Tombigbee Constructors v. The United States

420 F.2d 1037, 190 Ct. Cl. 615, 1970 U.S. Ct. Cl. LEXIS 106
CourtUnited States Court of Claims
DecidedJanuary 23, 1970
Docket194-65
StatusPublished
Cited by22 cases

This text of 420 F.2d 1037 (Tombigbee Constructors v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tombigbee Constructors v. The United States, 420 F.2d 1037, 190 Ct. Cl. 615, 1970 U.S. Ct. Cl. LEXIS 106 (cc 1970).

Opinion

ON ASSIGNMENT OF ERRORS

PER CURIAM:

This case was referred to Trial Commissioner David Schwartz with directions to prepare and file his opinion on the issues raised by the Assignment of Errors * of the parties. The commissioner has done so in an opinion and report filed on April 1, 1969, wherein such facts as are necessary to the opinion are set forth. Requests for review by the court of the commissioner’s opinion, report and recommended conclusion were filed by both parties. The case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the commissioner’s opinion, report and recommended conclusion, with minor modifications, it hereby adopts the same, as modified, as the basis for its judgment in this case as hereinafter set forth. Therefore, both plaintiff’s and defendant’s Assignments of Errors by the Armed Services Board of Contract Appeals are denied and the petition and counterclaims are dismissed.

Commissioner Schwartz’s opinion, with minor modifications by the court, is as follows:

Plaintiff contractor was unsuccessful before the Armed Services Board of Contract Appeals in two claims for an equitable adjustment for costs increased by reason of alleged changed conditions in the course of the performance of the contract by the subcontractor. Plaintiff now brings suit on these two claims for the benefit of the subcontractor, to review and set aside the findings of the Board and, alternatively, for breach of contract.

*1039 Plaintiff was successful in two other claims, on which the hearing was limited to the question of entitlement. After negotiations between the parties as to the amounts involved, the government paid plaintiff the sum of $14,805 on one of these claims and $65,308 on the other. The government, alleging error by the Board in its rulings on each of these claims, has counterclaimed for the sums paid. Plaintiff in its reply to the counterclaim pleads a denial and an accord and satisfaction.

In this court an order was entered, on the government’s unopposed motion in pretrial proceedings, that a trial de novo should not be held, and that .the proceedings be limited to a review of the administrative record before the Board pursuant to the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322. The claims of error by the Board presented here are made by assignment of errors in the Board’s decision, a procedure predating that provided in Chapter XIV of the Rules of the court for review of cases under the Wunderlich Act.

The Claim, for the Consequences of the Flooded Borrow Pit

Plaintiff contracted with the Air Force in March 1957 to construct runways and taxiways at Columbus Air Force Base in Mississippi. The contract contained an item of approximately 500,-000 cubic yards to be excavated and back filled with borrow, at 50 cents per cubic yard. Soon after the work started, there was discovered a subgrade layer of clay, unsuitable for taxiways. It was agreed that the clay had not been shown in the boring logs and charts furnished by the government to the contractor, and that it could not have been anticipated. The parties further agreed that the clay should be removed and backfilled, and this was done by the plaintiff. • The parties disagreed, however, on whether the work was routine excavation and back-fill, to be done at the contract rate of 50 cents per cubic yard, or should be paid for at a higher rate.

The government finally recognized that the work on the layer of clay was an extra, calling for a higher price, and a new price was negotiated and agreed upon, at a meeting in Mobile on November 19, 1957.

Modification No. 6 to the contract, embodying the agreement for the extra, was signed on the next day. On November 19, however, the borrow pit at the Base, designated in the contract papers as a source of borrow for backfilling, was unbeknownst to the parties flooded by heavy rain which fell on that day. The flood and the unavailability of an alternative source of borrow, plaintiff contends, caused a delay in the work through the winter, until May of 1958. Plaintiff claims the amount of its costs allegedly increased in consequence of the delay.

