Shader Contractors, Inc. And Citizens National Bank of Orlando, Assignee v. United States

276 F.2d 1, 149 Ct. Cl. 535, 1960 U.S. Ct. Cl. LEXIS 186
CourtUnited States Court of Claims
DecidedApril 6, 1960
Docket186-58
StatusPublished
Cited by35 cases

This text of 276 F.2d 1 (Shader Contractors, Inc. And Citizens National Bank of Orlando, Assignee v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shader Contractors, Inc. And Citizens National Bank of Orlando, Assignee v. United States, 276 F.2d 1, 149 Ct. Cl. 535, 1960 U.S. Ct. Cl. LEXIS 186 (cc 1960).

Opinion

JONES, Chief Judge.

This case comes to us with no substantial factual dispute between the parties. The main question to be answered is whether the contract in suit is one in which the quantity of the services to be performed by plaintiff is measured by the defendant’s requirements or one in which the quantity is fixed and definite.

The plaintiff contractor was awarded a contract by the Department of the Army on June 3, 1955, requiring it to furnish certain services at Camp Hale, Colorado, during the fiscal year which extended from July 1, 1955, to June 30, 1956. Three different types of services were to be supplied: the collection and disposal of garbage and rubbish and the operation of the sanitary fill and post incinerator; the unloading and stockpiling of coal; and the hauling of coal to certain locations within the camp. The schedule accompanying the invitation referred to these services as Items 1, 2, and 3. It set the prices per ton of material handled at $8.93, $1.50, and $2.50, respectively, and the total quantities of each material to be handled at 4,000, 5,500, and 5,500 tons, respectively. The column which set out the quantities for each item had the word “Estimated” typed in.

The special provisions of the contract provided that the contract was to extend from July 1, 1955, to June 30, 1956, unless sooner terminated (Special Provision 1) and that its contemplated scope was the performance of all work in connection with the collection and disposal of ash, trash, edible and non-edible garbage, operation of the sanitary fill, post incinerator, and coal handling. (Special Provision 2.)

Special Provision 8 authorized termination of the contract by the contracting officer whenever he might determine that such action was in the defendant’s best interest and it set up procedures for the settlement of claims which might arise out of any such termination.

In addition, these special provisions appeared:

“5. Etimated Quantities: Quantities of the various items listed herein are based upon the best information obtainable and represent the estimated and not the actual amounts for which supplies and/or services may be required during the contract period. The fact that specific quantities cannot be determined and given in this instrument shall not relieve the Government of its obligation to order from the Contractor all the supplies and/or services, which, in the judgment of the Con *3 tracting Officer, may be needed, and shall not in any case relieve the Contractor of his obligation to fill all orders for supplies and/or services which he may be required to furnish during the contract period. Supplies and/or services for the estimated quantities which are not ordered for delivery prior to expiration of the contract period shall be automatically cancelled.
“9. Estimated Annual Quantities: The Government estimates the quantity of refuse to be collected and disposed of per annum as 4,000 tons, and the estimated quantity of coal to be handled per annum as 5,500 tons.”

Standard Form 32 (Nov. 1949 edition) was the basis of the contract. We find under the heading “General Provisions (Supply Contract)” the following:

“4. Variation in Quantity
“No variation in the quantity of any item called for by this contract will be accepted unless such variation has been caused by conditions of loading, shipping, or packing, or allowances in manufacturing processes, and then only to the extent, if any, specified elsewhere in this contract.”

The specifications of the work to be done are divided into two parts. Part I is a statement of the work generally restating the scope of the entire contract. Part II consists of four sections: collection and disposal of rubbish and garbage; sanitary fill; post incinerator; and coal handling. The first section contains the following specification:

“1-07 Quantities of Work to be Done: The qualities of work to be performed are outlined in the Invitation to Bid. The quantity is estimated only and will be used in formulating and comparing bids. The quantity may vary from 75% to 125% of the figure. The contractor will be required to complete the work specified herein at the contract unit price regardless of the quantity of the work.”

