E.W. Bliss Co. v. United States

40 Cont. Cas. Fed. 76,769, 33 Fed. Cl. 123, 1995 U.S. Claims LEXIS 69, 1995 WL 218040
CourtUnited States Court of Federal Claims
DecidedMarch 31, 1995
DocketNo. 94-371C
StatusPublished
Cited by27 cases

This text of 40 Cont. Cas. Fed. 76,769 (E.W. Bliss Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.W. Bliss Co. v. United States, 40 Cont. Cas. Fed. 76,769, 33 Fed. Cl. 123, 1995 U.S. Claims LEXIS 69, 1995 WL 218040 (uscfc 1995).

Opinion

OPINION

MILLER, Judge.

This suit to recover costs incurred in preparing technical and cost proposals is before the court after argument on cross-motions for summary judgment.2 The issue for resolution is whether the Government’s award of a contract to an offeror other than plaintiff was arbitrary and capricious because, inter alia, the procuring agency accepted an allegedly non-responsive technical proposal.

FACTS

The following facts are undisputed, unless otherwise noted. On July 28,1993, the United States Department of the Treasury, Unit[126]*126ed States Mint (the “Mint”), issued Request for Proposals Solicitation No. USM 93-14 (the “RFP”) for Contract No. TM 93-1073, which contemplated the refurbishment and remanufacture of coin presses, as a small business set-aside. The solicitation determined the feasibility of refurbishing and re-manufacturing the Mint’s aging coin presses at a reasonable price. The goal of the proposed press remanufacture program was to provide coining presses that met or exceeded the original factory specifications, while incorporating the latest industrial standards, mechanical components, governmental safety requirements, and advanced control technology-

The RFP required each potential offeror to submit both cost and technical proposals. The cost proposals were to include six pricing schedules requiring fixed-price estimates for nine equipment and related repair service contract line item numbers (“CLINS”). Potential offerors were initially to provide prices for a base year and two option years for coin presses located in Philadelphia, Pennsylvania; and Denver, Colorado. The base year initially was established to run from the date of the contract award to September 30, 1993. The duration of the first option year was October 1, 1993, through September 30,1994. The second option year began October 1, 1994, and ended on September 30, 1995.

The RFP further required the contractor to provide all labor, engineering, materials, tools, and equipment necessary to pickup, rebuild, remanufacture, test, deliver, and reinstall the existing coining presses. In addition to required repairs, potential offerors were encouraged to provide recommendations that might improve the operation of the coin presses or otherwise benefit the coin production process. The RFP called for the award of an indefinite-quantity contract. Pursuant to this contract, performance by the contractor was authorized only by orders issued in accordance with the contract’s Ordering Clause. The contract incorporated Federal Acquisition Regulation (“FAR”) § 52.216-18, 48 C.F.R. § 52.216-18 (1984). The Ordering Clause stated that any services furnished under the contract should be ordered by the issuance of delivery orders.

The RFP provided that the contract would be awarded to the responsible offeror whose conforming offer would be most advantageous to the Government. However, the Mint could accept other than the lowest offer and award the contract on the basis of initial offers received, without discussion. Barring a qualified offer, the RFP authorized the Mint to accept any item or group of items of an offer and permitted an award on any item for a lesser quantity than the quantity offered.

The RFP specified five technical evaluation criteria to be considered in reviewing, evaluating, and scoring each technical proposal received. These factors were, in descending order of importance: 1) technical and performance features; 2) similar design/manufacturing experience; 3) quality control; 4) customer references; and 5) delivery schedule. A technical evaluation panel (the “TEP”), was to be set up to evaluate the proposals in order to provide both quantitative and qualitative descriptions of each technical proposal. The RFP also advised that each cost proposal would be reviewed and analyzed for cost reasonableness. With respect to cost proposals, the RFP stated that “[a]s offers become technically equal the importance of cost will increase____”

On July 28, 1993, the Mint issued Amendment No. 0003 to all four offerors, including E.W. Bliss Co. (“plaintiff’) and Pressmasters of Delaware Valley, Inc., (“Pressmasters”). The stated purpose of this amendment was to amend the RFP, as follows:

1. Delete pages 2 through 11 and replace with revised pages 2 through 11.
2. Delete pages 18, 34, and 76. Replace with revised pages 18, 34, and 76.