The payments specified by Modification No. 6 have been made and are not in suit. Also not in suit is the additional time, by reason of the flood, required to complete the work. The contractor received an appropriate extension of time. The claim concerns other costs, allegedly increased by virtue of the flood, such as those of equipment left idle from November to May and the costs of enlarging the borrow pit in an unflooded direction — which was eventually done — to make available the needed quantity of borrow material.

The Board found that Modification No. 6 gave plaintiff full payment for the extra work connected with the layer of clay; that while the Modification did not cover the costs resulting from the flood in the pit, such expenses resulted not from the existence and discovery of the clay but from rain, an act of God not the fault of the government, for which plaintiff was entitled only to the extension of time which it received.

Plaintiff contends .that the Board acted without substantial evidence and unlawfully in rejecting the claim for increased costs. Plaintiff claims that the government’s failure to disclose the layer of clay was a breach of contract leading *1040 to delayed performance, for which the damages are the costs of the delayed performance beyond the period of winter rains and floods. The damages were caused, it is said, first, by the government’s refusal, for a time, to recognize that the clay was a changed condition and that the work was an extra, followed, when the government did recognize the changed condition and .the extra, by a flood in the designated borrow pit, the only one available. The flood, it is said, delayed the work through the winter months of another year.

In response, the government urges, as the Board found, that Modification No. 6 was an agreement by plaintiff to accept 94 cents per cubic yard as complete payment for the work required by the excavation of the clay and the necessary backfill, and thus for the entire claim based on the changed condition and the extra. Plaintiff counters that Modification No. 6, itself an agreement, is voidable for a material mutual mistake of the parties as to a factual premise on which it was negotiated and signed. The Modification is said to have been based, by both parties, on the premise of the continuing availability of borrow, necessary for the job, in the pit designated in the contract documents. Since the pit was on the day of the negotiations flooded, and no alternative source of borrow was available, Modification No. 6 falls. More specifically, plaintiff argues that had the flood been known to the parties on that day, they would not have agreed to the 94 cent rate but would have agreed to another, higher rate, presumable including plaintiff’s increased costs, or they would not have reached any agreement, until the increased costs became known.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Betance Enterprises, Inc.
Armed Services Board of Contract Appeals, 2023
Short Bros. PLC v. United States
65 Fed. Cl. 695 (Federal Claims, 2005)
Fru-Con Construction Corp. v. United States
43 Cont. Cas. Fed. 77,449 (Federal Claims, 1999)
Willamette Crushing Co. v. State
932 P.2d 1350 (Court of Appeals of Arizona, 1997)
Bataco Industries, Inc. v. United States
39 Cont. Cas. Fed. 76,569 (Federal Claims, 1993)
Spirit Leveling Contractors v. United States
36 Cont. Cas. Fed. 75,770 (Court of Claims, 1989)
Dynamics Corp. of America v. United States
35 Cont. Cas. Fed. 75,663 (Court of Claims, 1989)
Norair Engineering Corp. v. United States
666 F.2d 546 (Court of Claims, 1981)
Turnkey Enterprises, Inc. v. United States
597 F.2d 750 (Court of Claims, 1979)
Pauley Petroleum Inc. v. United States
591 F.2d 1308 (Court of Claims, 1979)
Dynalectron Corp. v. United States
518 F.2d 594 (Court of Claims, 1975)
Foster Wheeler Corp. v. United States
513 F.2d 588 (Court of Claims, 1975)
Stock & Grove, Inc. v. United States
493 F.2d 629 (Court of Claims, 1974)
Pacific Architects & Engineers Inc. v. United States
491 F.2d 734 (Court of Claims, 1974)
J. A. Maurer, Inc. v. United States
485 F.2d 588 (Court of Claims, 1973)
Burnett Electronics Lab., Inc. v. United States
479 F.2d 1329 (Court of Claims, 1973)
Centre Manufacturing Co.
24 Cont. Cas. Fed. 82,153 (Court of Claims, 1973)
Sperry Rand Corp. v. United States
475 F.2d 1168 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
420 F.2d 1037, 190 Ct. Cl. 615, 1970 U.S. Ct. Cl. LEXIS 106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tombigbee-constructors-v-the-united-states-cc-1970.