Mason v. United States

615 F.2d 1343, 27 Cont. Cas. Fed. 80,204, 222 Ct. Cl. 436, 1980 U.S. Ct. Cl. LEXIS 58
CourtUnited States Court of Claims
DecidedFebruary 20, 1980
DocketNo. 116-77
StatusPublished
Cited by68 cases

This text of 615 F.2d 1343 (Mason v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mason v. United States, 615 F.2d 1343, 27 Cont. Cas. Fed. 80,204, 222 Ct. Cl. 436, 1980 U.S. Ct. Cl. LEXIS 58 (cc 1980).

Opinion

KASHIWA, Judge,

delivered the opinion of the court:

The plaintiff, Sommers Construction Company,1 seeks damages for the Government’s alleged breach of contract. [440]*440The case is before the court on plaintiffs motion for partial summary judgment and defendant’s cross motion for summary judgment. For the reasons stated below, we hold for defendant.

Sommers Construction Company is a maintenance contracting firm whose principal place of business is Theodore, Alabama. During the years 1974, 1975, and 1976, the General Services Administration [G.S.A.], after competitive bidding, awarded eight "term contracts” to plaintiff. Each term contract was in effect for a one-year period, covered a fixed geographical area, and contained descriptions of a number of different construction type projects — painting, plastering, partition relocation, etc. — with a fixed price per project. Under each such contract, when plaintiff performed any of the described work within the one-year term and described geographical area, it would be paid this predetermined price.

All eight term contracts contained a provision entitled "Section 3, Special Conditions.” This was a part of the bid specifications sent to all prospective bidders on these contracts and was incorporated by reference and became a part of each contract awarded to plaintiff. Section 3, Special Conditions, provided in relevant part as follows:

3-1 GENERAL
a. Purpose of Contract: The U. S. Government proposes to enter into a term contract whereby partitions, doors, hardware, painting, electrical work and other necessary materials, labor and equipment for a complete installation will be furnished and installed by a single contractor at the unit price established * * * in quantities and heights as may be required from time to time during the term of the contract * * *. The work ordered under this contract will be performed in any or all Government-owned and Government-leased buildings within [a specified geographical area].2
* * * * *
3-3 QUANTITIES OF WORK
a. Bidders are hereby cautioned that quantities shown and listed on the bid form as the bid evaluation estimated quantities are not guaranteed minimums or máximums and in no way have any connection with any [441]*441required quantities or intend any scope of work. These quantities are for bid evaluation purposes only.3
b. The minimum quantity of work which will be required under this contract * * * will not total less than five thousand dollars ($5,000).4
* * * * *

Two of the eight contracts covered the area in and around Nashville, Tennessee. These contained, in Section 3, Special Conditions, an additional clause, hereinafter referred to as the "Nashville clause,” which stated that "Any award under this [contract] will not prohibit or restrict the Government from having any work items performed by Government employees or by others.” None of plaintiffs other contracts contained this language.

During the life of, and within the geographical area covered by, each contract, defendant had others perform work similar or identical to that described in plaintiffs contracts. Defendant also ordered at least $5,000 of work under each of these term contracts.

Plaintiff places primary emphasis on the Purpose of Contract clause. In its view, while the Government had no obligation to have any of the described work performed, if the Government decided to have any of such work done in "any or all Government-owned and Government-leased buildings” within the applicable areas of the respective contracts, this clause gave plaintiff, as the "single contractor,” the exclusive right to perform this work. That is, a single contractor was to do all this work in all these buildings. Plaintiff further argues that the Guaranteed Minimum Quantity clause was only included to ensure mutuality of obligation, and that its presence in the contracts is totally consistent with the exclusive right created by the Purpose of Contract clause. In addition, in plaintiffs view, the Nashville clause when read in conjunction with the Purpose of Contract clause creates an ambiguity which, since the Government drafted the contracts, should be construed against the defendant under the doctrine of contra proferentem, leaving intact the exclusive performance rights created by the Purpose of Contract clauses in the Nashville contracts.

