.Cl. at 143. “In other words,” as the Court of Federal Claims said, “the contractors would not be permitted to use IR & D costs to reduce their costs of performing the ... contract if those costs were implicitly or explicitly required for contract performance.” Raytheon, 121 Fed.Cl. at 163-64 (emphasis added).

In response, Northrop did not take issue with the agency’s statement precluding treatment of the cost of “implicitly required” work as an IR & D cost. See id. at 143. The Court of Federal Claims found that Northrop “raised no objections to the Air Force’s statements regarding the allowability of IR & D costs.” Id. at 165. 1 Raytheon, in contrast, did object. Raytheon told the agency that its statement was contrary to ATK Thiokol, Inc. v. *594 United States, 598 F.3d 1329, 1334-35 (Fed.Cir.2010), which, Raytheon said, “held that research and development costs are allowable as IR & D costs unless specifically required by the contract.” J.A. 1218, quoted in Raytheon, 121 Fed.Cl. at 143.

What occurred thereafter is undisputed in the respects relevant to our decision. The Air Force changed its view: “the Air Force’s understanding changed to conform to Raytheon’s interpretation; the [Evaluation Notices] that the Air Force had sent to Raytheon and Northrop no longer reflected its position on the allowability of IR & D costs related to implicit contract requirements.” Raytheon, 121 Fed.Cl. at 147; id. at 164; J.A. 1837-39. The Air Force communicated its new view to Ray-theon, in substance if not in words, by accepting Raytheon’s treatment of certain costs as IR & D costs. In contrast, the Air Force never communicated its new view to Northrop — whose last communication on the subject from the government therefore remained the earlier, contrary view. “Thus, as far as Northrop was aware, the Air Force would not accept IR & D cost reductions for work implicitly required for contract performance.” Raytheon, 121 Fed.Cl. at 164; see id. at 165, 166.

When the bidders later submitted their final proposals, Raytheon “proposed IR & D cost reductions” of a certain amount, id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
809 F.3d 590, 2015 U.S. App. LEXIS 18458, 2015 WL 6405390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raytheon-company-v-united-states-cafc-2015.