The amendment also stated that “[a]ll terms and conditions remain unchanged.” Amendment No. 0003 also included a replacement page for page 40 of the RFP. This replacement page contained a change regarding FAR § 52.216-18, the contract’s Ordering Clause. The amended Ordering Clause read: “Ordering (APR 1984): (a) Contract award through September 30, 1994.” Each offeror [127]*127signed and returned Amendment 0003 to the Mint by September 14, 1993.

On August 6, 1993, the Mint conducted a pre-proposal conference in Philadelphia. Representatives of the Mint, plaintiff, Press-masters, and other prospective offerors attended the conference. In response to questions raised at the conference, the Mint issued Amendment No. 0001 to the RFP. The purpose of the amendment was to relay information generated by the question-and-answer session. The amendment contains the following exchange:

Q. How will we be able to determine if the crank shaft [sic] is good without disassembling the presses?
A. The proposal should address a new crankshaft to insure consistencies between the new remanufactured presses. All old components removed from the presses shall be returned to the Mint for use as spare parts.
A subsequent amendment was issued that is not germane to the case.

The Mint received four proposals by August 30,1993, the due date. These proposals were forwarded to the six-member TEP for review. On September 1 and 2, 1993, the TEP analyzed and scored the four technical proposals submitted in response to the RFP. These scores were set forth on individual scoring sheets. The evaluation factors were weighted, as follows: 1) technical and performance features (50 points); 2) similar design/manufacturing experience (25 points); 3) quality control system (12.5 points); 4) customer references (6.25 points); 5) delivery schedule (3.125 points). The total number of points possible was 100. Plaintiff and Press-masters’ scores follow:

Evaluator Criteria Plaintiff Pressmasters
Adler Technical features Similar design Quality control Customer reference Delivery schedule [redacted material]
Claybrook Technical features Similar design Quality control Customer references Delivery schedule
Gecys Technical features Similar design Quality control Customer references Delivery schedule [redacted material]
Felix Technical features Similar design Quality control Customer references Delivery schedule
Smith Technical features Similar design Quality control Customer references Delivery schedule
Wolff Technical features Similar design Quality control Customer references Delivery schedule

[128]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Caddell Construction Co., Inc. v. United States
111 Fed. Cl. 49 (Federal Claims, 2013)
One Largo Metro, Llc v. United States
109 Fed. Cl. 39 (Federal Claims, 2013)
Glenn Defense Marine (Asia), PTE Ltd. v. United States
97 Fed. Cl. 568 (Federal Claims, 2011)
SP Systems, Inc. v. United States
86 Fed. Cl. 1 (Federal Claims, 2009)
Software Engineering Services, Corp. v. United States
85 Fed. Cl. 547 (Federal Claims, 2009)
Grunley Walsh International, LLC v. United States
78 Fed. Cl. 35 (Federal Claims, 2007)
NVT Technologies, Inc. v. United States
73 Fed. Cl. 459 (Federal Claims, 2006)
United Enterprise & Associates v. United States
70 Fed. Cl. 1 (Federal Claims, 2006)
MTB Group, Inc. v. United States
65 Fed. Cl. 516 (Federal Claims, 2005)
J.C.N. Construction Co. v. United States
60 Fed. Cl. 400 (Federal Claims, 2004)
Hawaiian Dredging Construction Co. v. United States
59 Fed. Cl. 305 (Federal Claims, 2004)
Colorado Construction Corp. v. United States
57 Fed. Cl. 648 (Federal Claims, 2003)
Metcalf Construction Co. v. United States
53 Fed. Cl. 617 (Federal Claims, 2002)
JWK International Corp. v. United States
52 Fed. Cl. 650 (Federal Claims, 2002)
Worldtravelservice v. United States
49 Fed. Cl. 431 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
40 Cont. Cas. Fed. 76,769, 33 Fed. Cl. 123, 1995 U.S. Claims LEXIS 69, 1995 WL 218040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ew-bliss-co-v-united-states-uscfc-1995.