Gemsco, Inc. v. United States

115 Ct. Cl. 209, 1950 U.S. Ct. Cl. LEXIS 54, 1950 WL 5028
CourtUnited States Court of Claims
DecidedJanuary 3, 1950
DocketNo. 47361
StatusPublished
Cited by7 cases

This text of 115 Ct. Cl. 209 (Gemsco, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gemsco, Inc. v. United States, 115 Ct. Cl. 209, 1950 U.S. Ct. Cl. LEXIS 54, 1950 WL 5028 (cc 1950).

Opinion

Howell, Judge,

delivered the opinion of the court:

Plaintiff sues to recover damages sustained by reason of the Government’s breach of a contract for the manufacture of a quantity of metal Nurse Corps collar devices for the Navy Department.

On August 9, 1948, this Court entered an order herein limiting the hearing in the first instance to the issue of whether defendant is liable, leaving for further consideration the question of damages. Therefore, the sole question to be decided is whether there has been a breach of contract for which defendant is liable.

On October 14, 1943, the Navy Purchasing Office issued a Request for Tender requesting bids for the furnishing and sale to the Navy Department of certain insignia and devices for naval uniforms, including as Item 58 of the listed items, 25,000 pairs of “Devices, Collar, U. S. Navy, Nurse Corps, Metal, Pin-on, rights and lefts.” This Request for Tender contained a list of the insignia to be furnished, accompanied by a column headed “Quantity” at the top of which was inserted the note “(More or less).”1 Below this note was a statement of the quantity of each device for which bids were requested. At the top of the column listing the articles to be furnished, there appeared the following statement:

To be delivered all transportation charges paid to the Supply Officer in Command, Naval Clothing Depot, 29th St. & 3rd Ave., Brooklyn, N. Y., WITHIN 10 days, after receipt of first order; bulk orders WITHIN 30 days; additional orders to be delivered at the same rate, but to [223]*223begin after completion of preceding orders, in such, quantities of each item as may be required during the period beginning with date of contract and ending June 30, 1944.
NOTE: NO DELIVERIES SHALL BE MADE UNDER THIS CONTRACT UNLESS SPECIFICALLY ORDERED.

At the foot of this column there appeared this paragraph entitled “Indefinite Quantities”:

The uncertain and varying needs of the Navy (Government) make it impossible to determine the quantity or quantities of the articles required during the contemplated period of the contract. Estimated quantities are stated for information only. It is mutually understood and agreed that the Government will order and the contractor will deliver the quantities of the kinds of articles and materials described in the specifications that, in the judgment of the ordering officer, may be required during the contract period, except as may be otherwise indicated in the tender. These supplies will be ordered in such quantities for delivery in such forms and to such places provided for by the contract as the needs of the Naval Service require. Tenders made with the proviso that the total deliveries will not exceed a certain specified quantity will be considered, but the right is reserved to reject any tender which provides that the Government shall guarantee to take any definite quantity. [Italics supplied.]

On November 6,1943, plaintiff submitted a bid for the furnishing of various insignia and devices listed in the request for tender and included therein a tentative bid for the 25,000 Nurse Corps devices listed as Item 58. Plaintiff’s tentative bid on this item was based upon gold plating which differed slightly from the specifications stated in the request for tender.

On December 15, 1943, plaintiff entered into a contract with the defendant for furnishing nine of the items listed in the request for tender but not including Item 58, the metal Nurse Corps collar device. This contract incorporated all of the provisions of the request for tender quoted above, including Article 13 “Changes” which will be referred to later in this opinion.

[224]*224On February 9, 1944, tbe parties entered into a further agreement, designated “Extension Amendment No. 1” which was an addition and amendment to the contract of December 15,1943, and which provided as follows:

Contractor is hereby authorized, upon acceptance of this amendment as directed below, to proceed with the following extension of the above numbered contracts, or order, in addition to the quantities or services previously contracted for, at the price and subject to the terms and conditions hereinbelow specified:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Media Press, Inc.
566 F.2d 1192 (Court of Claims, 1977)
Coastal States Petrochemical Co. v. United States
559 F.2d 1 (Court of Claims, 1977)
Harvey Ward Locke v. United States
283 F.2d 521 (Court of Claims, 1960)
Ready-Mix Concrete Company v. United States
158 F. Supp. 571 (Court of Claims, 1958)
Walters v. United States
130 F. Supp. 360 (Court of Claims, 1955)
Boomer v. Abbett
263 P.2d 476 (California Court of Appeal, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
115 Ct. Cl. 209, 1950 U.S. Ct. Cl. LEXIS 54, 1950 WL 5028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gemsco-inc-v-united-states-cc-1950.