[442]*442Plaintiff, accordingly, contends that with respect to each of its contracts, it had the exclusive contractual right to perform the work which defendant in fact awarded to others. The Government has thus breached each term contract, entitling plaintiff to damages. Plaintiff also asserts that it had a corresponding legal obligation to perform all such work. Plaintiff, however, refuses to characterize its contracts as requirements contracts.

A careful examination of plaintiffs argument convinces us that, stripped to its legal essentials, plaintiff does contend it held requirements contracts. We must ignore the label plaintiff attaches to its contracts and see what legal rights it claims it received.

The projects enumerated in these contracts were all construction type work. Such work cannot be performed now, then stored away for future use. For the Government to order more work than it needed done would therefore make no sense, and in interpreting a contract, we should keep in mind that "[t]he Government is no more devoid of minimal business sense than [are] contractors.” Franklin Co. v. United States, 180 Ct. Cl. 666, 672, 381 F. 2d 416, 419 (1967). Logically then, regardless of who actually performed the described work, the Government would order such work done only if it needed it done. Plaintiffs argument that for the one-year term of each contract it had the exclusive right and the legal obligation to fill all of defendant’s orders for work of the type described in its contracts thus reduces to an argument that during the life of each contract it had the exclusive right and legal obligation to satisfy defendant’s needs for such work. This, however, is the definition of a requirements contract. As we said in Media Press, Inc. v. United States, "[a] requirements contract has been defined as a contract in which the purchaser agrees to buy all of its needs of a specified material from a particular supplier, and the supplier agrees, in turn, to fill all of the purchaser’s needs during the period of the contract.” 215 Ct. Cl. 985, 986, 566 F. 2d 1192 (1977).

Under these contracts, plaintiff had to provide the services at a predetermined, fixed price. This does not undercut our characterization of plaintiffs argument— fixed price terms are totally consistent with requirements [443]*443contracts. Shader Contractors, Inc. v. United States, 149 Ct. Cl. 535, 540, 276 F. 2d 1, 4 (1960).

Defendant insists that, with respect to each contract, all the clauses in Section 3, Special Conditions, should be read as a whole, and when so viewed, these are all indefinite quantities contracts with a $5,000 minimum purchase amount per contract. Thus, its only obligation to plaintiff was to order at least $5,000 of work under each contract.5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sage Acquisitions LLC v. Hud
119 F.4th 973 (Federal Circuit, 2024)
Davidson Oil Company v. City of Albuquerque
108 F.4th 1226 (Tenth Circuit, 2024)
Heartland Energy Partners LLC
Armed Services Board of Contract Appeals, 2022
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165 (Federal Claims, 2015)
Patriot Pride Jewelry, LLC
Armed Services Board of Contract Appeals, 2014
NCLN20, Inc. v. United States
99 Fed. Cl. 734 (Federal Claims, 2011)
Horn v. United States
98 Fed. Cl. 500 (Federal Claims, 2011)
Digital Technologies, Inc. v. United States
89 Fed. Cl. 711 (Federal Claims, 2009)
XO Communications, LLC v. Level 3 Communications, Inc.
948 A.2d 1111 (Court of Chancery of Delaware, 2007)
Unfoldment, Inc. v. District of Columbia Contract Appeals Board
909 A.2d 204 (District of Columbia Court of Appeals, 2006)
International Data Products Corp. v. United States
64 Fed. Cl. 642 (Federal Claims, 2005)
United Medical Supply Co. v. United States
63 Fed. Cl. 430 (Federal Claims, 2005)
Precision Pine & Timber, Inc. v. United States
63 Fed. Cl. 122 (Federal Claims, 2004)
In Re Anchor Glass Container Corp.
297 B.R. 887 (M.D. Florida, 2003)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
615 F.2d 1343, 27 Cont. Cas. Fed. 80,204, 222 Ct. Cl. 436, 1980 U.S. Ct. Cl. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mason-v-united-states-cc-1980.