None of the other three sections of Part II of the specifications has a similar provision as to percentages of the estimated quantities. The only other contract provision of significance is Specification 1-05, which prescribes how often garbage and refuse would be collected from the various types of buildings at the camp.

Plaintiff contractor committed men and equipment to this project which thereafter were unavailable for other projects because of the remote location of Camp Hale (over 100 miles from Denver, high in the Rocky Mountains). Plaintiff provided hauling services for the defendant throughout the contract period in the following amounts, for which it has been paid: garbage and trash, 2,313.088 tons; unloading coal, 4,430.05 tons; 1 delivery of coal, 2,511.15 tons.

No termination notice was ever given and, at the expiration of the contract period, the plaintiff had been fully paid for work actually done. In August 1956, Shader notified the contracting officer that it desired to file a termination claim for that portion of the estimated services which had not been ordered by defendant. The contracting officer’s denial was appealed to the Armed Services Board of Contract Appeals which decided that the contract was a requirements contract and, since there was no showing of bad faith on the part of the Government, no recovery could be allowed. In this action, the plaintiff makes no allegation of bad faith on the part of the defendant.

During the life of the contract, Shader assigned the proceeds to plaintiff Orlando Bank in consideration for moneys advanced, and the defendant was given no *4 tice of the assignment. Shader is indebted to Orlando on this and other contracts.

Plaintiff Shader’s position in this action is based on its interpretation of the contract as one for the amount of hauling services provided for in the contract estimates (give or take a reasonable variance). The defendant does not see the contract as one guarantying any specific quantity of services; rather it insists that it is nothing more nor less than a requirements contract which it has performed in good faith. The contractor claims that the contracting officer acted arbitrarily in denying it the opportunity to file a termination claim. It asserts that the defendant’s action in automatically canceling the portion of the estimated services not required amounted to a termination for the convenience of the Government which entitled the contractor to the benefits of the termination clause.

The law concerning the requirements contract, and its analogue, the output contract, is of comparatively recent development. A requirements contract is simply one in which one party promises to supply all the specific goods or services which the other party may need during a certain period at an agreed price. The other party implicitly promises that he will obtain his required goods or services from the first party exclusively.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Short Bros. PLC v. United States
65 Fed. Cl. 695 (Federal Claims, 2005)
Flink/Vulcan v. United States
63 Fed. Cl. 292 (Federal Claims, 2004)
Padilla v. United States
58 Fed. Cl. 585 (Federal Claims, 2003)
Datalect Computer Services, Inc. v. United States
56 Fed. Cl. 178 (Federal Claims, 2003)
Hi-Shear Technology Corp. v. United States
53 Fed. Cl. 420 (Federal Claims, 2002)
J. Cooper & Associates, Inc. v. United States
53 Fed. Cl. 8 (Federal Claims, 2002)
Educators Associates, Inc. v. United States
42 Cont. Cas. Fed. 77,376 (Federal Claims, 1998)
Datalect Computer Services, Ltd. v. United States
42 Cont. Cas. Fed. 77,243 (Federal Claims, 1997)
Jones v. University of Pittsburgh
D. New Hampshire, 1995
Ceredo Mortuary Chapel, Inc. v. United States
39 Cont. Cas. Fed. 76,573 (Federal Claims, 1993)
A-Transport Northwest Co. v. United States
38 Cont. Cas. Fed. 76,440 (Federal Claims, 1992)
Vanguard Security Inc. v. United States
20 Cl. Ct. 90 (Court of Claims, 1990)
Biener GmbH v. United States
35 Cont. Cas. Fed. 75,701 (Court of Claims, 1989)
Torncello v. United States
681 F.2d 756 (Court of Claims, 1982)
Alyeska Pipeline Service Co. v. O'KELLEY
645 P.2d 767 (Alaska Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
276 F.2d 1, 149 Ct. Cl. 535, 1960 U.S. Ct. Cl. LEXIS 186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shader-contractors-inc-and-citizens-national-bank-of-orlando-assignee-v-cc-1960.