Short Bros. PLC v. United States

65 Fed. Cl. 695, 2005 U.S. Claims LEXIS 160, 2005 WL 1395028
CourtUnited States Court of Federal Claims
DecidedJune 10, 2005
DocketNo. 98-894C
StatusPublished
Cited by15 cases

This text of 65 Fed. Cl. 695 (Short Bros. PLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Short Bros. PLC v. United States, 65 Fed. Cl. 695, 2005 U.S. Claims LEXIS 160, 2005 WL 1395028 (uscfc 2005).

Opinion

OPINION

CHRISTINE O.C. MILLER, Judge.

This case involves the acquisition for the U.S. Army National Guard of a commercial aircraft converted to a military aircraft, the C-2BB +, under a sole-source fixed-price contract. The finished product is quite the success; the C-23B+ is in service today, and some of the military aircraft are with our nation’s servicemembers in Iraq. The success did not come without cost. Defendant agreed to pay approximately $150 million for twenty-eight aircraft. Plaintiff sued in the United States Court of Federal Claims to recover cost overruns that, as of trial, plaintiff calculated at $58.9 million.

Trial demonstrated that plaintiff, a sophisticated original manufacturer and maintenance provider of aircraft, undertook a major modification effort that it had never performed before, underestimated the effort that the scope of work required, grossly underestimated hours and costs, and was hobbled by its production subcontractor. For its part, the military underestimated the effort that the scope of work required and exhibited questionable candor concerning the risks and costs that plaintiff faced.

Plaintiff produced and delivered twenty-eight aircraft based on what turned out to be a wholly inadequate government-approved proposal. Although the proposal period represented a singularly bilateral coordination effort on the part of the contractor and the military, plaintiff recorded, for the conversion alone, direct labor hours of 1,124,603 against the 253,531 estimated hours that formed the basis of its proposal. Where the fault for this discrepancy lay is the issue before the court.

PROCEDURAL HISTORY

Short Brothers, PLC (“plaintiff’), filed this lawsuit against the United States in the United States Court of Federal Claims on November 25, 1998. Short Brothers, PLC v. United States, No. 98-894C. The complaint sought relief on the following nine counts: two counts for illegal fixed-price contract; impossibility; commercial impracticability; failure to disclose superior knowledge; mutual mistake; defective government-furnished property; breach of implied duties of good faith, cooperation, and fairness; and unjust enrichment. The United States answered, and after completion of two years’ discovery, defendant moved for summary judgment on March 13, 2001. Briefing on defendant’s motion was completed in September 2001, and, after a ruling had not issued by October 2002, the parties filed motions for leave to file supplemental authority. The supplemental briefing was added to the record as of February 26, 2003, and the case was reassigned to the undersigned on March 10, 2004. As of that date, the summary judgment motion still was pending.

On March 18, 2004, an order entered that granted in part and denied in part defendant’s motion for summary judgment and scheduled trial. Short Brothers, PLC v. United States, No. 98-894C (Fed.Cl. Mar.18, 2004) (unpubl.) (the “Summary Judgment Order”). Surviving the Summary Judgment Order were plaintiffs claims for commercial impracticability, failure to disclose superior knowledge, mutual mistake, and defective government-furnished property. Plaintiffs [696]*696claims for illegal contract and impossibility were adjudicated in defendant’s favor. The parties proceeded to trial beginning in January 2005.1

OVERVIEW OF THE PROCUREMENT

In 1993 the United States Government, through the U.S. Army Aviation and Troop Command (“ATCOM”), entered into Contract [697]*697No. DAAJ09-93-C-0656 with plaintiff for the procurement of twenty military aircraft with an option for an additional ten; U.S. Army National Guard (the “Guard”) was the customer. The aircraft was to be known as the C-23B + ,2 a modified version of older, commercial aircraft previously manufactured by plaintiff known as the SD3-60. While a C-23B + aircraft had never been manufactured prior to this contract, its procurement stemmed from the Guard’s need for an additional number of aircraft that plaintiff, the original equipment manufacturer, had discontinued, known as the C-23B, or C-23B Sherpa. The C-23B + , or the C-23B+ Sherpa, was to augment the Guard’s fleet of sixteen C-23B’s; its mission was to perform a medical evacuation role in support of the Army National Guard Aviation Classification Repair Activity Deport System and Theater Defense Force Airlift requirements. The C-23B+ also had to be capable of airdropping cargo and paratroopers.

The critical procurement events, to be described in detail, begin not with the issuance of the Request for Proposal (the “RFP”), but with the parties’ development of the Statement of Work (the “SOW”), a document incorporated into the contract that set forth the requirements for contract performance. SOW development occurred predominantly during 1992.

The Government issued the RFP on January 13, 1993, which was to be sole-sourced through plaintiff. Plaintiff submitted its first formal proposal on February 22, 1993, and, after a series of audits and revisions, submitted final updates on May 24, 1993. The parties conducted contract negotiations during August 1993, and the Government awarded Contract No. DAAJ09-93-C-0656 to plaintiff on September 30,1993.

The contract called for major modification work3 to the second-hand SD3-60 aircraft, which, as part of its work under the contract, plaintiff would select and induct into the program. The conversion of the commercial SD3-60 aircraft, an analog to the C-23B, into a military C-23B+ encompassed discrete tasks required to meet the performance specifications set forth in the contract, including, but not limited to, the following major items: remove the tail of the SD3-60 and replace with a new twin fin tail with a rear ramp; remove a 36-inch section of the fuselage to shorten the aircraft, rejoin the sections and replace all electrical systems; install improved avionics systems; modify the cockpit; install new seats and cargo equipment; add a role beam to support a paratrooper- and cargo handling- air drop performance specification; and install thirty-seven items of new electronics.

The converted aircraft would replicate most, if not all, of the functions of the C-23B, other than performance. The Guard did not require a typical 30-year life of an airplane, flying at 2,500 hours. As described by Ian Heaton, plaintiff’s Director of New Pro-grammes, who was involved in developing the milestones for the project, “[W]e were trying to produce both a lookalike and an operationally similar airplane so that a crewman could step ... into a C-23B + from a C-23B and effectively not really notice the difference.” Deposition of Ian Heaton, Aug. 1-2, 2000, at 34 (“Heaton I”). “The [SD]3-60 to C-23B conversion required the supplying' of what was essentially 20% or whatever of a new aircraft that we had manufactured before into an old airplane[.]” Id. at 42.

[698]*698FACTS

I. BACKGROUND

1. Plaintiff and its businesses

Short Brothers, PLC (“plaintiff’), is a Public Limited Company organized and existing under the laws of Northern Ireland, with its principal place of business in Belfast, Northern Ireland. It is a subsidiary of Bombardier Aerospace (“Bombardier”), which acquired plaintiff in 1989, after which plaintiff took on the name Bombardier Shorts. Prior to the Bombardier acquisition, plaintiff was a government-owned aerospace company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pontchartrain Partners, LLC
Armed Services Board of Contract Appeals, 2025
Ingham Regional Medical Center v. United States
126 Fed. Cl. 1 (Federal Claims, 2016)
Copar Pumice Company, Inc. v. United States
112 Fed. Cl. 515 (Federal Claims, 2013)
Lakeshore Engineering Services, Inc. v. United States
110 Fed. Cl. 230 (Federal Claims, 2013)
Horn & Associates, Inc. v. United States
104 Fed. Cl. 121 (Federal Claims, 2012)
United Partition Systems, Inc. v. United States
90 Fed. Cl. 74 (Federal Claims, 2009)
Englewood Terrace Ltd. Partnership v. United States
79 Fed. Cl. 516 (Federal Claims, 2007)
ConocoPhillips v. United States
73 Fed. Cl. 46 (Federal Claims, 2006)
La Gloria Oil & Gas Co. v. United States
72 Fed. Cl. 544 (Federal Claims, 2006)
Stockton East Water District v. United States
70 Fed. Cl. 515 (Federal Claims, 2006)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
65 Fed. Cl. 695, 2005 U.S. Claims LEXIS 160, 2005 WL 1395028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/short-bros-plc-v-united-states-uscfc-2005.